Black v. Philip Miller Co.

14 P.2d 11, 169 Wash. 409, 1932 Wash. LEXIS 766
Washington Supreme Court·Decided August 25, 1932·No. No. 23179. En Banc.·Published·Cited by 2 cases

Opinion

Ok Reheauikg.

Tolmah, C. J.

This case was first heard by a Department of this court at the 1931 September term. The Departmental opinion will be found in 166 Wash. 430, 7 P. (2d) 33.

Thereafter, a petition for rehearing was granted, *411 and the case was reheard by the court sitting En Banc at the term just closed.

It is but fair to all concerned to say that, at the time of the Departmental hearing, no brief had been presented on behalf of the appellant Black. He was not represented by counsel at that hearing, and the judge writing the Departmental decision was left to grope his way through a stupendous record wholly unaided by brief or argument, and to ascertain as best he might what the appellant’s rights, if any, might be. At this hearing, a brief was presented on behalf of the appellant, his counsel appeared and argued orally, and a very different case is now made to appear.

Because of the multiplicity of the issues and the size of the record, we shall not restate the facts as given in the Departmental opinion, but will supplement or correct them where necessary, as briefly as possible.

As to the arbitration provision, the Departmental opinion makes too broad a statement. The contract provides:

“ (3) No alteration shall be made in the work shown or described by the drawings and specifications, except upon a written order of the architect, and when so made, the value of the work added or omitted shall be computed by the architect, and the amount so ascertained shall be added to or deducted from the contract price. In the case of dissent from such award by either party hereto, the valuation .of the work added or omitted shall be referred to three disinterested arbitrators, one to be appointed by each of the parties to this contract, and the third by the two thus chosen; the decision of any two of whom shall be final and binding, and each of the parties hereto shall pay one-half of the expense of such reference.”

Clearly, then, the only question to be arbitrated under the contract is “the value of the work added or omitted,” as computed and certified by the architect. *412 Since it clearly appears that the architect at no time attempted to make any award either by way of addition or deduction, he made no ruling which was reviewable by arbitration under the terms of the contract, and there is no question of arbitration in the case.

This was a remodeling job, by which two old buildings were to be so altered and added to as to produce a modern four-story hotel containing 156 guest rooms, where before had stood, adjoining each other, a one-story and a three-story building, neither in any degree modern.

The appellant argues that the contract was, in legal effect, a cost-plus contract, because, though $139,-000 was named as the contract price for the work, the contract carried a proviso:

. . . provided the cost to the contractor plus seven per cent (7%) shall equal said sum and if said cost plus 7 % shall be less than $139,000, the difference shall inure to the benefit of the owner, subject to additions and deductions as hereinbefore provided, J J

For several weeks or months prior to the signing of the building contract, the appellant, apparently in the hope of obtaining a contract to do the work, employed the architect who was afterwards in charge, and with him labored diligently in the preparation of sketches, plans and specifications. He participated in conferences with the owner, with the prospective tenant and with those charged with the financing, and appears to have been fully aware of just what plan was in view for raising the money to carry out the undertaking.

He knew that a bond issue of $150,000, secured upon the ground and building*, was to be floated; that the expense of thus financing was to be deducted from the *413 amount realized from the sale of the bonds; and that, at the best, there would be available from that source but $139,000 for the construction work. He and the owner both contemplated that the cost of construction should not exceed this sum, and into the contract was written a provision that if the cost was less the saving should inure to the owner. The plans and specifications then existing were most general in character. They contemplated the completion of a four-story modern hotel building at a cost of not exceeding $139,000, and a contractor’s bond in that amount was given to insure faithful performance.

Therefore, taking the contract as a whole, and considering the known circumstances under which it was entered into, we have no hesitancy in saying that it was not a cost-plus contract, but that it was what it purports to be, a contract to do the work then contemplated for a fixed sum, with a saving to the owner, if the actual cost of the work, plus seven per cent compensation to the contractor, totaled less than the amount so fixed.

Perhaps the most serious and troublesome question is: What was the work contemplated, and did the owner, as the work progressed, by its direct orders or otherwise, require work to be done which was not within the contemplation of the parties at the time the contract was executed?

It seems to be conceded that, when the contract was signed, the drawings and specifications were very far from complete. Respondents seem to contend that this situation called only for ordinary detailed plans such as are usually prepared and furnished as the work progresses. On the other hand, appellant contends that the plans as they existed when he signed the contract were mere “picture plans,” under which almost anything could be specified, and that, even as to de *414 tail alone, the detail plans and specifications conld be and were “loaded” against him. In general, we think the appellant has sustained his position by the convincing weight of the evidence.

The appellant claimed as extras and additions sixty-one different items, aggregating’ in amount many thousands of dollars. Some of these were allowed by the trial court, some allowed in part, but in the main they were rejected; for just what reason does not clearly appear. Each of these items presents a more or less distinct issue of fact. The evidence relating to these different issues was given by many witnesses, and is embraced in a statement of facts of more than 1800 pages, the abstract of which exceeds 700 pages. It is manifestly impossible for a reviewing court to go through all of this evidence and segregate and classify the testimony of each witness on each issue so as to accurately assemble and weigh the evidence pro and con upon each particular issue; nor will we attempt that task.

By laying down certain guiding principles, we hope to clearly establish the rule by which the trial court (or referee, if he shall think it wise to appoint one) may, from the evidence already taken, or by receiving additional evidence, if in his discretion that will tend to greater justice, reach a complete, final and just decision.

Free access — add to your briefcase to read the full text and ask questions with AI

Black v. Philip Miller Co., 14 P.2d 11, 169 Wash. 409, 1932 Wash. LEXIS 766 (Wash. 1932).

14 P.2d 11 (Black v. Philip Miller Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Opinion No.
Texas Attorney General Reports, 1984
Untitled Texas Attorney General Opinion
Texas Attorney General Reports, 1984