Blackstaff Engineering Co. v. Commissioners of Sewerage

145 S.W. 152, 147 Ky. 629, 1912 Ky. LEXIS 310
CourtCourt of Appeals of Kentucky
DecidedMarch 16, 1912
StatusPublished
Cited by1 cases

This text of 145 S.W. 152 (Blackstaff Engineering Co. v. Commissioners of Sewerage) is published on Counsel Stack Legal Research, covering Court of Appeals of Kentucky primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Blackstaff Engineering Co. v. Commissioners of Sewerage, 145 S.W. 152, 147 Ky. 629, 1912 Ky. LEXIS 310 (Ky. Ct. App. 1912).

Opinion

Opinion of the Court by

William Bogers Clay, Commissioner—

Affirming.

Tke Commissioners of Sewerage of Louisville advertised for bids for the construction of Section F, Bear-grass Intercepter Sewer. Upon the original letting there were four bidders, each of whom bid a given price per item on the items indicated in the pamphlet entitled “Information for Bidders.” The bids, based upon the price per item multiplied by the quantities estimated by the engineer, were as follows:

Blackstaff Engineering Company........$34,226.22

Henry Bickel Company ................. 45,337.60

O’Connell ..................... 60,020.55

McCracken ............................ 65,506.33

While the above figures are shown as an aggregate, a lump bid was not made by any contractor; but the final [630]*630payment depended wholly upon the quantity of each item that was used. The Blackstaff Engineering Company, being the lowest bidder, was awarded the contract, which was. formally executed on January 31, 1910. The Fidelity and Deposit Company, of Maryland, became its surety for the faithful performance of the work, its liability, however, being limited to $8,000.

On March 1, 1910, the Blackstaff Engineering Company commenced work by opening up a shaft just north of Kentucky street.- A little later it opened a trench toward the southern part of Section F. It continued work until July 16, 1910, when it threw up the contract. Thereupon the Commissioners of Sewerage advertised for new bids and re-let to Henry Bickel Company, the lowest bidder, at a loss alleged to amount to $20,353.33.

This action was brought by the Commissioners of Sewerage against the Blackstaff Engineering Company to recover the sum of $20,353.33, the difference between the Blackstaff Engineering Company’s bid on the estimated quantities, and the bid of the Henry Bickel Company, excluding the amount of work already done by the Blackstaff Engineering Company. The Fidelity and Deposit Company of Maryland was made a party defendant, and recovery asked against it as surety on the bond of the Blackstaff Engineering Company. The defendants resisted recovery on the ground that the contract should be canceled because of a mutual mistake of the parties thereto. The mistakes charged were:

“First. That the plans upon which bids were invited showed borings indicating that the material to be encountered, through which the sewer would run, was blue clay, whereas, it was claimed to be something else.

“Second. That the plans represented that the material to be encountered in the trench was solid, whereas it was soft and semi-fluid.

“Third1. That in the approximate quantities, it was estimated by the engineer that 4,100 feet of timber foundation would be required, whereas, in fact, about 22,000 feet of timber foundation was used. It is claimed by argument that this miscalculation caused the defendant to bid less on another item, towit: excavation, than it would otherwise have done.”

The answer of the Blackstaff Engineering Company also sought to' recover for about $11,000, which it, claimed was the reasonable value of the work done by it and not [631]*631paid for by the Commissioners of Sewerage. Thereupon the Commissioners of Sewerage filed a reply, denying the affirmative allegations of the answer and pleading certain clauses of the contract in avoidance of the defenses set out in the answer. A rejoinder by the Black-staff Engineering Company completed the issue. Upon submission of the case, the chancellor gave judgment in favor of the Commissioners of Sewerage against the Blackstaff Engineering Company in the sum of $19,-■196.10, and dismissed its counterclaim. Judgment was also rendered against the Fidelity and Deposit Company of Maryland, in the sum of $8,000, the full amount of the bond. Only the Blackstaff Engineering Company appeals.

Appellant, Blackstaff Engineering Company, agreed to do the construction work according to certain plans and' specifications. Prior to the letting of the contract, appellees had taken samples of the sub-soil by means of a hand-auger, at points along the line of the work about two hundred feet apart. The locations of these borings are shown on certain blue-prints, numbered $77 and 878. There were other blue-prints, numbered 876, 879 and 880, showing the sewer when constructed. Appellees furnished each of the bidders a pamphlet containing information for bidders, a blank form of proposal, and a contract to be executed by the successful bidder. The material parts of the “Information for Bidders,” are as follows:

“The following is an approximate statement of the extent of the work required, based upon the estimate of the engineer; the several bids will be computed, tested and canvassed by the quantities of work given in the statement, viz.:

“Item la. Earth excavation and refill depth of cut 22 ft. to 29 ft. 942 linear feet.

“Item lb. Earth excavation and refill depth of cut 18 ft. to 30 ft. 438 linear feet.

“Item 1c. Earth excavation and refill depth of cut 10 ft. to 23 ft. 1,075 linear feet.

“Item Id. Earth excavation and refill depth of cut 13 ft. to 30 ft. 748 linear feet.

“Item 5a. Steel for reinforcing concrete (21,400 lbs., should the Commission elect to use plain steel bars.)

“Item 5b or 5c. Steel for reinforcing concrete (21,-300 lbs., should the Commission elect to use deformed steel bars.)

[632]*632“Item 6. Earth excavation in trench below masonry 40 cnbic yards.

“Item 7. Gravel refilling in trench below masonry 40 cnbic yards.

“Item 8. Vitrified pipe furnished and delivered.

“Item 11. 8-inch underdrain, 3,203 linear feet.

“Item 12. Timber foundation 4,100 ft. B. M.

“Item 13. Sheeting, bracing and cofferdam timber left in place.

“Item 14. Extra work.

“Item. 15. Cleaning up.

“These quantities are based upon the construction of the sewer in open cut, are approximately only, being given as a basis for the comparison of bids, and the Commissioners of Sewerage do not expressly or by implication agree that the actual amount of work will correspond therewith, but reserve the right to increase or decrease the amount -of any class or portion of the work as may be deemed necessary by the engineer. * * *

“As the above-mentioned quantities, though stated with as much accuracy as is practicable in advance, are approximate only, bidders are required to submit their estimates upon the following express conditions, which shall apply to and become part of every bid received, viz.:

“BIDDERS MUST SATISFY THEMSELVES, bv PERSONAL EXAMINATION of the location of the proposed work, and by such other means as they may prefer, as to the ACTUAL CONDITIONS and requirements of the work and the ACCURACY of the FOREGOING ESTIMATES OF THE ENGINEER, and shall not, at any time after the submission of an estimate of the engineer, dispute or complain of such statement or estimate, nor assert that there was any misunderstanding in regard to the nature or amount of work to be done.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wade v. City of Tacoma
230 P. 99 (Washington Supreme Court, 1924)

Cite This Page — Counsel Stack

Bluebook (online)
145 S.W. 152, 147 Ky. 629, 1912 Ky. LEXIS 310, Counsel Stack Legal Research, https://law.counselstack.com/opinion/blackstaff-engineering-co-v-commissioners-of-sewerage-kyctapp-1912.