Blue Cross v. McDevitt & Street Co.

360 S.E.2d 825, 234 Va. 191, 4 Va. Law Rep. 785, 1987 Va. LEXIS 228
CourtSupreme Court of Virginia
DecidedOctober 9, 1987
DocketRecord 840870
StatusPublished
Cited by20 cases

This text of 360 S.E.2d 825 (Blue Cross v. McDevitt & Street Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Blue Cross v. McDevitt & Street Co., 360 S.E.2d 825, 234 Va. 191, 4 Va. Law Rep. 785, 1987 Va. LEXIS 228 (Va. 1987).

Opinion

POFF, J.,

delivered the opinion of the Court.

We granted this appeal to consider whether the trial court erred in ruling that an owner of a building contractually had waived its rights to recover from the general contractor and the architect damages for a loss covered by a property insurance policy.

Blue Cross of Southwestern Virginia and Blue Shield of Southwestern Virginia (collectively, the owner) engaged the partners in Hayes, Seay, Mattern & Mattern (the architect) to design, and McDevitt & Street Company (the contractor) to construct, the owner’s headquarters building in Roanoke. The three parties memorialized their agreements in form contracts published by the American Institute of Architects (AIA), each of which was modified in part. Insofar as relevant to this appeal, paragraph 11.4 of the architect’s contract provided:

*193 11.4 The Owner and the Architect waive all rights against each other and against the contractors, consultants, agents and employees of the other for damages covered by any property insurance during construction .... The Owner and the Architect each shall require appropriate similar waivers from their contractors, consultants and agents.

Both the contractor’s and the architect’s contracts with the owner incorporated by reference the provisions of AIA Document A201 entitled “General Conditions of the Contract for Construction”. For purposes of interpretation, paragraph 1.1.3 of that document defined the term “the Work” as follows:

The Work comprises the completed construction required by the Contract Documents and includes all labor necessary to produce such construction, and all materials and equipment incorporated or to be incorporated in such construction.

The term thus defined appears in two paragraphs of the general conditions that are crucial to the determination of the waiver issue framed on appeal:

11.3.1 Unless otherwise provided, the Owner shall purchase and maintain property insurance upon the entire Work at the site to the full insurable value thereof. This insurance shall include the interests of the Owner, the Contractor, Subcontractors and Sub-subcontractors in the Work and shall insure against the perils of fire and extended coverage and shall include “all risk” insurance for physical loss or damage including, without duplication of coverage, theft, vandalism and malicious mischief.
11.3.6 The Owner and Contractor waive all rights against (1) each other and the Subcontractors, Sub-subcontractors, agents and employees each of the other, and (2) the Architect and separate contractors, if any, and their subcontractors, sub-subcontractors, agents and employees, for damages caused by fire or other perils to the extent covered by insurance obtained pursuant to this Paragraph 11.3 or any other property insurance applicable to the Work .... The Owner *194 or the Contractor, as appropriate, shall require of the Architect, separate contractors, Subcontractors and Sub-subcontractors by appropriate agreements . . . similar waivers each in favor of all other parties ....

(Emphasis added.)

The parties agree that the building was substantially complete on September 2, 1981 and that, pursuant to a temporary certificate of occupancy, the owner occupied and began using the building on September 7, 1981. On January 11, 1982, the water in a pipe in the third-floor ceiling sprinkler system froze and the pipe burst. As appears from the parties’ stipulation of facts, “[t]he ‘Work’ to be performed . . . had been substantially, although not fully, completed at the time of the freezing and bursting”.

Pursuant to its commitment under the contract documents, the owner had acquired two policies of property insurance on the building. One, a policy containing a builder’s risk endorsement, was in effect from December 1, 1979 to October 1, 1981. Coverage under the other began October 1, 1981 and was in effect on and after January 11, 1982. The loss was one covered by the latter policy, and the insurer paid the owner $109,116.54 in satisfaction of its claim.

The City of Roanoke issued a final certificate of occupancy dated February 10, 1982. The contractor submitted an application March 17, 1983 for final payment for the “Period from: 2-28-83 to: 3-17-83”. The owner made final payment by check dated April 8, 1983.

In a motion for judgment filed in the name of the owner, the plaintiff claimed damages in contract and in tort against the contractor, the architect, and others. 1 The principal defendants filed special pleas of waiver and estoppel, and the parties submitted a stipulation of facts and memoranda of law. The stipulation contained no reference to extrinsic evidence of contractual intent. Construing the provisions of the contract documents and applying them to the facts at bar, the trial court ruled that the owner con *195 tractually had waived its rights against the contractor and the architect and dismissed the motion for judgment.

As framed on appeal, the dispositive issue is whether the trial court misconstrued and misapplied the contract documents. Preliminarily, the owner complains that the language is ambiguous, that “[t]he architect and contractor should be considered the drafters of the documents because they submitted the forms”, and that the trial court should have applied the rule that ambiguous contracts must be construed strictly against the author.

We have applied the rule the owner invokes against “the party who supplied . . . printed forms” when “the language as a whole arguably supports two antithetical interpretations.” Bank of Martinsville v. Ford, 219 Va. 942, 946, 252 S.E.2d 354, 357 (1979). The rule applies, however, only when the contract is ambiguous on its face. When, as here, the language is plain and unambiguous, this Court must give effect to the plain meaning of that language. Amos v. Coffey, 228 Va. 88, 92, 320 S.E.2d 335, 337 (1984); accord Berry v. Klinger, 225 Va. 201, 208, 300 S.E.2d 792, 796 (1983).

On appeal, the owner contends that the waiver provision in paragraph 11.4 of the architect’s contract applies only “during construction”; that the loss in issue “occurred after substantial completion and therefore not ‘during construction’ ”; and that “the insurance and the waiver must lapse simultaneously at substantial completion and occupancy.” The owner reasons that “[t] he risk of casualty damage ... is on the contractor until the date of substantial completion, at which time the risk shifts to the owner”, that the contractor then has no insurable interest in the project, and, consequently, that the only claim contemplated by the waiver provision was a claim covered by “builder’s risk insurance”. 2

Free access — add to your briefcase to read the full text and ask questions with AI

Related

John L. Mattingly Construction Co. v. Hartford Underwriters Insurance
999 A.2d 1066 (Court of Appeals of Maryland, 2010)
Williams v. CDP, INC.
713 F. Supp. 2d 556 (E.D. Virginia, 2010)
Travelers Property Casualty Co. v. Premier Project Management Group, L.L.C.
78 Va. Cir. 315 (Hanover County Circuit Court, 2009)
Tiger Fibers, LLC v. Aspen Specialty Insurance
594 F. Supp. 2d 630 (E.D. Virginia, 2009)
A v. v. Iparadigms, Ltd. Liability Co.
544 F. Supp. 2d 473 (E.D. Virginia, 2008)
TX. C.C., Inc. v. Wilson/Barnes General Contractors, Inc.
233 S.W.3d 562 (Court of Appeals of Texas, 2007)
Holt v. Nedry
64 Va. Cir. 373 (Fairfax County Circuit Court, 2004)
Gray Ins. Co. v. Old Tyme Builders, Inc.
878 So. 2d 603 (Louisiana Court of Appeal, 2004)
Regency Photo & Video, Inc. v. America Online, Inc.
214 F. Supp. 2d 568 (E.D. Virginia, 2002)
Nationwide Insurance v. Dudley
55 Va. Cir. 446 (Norfolk County Circuit Court, 2000)
Gordonsville Energy, L.P. v. Virginia Electric & Power Co.
512 S.E.2d 811 (Supreme Court of Virginia, 1999)
Town of Silverton v. Phoenix Heat Source System, Inc.
948 P.2d 9 (Colorado Court of Appeals, 1997)
In Re Lewis
212 B.R. 827 (E.D. Virginia, 1997)
Schneider v. Continental Casualty Company
989 F.2d 728 (Fourth Circuit, 1993)
Schneider v. Continental Casualty Co.
989 F.2d 728 (Fourth Circuit, 1993)
State v. US Fidelity and Guar. Co.
577 So. 2d 1037 (Louisiana Court of Appeal, 1991)
Paramount Termite Control Co. v. Rector
380 S.E.2d 922 (Supreme Court of Virginia, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
360 S.E.2d 825, 234 Va. 191, 4 Va. Law Rep. 785, 1987 Va. LEXIS 228, Counsel Stack Legal Research, https://law.counselstack.com/opinion/blue-cross-v-mcdevitt-street-co-va-1987.