Blount International, Ltd. v. Schuylkill Energy Resources Inc.

124 F.R.D. 523, 1989 U.S. Dist. LEXIS 4255, 1989 WL 21578
CourtDistrict Court, D. Massachusetts
DecidedApril 19, 1989
DocketCiv. A. No. M.B.D. 88-729
StatusPublished
Cited by1 cases

This text of 124 F.R.D. 523 (Blount International, Ltd. v. Schuylkill Energy Resources Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Massachusetts primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Blount International, Ltd. v. Schuylkill Energy Resources Inc., 124 F.R.D. 523, 1989 U.S. Dist. LEXIS 4255, 1989 WL 21578 (D. Mass. 1989).

Opinion

MEMORANDUM AND ORDER ON DEFENDANTS’ OBJECTIONS TO MAGISTRATE’S ORDER OF MARCH 13, 1989

MAZZONE, District Judge.

After review of the entire record presented to me, I conclude the Magistrate’s Order of March 13, 1989 is entirely proper and will be affirmed.

Although I sit in review from a more removed position, the shrill, unflattering and pejorative presentations came through clearly to me. In the face of that atmosphere, the Magistrate delivered a thorough and well-reasoned Memorandum and Order, ruling properly on the merits of the discovery dispute, and entirely consistently with the Supreme Court’s teaching in Oppenheimer Fund v. Sanders, 437 U.S. 340, 341, 352-3, 98 S.Ct. 2380, 2389, 2390, 57 L.Ed.2d 253 (1978). Moreover, the Magistrate went beyond the call of duty and parsed the record in an attempt to guide and limit the discovery in the future to permissible bounds.

In every respect, the Magistrate acted properly, reasonably, and in accordance with established law in this Circuit. Discovery was properly limited to those areas which affect the claims and defenses of these parties, as outlined in the Order.

The Order of the Magistrate is affirmed. The request for attorneys’ fees is denied.

SO ORDERED.

MEMORANDUM AND ORDER ON MOTION OF NON-PARTY BANK OF NEW ENGLAND, N.A. AND MICHAEL A. McCABE FOR A PROTECTIVE ORDER (# 17A)

ROBERT B. COLLINGS, United States Magistrate.

Blount International, Ltd. (hereinafter, “Blount”) filed suit against Schuylkill Energy Resources, Inc. (hereinafter, “SER”) in the United States District Court for the Eastern District of Pennsylvania.

The Amended Complaint alleges that on December 29, 1986, Blount and SER entered into a contract pursuant to which Blount, for a stated price, would construct an electrical cogeneration facility for SER in Schuylkill County, Pennsylvania. In Count I, Blount alleges that SER has failed to pay for change orders and thereby materially breached the contract; it seeks a declaratory judgment that SER is in material breach of the contract thereby allowing Blount to suspend work on the project until payment is made. In Count II, Blount alleges that SER failed to make payment for additional work which Blount had to do because of the subsurface conditions at the site about which SER knew but did not inform Blount. Blount also alleges that SER had in its possession mine maps which would have revealed the subsurface problems but SER did not disclose them prior to the signing of the contract. Blount claims that after the maps were disclosed, it was necessary to relocate the plant and revise the foundation design at additional costs which SER refused to pay. Accordingly, Blount seeks a declaratory judgment that the contract was induced by fraud and that Blount is entitled to recission of the contract and payment on the basis of quantum meruit. Count III seeks damages for breach of contract in the failure to pay for additional work due to the subsurface conditions encountered. Count IV seeks damages for breach of contract for a specific change order, i.e. the addition of a redundant culm feed system. Count V seeks damages for breach of contract in the failure to pay for the other change orders. Count VI purports to state a claim against two other corporations, Reading Anthracite Company and Reading Anthracite Coal Company, on a theory of misrepresentation in their failure, as parents of SER and previous owners of the land on which the cogeneration plant is being built, to disclose the mining maps and to furnish accurate information about the site. Count VIII is a claim for punitive damages.

SER’s Answer pleads as affirmative defenses that Blount’s claims are barred due to a failure of consideration, “as a result of the equitable doctrine of estoppel,” “as a [525]*525result of the equitable doctrine of laches,” “as a result of plaintiff’s material breaches of the contract,” “as a result of waiver,” and “because plaintiff has frustrated, hindered and prevented SER from having the project constructed in a timely manner and in accordance with the contract.” Lastly, as an affirmative defense, it is pleaded that “[p]laintiff’s claims against SER for compensation for work performed in addition to that required by the contract are barred because plaintiff failed to provide SER with notice of such claims in accordance with the contract.

As reported by counsel, the District Judge has declined to issue any declaratory judgment in advance of a trial on the other claims in the Amended Complaint. Discovery has commenced and will continue through the summer of 1990.

As part of discovery, SER caused subpoenae to be issued in the District of Massachusetts and to be served upon the Bank of New England and two of its officers, Michael A. McCabe and James A. Croyle, commanding them to appear for their depositions. Neither the Bank of New England nor any of its officers are named in the Amended Complaint or the Answer as parties or otherwise. However, the Bank of New England together with other banks (“the bank group”) provided SER the financing for the construction of the cogeneration plant.

The deposition of Mr. McCabe went forward on November 10 and 11,1988 but was not completed. The deposition of Mr. Croyle went forward on January 10 and 11, 1989. So far as appears, the deposition of Mr. Croyle was completed. However, SER sought to continue the deposition of Mr. McCabe. Contending that the subject matter of the depositions went beyond permissible bounds and that the depositions are being conducted for improper purposes, the Bank of New England filed a motion for protective order pursuant to Rule 26(c), Fed.R.Civ.P., in the District of Massachusetts on January 27, 1989 seeking a protective order:

(1) limiting the scope of [SER’s] examination of Mr. McCabe and any other [Bank of New England] officer or employee to matters which are relevant to the subject matter of the Pennsylvania federal court action ... out of which this miscellaneous action arises; and
(2) directing [SER] to refrain from any further questioning of Mr. McCabe or any other [Bank of New England] officer or employee concerning defendants’ threatened, but as yet unfiled, suit against [the Bank of New England] based on uncharged and factually unsupported allegations of “lender liability” and/or “conspiracy.”

Motion of Non-Party Bank of New England, N.A. and Michael A. McCabe for a Protective Order (# 17A) at pp. 1-2.

At the time the motion was filed, the undersigned was presiding over a three-week civil jury trial and was unable to hear the motion until the trial was completed. Rather than await a hearing on the motion, counsel agreed to proceed with the continuation of Mr. McCabe’s deposition on February 1 and 2, 1989 but not as to the questioning which was the subject of the motion for a protective order.

Matters did not proceed smoothly on February 1 and 2. As a result, on February 5, 1989, the Bank of New England and Mr. McCabe requested further relief pursuant to Rule 30(d), Fed.R.Civ.P. as follows:

[B]ecause of the oppressive, repetitive and irrelevant nature of [SER’s counsel’s] examination of Mr. McCabe, [the Bank of New England] and Mr. McCabe request that defendants’ examination of Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Addamax Corp. v. Open Software Foundation, Inc.
148 F.R.D. 462 (D. Massachusetts, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
124 F.R.D. 523, 1989 U.S. Dist. LEXIS 4255, 1989 WL 21578, Counsel Stack Legal Research, https://law.counselstack.com/opinion/blount-international-ltd-v-schuylkill-energy-resources-inc-mad-1989.