Blair v. Corby

37 Mo. 313
Supreme Court of Missouri·Decided February 15, 1866·Published·Cited by 3 cases

Opinion

Holmes, Judge,

delivered the opinion of the court.

The petition is based upon a written contract for the build-ding of a portion of the western division of the Hannibal and St. Joseph Railroad, and the plaintiff claims to recover of the defendant a balance of fifteen hundred dollars for what he alleges to be due for extra work done under said contract, but over and above what was therein specially provided for. The plaintiff had contracted to construct and complete the clearing, grubbing, grading and masonry, and to furnish all requisite materials for the completion of the work, according to the specifications annexed, and he was to receive, in full compensation therefor, certain fixed prices for the kinds of work specified, among which were for embankment or for excavation, twenty cents per cubic yard; and in the specifications, excavation was divided into five classes: first, earth excavation, including all materials except hard-pan,” and quicksand, and rock; second, “ hard-pan;” third, quicksand; fourth, loose rock; and fifth, solid rock; but no fixed prices were named in the contract for any of these divisions but for “ excavation.”

It was stipulated in the contract that the determination of the measurements and calculations of the engineer of the [316] respective quantities and classifications of such excavation, should be final and conclusive. Another provision was, that when rock, or “ hard-pan,” was placed in embankments, and had been paid for as shell, the price of embankment should be deducted therefrom ; that is, it was not to be paid for both as excavation and embankment, but the excess of the price of excavating such material, only, was to be paid for. The plaintiff sought to recover for several items, as extra work, which, it was conceded, were not embraced within the terms of the written contract, and also for the following items, which are the main subjects of dispute in the case, namely: chopping and clearing, at sixteen stations, indurated earth, and excavation of foundations wasted.

The answer denied all the material allegations of the petition, and averred, by way of defence, that the plaintiff had been fully paid the whole amount due him, and that the matters in issue had been adjudicated on a former trial, in another suit.

The contract was read in evidence by the plaintiff in support of his petition, and he offered to prove (among other things) in substance, that it was expressly agreed, in making the contract, that it should only apply to ordinary earth or excavation, and not to indurated earth ; that the terms used in the contract, concerning embankment and excavations, were intended and understood to mean common earth excavation ; that, after it was discovered that there was indurated earth to be excavated, there was an agreement entered into between the parties as to the amount to be paid for excavating such indurated earth, and the terms of the agreement, and the prices of different kinds of excavation; and that, at the time of making the contract, it was understood by the parties that there was no excavation but that of common earth to be done on that part of the road which was embraced within the contract; that the word “ excavation,” as used in contracts among railroad men, is understood to mean common earth, and not indurated earth; that at the time of the contract it was not contemplated by the parties [317] that there was any indurated earth on that part of the road which was embraced within the contract; and that after indurated earth was discovered within that portion of the road, the defendant paid the plaintiff an extra price for such excavation, and agreed to pay extra for such work. All this evidence was excluded. Some depositions were also excluded, but the foregoing is supposed to cover the points to be decided.

Free access — add to your briefcase to read the full text and ask questions with AI

Blair v. Corby, 37 Mo. 313 (Mo. 1866).

37 Mo. 313 (Blair v. Corby) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Davis v. Commissioners of Sewerage
13 F. Supp. 672 (W.D. Kentucky, 1936)
Moran Bolt & Nut Manufacturing Co. v. St. Louis Car Co.
109 S.W. 47 (Supreme Court of Missouri, 1908)
Gaunt, Maupin & Co. v. C. H. Pries & Co.
21 Mo. App. 540 (Missouri Court of Appeals, 1886)