Black v. Philip Miller Co.

7 P.2d 33, 166 Wash. 430, 1932 Wash. LEXIS 548
CourtWashington Supreme Court
DecidedJanuary 26, 1932
DocketNo. 23179. Department One.
StatusPublished
Cited by1 cases

This text of 7 P.2d 33 (Black v. Philip Miller Co.) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Black v. Philip Miller Co., 7 P.2d 33, 166 Wash. 430, 1932 Wash. LEXIS 548 (Wash. 1932).

Opinion

Beeler, J.

We shall refer to the appellant Black as ‘ ‘ contractor, ’ ’ to the appellant Aetna Casualty and Surety Company as “surety” and to the respondent, Philip Miller Company, as “owner.”

On June 16, 1926, the contractor and the owner entered into a written contract jvhereby the former, for and in consideration of the sum of $139,000, agreed to furnish all materials and perform all labor neces *431 sary to make certain alterations and build or construct certain additions to tbe Elman hotel and Pilcher building for the owner at Wenatchee, Washington, in accordance with certain specifications and drawings. The surety gave its indemnity bond for a like amount indemnifying the owner against loss in the event the contractor failed to perform. The contract, in part, provided :

“No alteration shall be made in the work shown or described by the drawings and specifications, except upon a written order of the Architect, and when so made, the value of the work added or omitted shall be computed by the Architect, and the amount so ascertained shall be added to or deducted from the contract price. In the case of dissent from such award by either party hereto, the valuation of the work added or omitted shall be referred to three disinterested arbitrators, one to be appointed by each of the parties to this contract, and the third by the two thus chosen; the decision of any two of whom shall be final and binding, and each of the parties hereto shall pay one-half of the expense of such reference. . . .
“All payments shall be made upon written certificate of the architect to the effect that such payments have become due.
“If at any time there shall be evidence of any lien or claim for which, if established, the owner of the said premises might become liable, and which is chargeable to the contractor, the owner shall have the right to retain out of any payment then due or thereafter to become due an amount sufficient to completely indemnify him against said lien or claim. Should there prove to be any such claim after all payments are made, the contractor shall refund to the owner all moneys that the latter may be compelled to pay in discharging any lien on said premises made obligatory in consequence of the contractor’s default.
“(10) It is further mutually agreed between the parties hereto that no certificate given in payment made under this contract, except the final certificate or final payment, shall be conclusive evidence of the *432 performance of this contract either wholly or in part, and that no payment shall be construed to be an acceptance of defective work or improper materials.”

On the same day, the owner and the contractor entered into another agreement called “general review of alterations and additions of the Elman hotel and Pilcher building,” which, in part, provided:

“The owner reserves the right to make any alterations in the plans, specifications and construction whether additions or deductions without rendering void the contract and the amount allowed any contractor or credited to the owner shall be based upon the market value of such materials and such labor at the time such alterations, additions or deductions are made.”

Before the hotel was completed, differences arose between the contractor and the owner, and the former stopped work on the hotel. As a result, the architect, on April 7, 1927, in accordance with the terms of the contract, certified that the contractor had failed to complete the building, and that the owner was entitled to take possession and complete it himself.

Between the dates of April 7 and April 16, 1927, the owner and the contractor entered into negotiations with a view of adjusting their differences. On the latter date, they entered into a supplemental written agreement whereby the owner was to furnish all materials, and pay all labor charges each week, the contractor to superintend the construction and to receive ten per cent of the cost of the labor" furnished and the materials used. The work under this arrangement or agreement "was to be performed, as formerly, under the direction and with the approval of the architect. This supplemental agreement expressly provided that neither party should be released from the terms or conditions of the original contract. This instrument, in part, provided:

*433 “(2) Subject to the foregoing provisions, the first party as contractor agrees to perform or cause to be performed for the second party as owner all services reasonably necessary to complete the said Elman hotel and Pilcher building, and to expedite the work of such completion as rapidly as reasonably possible. The second party as owner is to furnish and supply all materials of every nature required for use in said completion, except the second party as owner shall have the right to have used in said completion any materials suitable for such purposes now on hand in connection with the work heretofore being done on said building. Such material however to be charged to and paid for by second party as owner, if not heretofore paid for by the owner or not the property of the owner, except as hereinafter stated.
“ (3) The actual cost of the material, not including material already on job, so used in said completion shall be paid for by second party as owner.
(4) The actual cost of labor and material used by first party under this contract shall be paid by second party direct to labor and material men. . . . ”

After the parties had operated under the above contract a few weeks, the contractor again abandoned the work, and later the architect computed and certified as to various items of damage, aggregating the sum of $18,151.59, sustained by the owner by reason of the non-completion of the building by the contractor.

On June 22, 1927, the contractor brought this action, alleging that the owner had breached the contract. This the owner denied, and by cross-complaint alleged that the contractor had breached the contract, and sought judgment against him in the sum of $18,-151,59. Various lien claimants appeared in the action. The cause came on for trial to the court June, 1928, and extended over a period of several weeks. Later, all questions were extensively argued to the court, and thereafter the trial judge took the cause under advise *434 ment, and on January 19, 1929, filed a very comprehensive and thorough written memorandum decision.

On March 13, 1929, judgment was entered against the owner and in favor of the contractor in the sum of $17,409.09, and against the owner and in favor of the various lien claimants, including interest and attorney’s fees, in the sum of $17,280.27. The judgment in part provided:

“It is Further, Ordered, Adjudged aud Decreed, That the defendant the Philip Miller Company, have judgment against the defendant Aetna Casualty and Surety Company, in such sum as the amount of costs herein adjudged to be paid by the Philip Miller Company in favor of the lien foreclosure judgment creditors shall exceed the sum of $127.82.” (Italics ours.)

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Black v. Philip Miller Co.
14 P.2d 11 (Washington Supreme Court, 1932)

Cite This Page — Counsel Stack

Bluebook (online)
7 P.2d 33, 166 Wash. 430, 1932 Wash. LEXIS 548, Counsel Stack Legal Research, https://law.counselstack.com/opinion/black-v-philip-miller-co-wash-1932.