Black Warrior Riverkeeper, Inc. v. Birmingham Airport Authority

561 F. Supp. 2d 1250, 2008 U.S. Dist. LEXIS 46703, 2008 WL 2421166
CourtDistrict Court, N.D. Alabama
DecidedMay 28, 2008
DocketCase CV-07-J-591-S
StatusPublished
Cited by1 cases

This text of 561 F. Supp. 2d 1250 (Black Warrior Riverkeeper, Inc. v. Birmingham Airport Authority) is published on Counsel Stack Legal Research, covering District Court, N.D. Alabama primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Black Warrior Riverkeeper, Inc. v. Birmingham Airport Authority, 561 F. Supp. 2d 1250, 2008 U.S. Dist. LEXIS 46703, 2008 WL 2421166 (N.D. Ala. 2008).

Opinion

ORDER

INGE PRYTZ JOHNSON, District Judge.

Pending before the court are motions to dismiss and briefs in support of said motions filed by defendants Dunn Construction Company (“Dunn”) and Birmingham Airport Authority (“BAA”) (docs. 4, 5, 7, 8, 23, 25 and 44). The plaintiff has filed responses to these motions (docs. 14,15,19 and 54) and the defendants have filed replies (docs. 57 and 58). The court has considered the pleadings, briefs, affidavits and evidence submitted by the parties. Because the parties have submitted evidence in support of the various motions, responses and replies, the court is of the opinion that the motions are properly considered as motions for summary judgment pursuant to Rule 12(d), Fed.R.Civ.Pro.

FACTUAL BACKGROUND

The plaintiff brought this action pursuant to the citizen’s suit provision of the Federal Water Pollution Control Act, commonly called the Clean Water Act (“CWA”), 33 U.S.C. § 1365, for violations of the CWA and the Alabama Water Pollution Control Act (“AWPCA”). Plaintiff asserts that the airport runway extension project at the Birmingham International Airport is causing discharges of pollutants to Village Creek, in violation of the NPDES General Construction Site Permit, issued by the Alabama Department of Environmental Management (“ADEM”). Complaint, ¶¶ 9, 16. Defendant BAA owns and operates the construction site in question. Complaint, ¶¶ 6, 9. Defendant Dunn is a contractor performing construction work in conjunction with the airport expansion project. Complaint, ¶ 10. All other defendants named in the complaint have been dismissed.

The NPDES permit in question is a General Permit, applicable to construction *1252 sites, issued by the state through ADEM. The requirements for this permit are found at Alabama Administrative Code § 335-6-12-.01, et seq. The plaintiff asserts the defendants have violated the permit in a variety of ways, that the violations are ongoing, and that the violations are adversely impacting Village Creek. Plaintiffs response (doc. 54).

The court stayed this ease to allow the administrative proceedings pending before ADEM to conclude. In January 2008 the parties informed the court that the proceedings had concluded, resulting in Consent Orders being entered between ADEM and each defendant (doc. 44). The plaintiff thereafter appealed those Consent Orders, but prior to the hearing set on that appeal, voluntarily dismissed its appeals.

STANDARD OF REVIEW

Although styled as motions to dismiss, both defendants and the plaintiff filed affidavits and evidence in support of their respective pleadings. The court therefore considers the pending motion and responses under Rule 56, Fed.R.Civ.P.

Under Rule 56(c), Fed.R.Civ.P., summary judgment is proper “if the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact that the moving party is entitled to judgment as a matter of law.” Celotex Corp. v. Catrett, 477 U.S. 317, 322, 106 S.Ct. 2548, 91 L.Ed.2d 265 (1986). Because the court must consider the pending motion as a motion for summary judgment, the court shall construe the evidence and factual inferences arising therefrom in the light most favorable to the nonmoving party. See Adickes v. SH. Kress & Co., 398 U.S. 144, 157, 90 S.Ct. 1598, 26 L.Ed.2d 142 (1970).

As required when a motion is dismiss is converted to a motion for summary judgment, the court allowed the parties time to respond and reply to the pending motions, such that the plaintiff and defendants were given reasonable opportunity to present evidence, and did present evidence as exhibits to their respective pleadings.

LEGAL ANALYSIS

The issues before the court on the current motions center around whether this action is barred. Defendants argue that because the plaintiff actively participated in the state enforcement action and voluntarily withdrew its appeal of that process, this case should be dismissed. The defendants further argue that under the doctrine of primary jurisdiction, this case cannot continue. Because ADEM held administrative proceedings resulting in Consent Orders, the defendants assert that the Court should refrain from exercising jurisdiction in deference to ADEM. For reasons set forth below, the court finds this argument less than convincing.

The plaintiff argues that despite the enforcement action by ADEM and the Consent Orders entered by the defendants, the defendants continue to violate their permits. See plaintiffs response (doc. 54). The plaintiff also asserts that many of the violations raised in this case were not addressed by the Consent Orders or the administrative actions. 1 See e.g., plaintiffs response (doc. 14) at 4-5. Defendant *1253 Dunn responds that the plaintiff complains of new violations, rather than continuing violations, necessitating a new 60 day notice, which has not been done. Reply of Dunn (doc. 57).

A § 1319 (g) (A) (ii):

The defendants assert that the plaintiffs complaint is barred under 33 U.S.C. § 1365 because the state has diligently prosecuted an enforcement action. Under the CWA, a citizen suit may not be brought if the State “has commenced and is diligently prosecuting an action under a State law comparable to this subsection ...” 33 U.S.C. § 1319(g)(6)(A)(ii). The plaintiff asserts that it falls within the exception to 1319(g)(6)(A)(ii), that being 1319(g)(6)(B)(ii). 33 USC § 1319(g)(6)(B)(ii) states that the limitations in subparagraph A against citizen suits do not apply with respect to any violation for which notice of the violation of 1365(a)(1) was properly given prior to commencement of a State enforcement action and a citizen suit action is filed within 120 days of the date on which the 60 day notice was given. See Public Interest Research Group of New Jersey, Inc. v. Elf Atochem North America, Inc., 817 F.Supp. 1164, 1172 (D.N.J.1993)(“The provision goes on to state that the bar does not apply if, prior to the commencement of the state enforcement action, the citizen plaintiff has provided 60-days notice of the alleged violations pursuant to § 505(b)(1)(A) of the Act and if the citizen plaintiff thereafter files suit within 120 days after such notice. See id. § 1319(g)(6)(B)(ii)”).

The court is of the opinion that the exception contained in 33 USC 1319(g)(6)(B)(ii) applies. The plaintiff sent 60 day notices of intent to sue as required by the CWA on January 30, 3007. It could not file suit until March 30, 2007, and did file suit April 3, 2007.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

MOSS v. SAL LAPIO, INC.
E.D. Pennsylvania, 2020

Cite This Page — Counsel Stack

Bluebook (online)
561 F. Supp. 2d 1250, 2008 U.S. Dist. LEXIS 46703, 2008 WL 2421166, Counsel Stack Legal Research, https://law.counselstack.com/opinion/black-warrior-riverkeeper-inc-v-birmingham-airport-authority-alnd-2008.