Blackstone Valley Electric Co. v. Stone & Webster, Inc.

867 F. Supp. 73, 1994 U.S. Dist. LEXIS 16213, 1994 WL 643182
CourtDistrict Court, D. Massachusetts
DecidedNovember 7, 1994
DocketCiv. A. 94-10178-JLT
StatusPublished
Cited by6 cases

This text of 867 F. Supp. 73 (Blackstone Valley Electric Co. v. Stone & Webster, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Massachusetts primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Blackstone Valley Electric Co. v. Stone & Webster, Inc., 867 F. Supp. 73, 1994 U.S. Dist. LEXIS 16213, 1994 WL 643182 (D. Mass. 1994).

Opinion

MEMORANDUM

TAURO, Chief Judge.

In 1984, the Massachusetts Department of Environmental Quality Engineering (now the Department of Environmental Protection), determined that a site in Attleboro Massachusetts had been contaminated by industrial waste. Acting pursuant to CERCLA and the Massachusetts state law equivalent, M.G.L. c. 21E, the Commonwealth of Massachusetts commenced a cleanup operation at the site. Three years later, the Commonwealth brought suit against the Blackstone Valley Electric Company (“BVE”), alleging that the industrial waste found at the site was generated by Blackstone Valley Gas & Electric (“BVG&E”), a predecessor of BVE, and seeking to recover the costs incurred in the cleanup. That case, Commonwealth v. Blackstone Valley Electric Co., C.A. No. 87- *75 1799-T, was decided on November 7, 1994, and is reported at 867 F.Supp. 78. 1

BVE now brings the present action against several defendants, arguing that any costs assigned to it should be borne by several parties in accordance to their fault. One of these defendants, the Valley Gas Company, has now moved the court for summary judgment.

I.

BACKGROUND

The waste that gave rise to the cleanup operations at the center of this dispute originated at a gas manufacturing plant in Paw-tucket, Rhode Island (“the Tidewater plant”) between the late 1800’s and the mid 1950’s. At all relevant times in this period, the Tidewater plant was owned and operated by BVG & E or one of its corporate predecessors.

The corporate reorganization that lies at the heart of this dispute dates back to the late 1950’s, when, in response to a SEC divestiture order, BVG & E was forced to divest itself of its gas division. This divestiture occurred in several stages over the next decade. In 1956, the Rhode Island Legislature, by special charter, created the Valley Gas Company as a subsidiary of BVG & E. In this capacity, Valley Gas became responsible for all of BVG & E’s gas operations. In 1961, BVG & E’s gas-related assets were formally transferred to Valley Gas pursuant to a series of sales agreements (“the agreements”). In 1964, the divestiture was finalized with BVG & E’s sale of all remaining Valley Gas stock. One year later, in 1965, the Rhode Island General Assembly amended BVG & E’s charter, renaming the company Blackstone Valley Electric Company.

Valley Gas’ motion to dismiss is based upon the terms of the 1961 sales agreements between BVG & E and Valley Gas. 2 Valley Gas first argues that, by the terms of the 1961 agreements, it never assumed any of BVG & E’s environmental liabilities. Second, Valley Gas argues that any liability transferred in spite of the agreement was shifted back onto BVG & E by a contemporaneous indemnification agreement. Because the need to reach the second issue is contingent upon the resolution of the first, the court begins by examining the transferability, by contract or otherwise, of CERCLA liability.

II.

Analysis

A. The Transfer of CERCLA Liability.

Valley Gas argues that the divestiture agreement between Valley and BVG & E precludes the transfer of CERCLA liability. In John S. Boyd Co. v. Boston Gas Co., 992 F.2d 401 (1st Cir.1993), the First Circuit examined the transfer of CERCLA liability in the context of the doctrine of successor liability. Looking to Massachusetts law for the substantive rule of decision, the court held that CERCLA liability would not be transferred by contract without language in the agreement “broad enough to allow [the court] to say that the parties intended to transfer either contingent environmental liability, or all liability.” Boyd, 992 F.2d at 406.

Applying the Boyd standard to this case, it is clear that the agreements in question demonstrate no intent to transfer contingent environmental liability. As well, the agreements contain no general transfer of liability. In fact, the contract expressly limits Valley’s assumptions of liability to specific items ref *76 erenced in BVG & E’s books. 3 If the court were to look only at the agreement between the parties in determining the scope of liability assumed by Valley, it would conclude that Valley never assumed any of BVG & E’s environmental liabilities.

Boyd defines the conditions in which CERCLA liability may be transferred by agreement. It does not, however, hold that CERCLA liability may be transferred only by agreement. BVE properly notes that the agreement to assume liability discussed in Boyd is merely one of several ways for a buyer to assume the liabilities of a seller. In this respect, the First Circuit in Boyd noted:

In Dayton v. Peck, Stow and Wilcox Co., 739 F.2d 690, 692 (1st Cir.1984), we identified four situations in which successor liability is appropriate: when the buyer agrees to assume liability; when a consolidation or de facto merger occurs; when the buyer is merely a continuation of the seller; and when the transaction is a fraud to escape liability.
Boyd, 992 F.2d at 408.

Recognizing that the First Circuit’s decision in Boyd precludes the contractual transfer of environmental liabilities in this case, BVE argues that Valley Gas’ liability arises out Valley’s continuation of BVG & E’s gas business, independently of the agreements signed in 1961.

The interpretation of Boyd advanced by BVE limits a private party’s ability to allocate environmental liability by contract. A successor business that acts as a “mere continuation” of a predecessor will inherit environmental liabilities despite explicit contractual provisions to the contrary. This conclusion is in keeping with the principle, underlined in Boyd, that although parties may “allocate responsibility among themselves by contract,” a party cannot “escape liability by means of a contract with another party.” Boyd, 992 F.2d at 405. See Fisher Dev. Co. v. Boise Cascade Corp., 37 F.3d 104, 108 (3rd Cir., 1994).

The doctrine of “mere continuation” has been unanimously embraced in the CERCLA context. Courts have generally held that the “mere continuation” theory advances CERC-LA’s purpose of obtaining rapid recovery from “those responsible for problems caused by the disposal of chemical poisons.” Boyd, 992 F.2d at 405. State contact law that allowed a responsible party to escape liability by way of merger or consolidation could frustrate this Congressional objective. Smith Land & Improvement Corp. v. Celotex Corp.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Halliburton Energy Services, Inc. v. NL Industries
648 F. Supp. 2d 840 (S.D. Texas, 2009)
JSB Industries, Inc. v. Nexus Payroll Services, Inc.
463 F. Supp. 2d 103 (D. Massachusetts, 2006)
Heinrich Ex Rel. Heinrich v. Sweet
49 F. Supp. 2d 27 (D. Massachusetts, 1999)
Atlas Tack Corp. v. Crosby
671 N.E.2d 954 (Massachusetts Appeals Court, 1996)
United States v. Hardy
916 F. Supp. 1385 (W.D. Kentucky, 1996)
National Gypsum Co. v. Continental Brands Corp.
895 F. Supp. 328 (D. Massachusetts, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
867 F. Supp. 73, 1994 U.S. Dist. LEXIS 16213, 1994 WL 643182, Counsel Stack Legal Research, https://law.counselstack.com/opinion/blackstone-valley-electric-co-v-stone-webster-inc-mad-1994.