Black v. Cutko

CourtSuperior Court of Maine
DecidedAugust 10, 2021
DocketCUMbcd-cv-20-29
StatusUnpublished

This text of Black v. Cutko (Black v. Cutko) is published on Counsel Stack Legal Research, covering Superior Court of Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Black v. Cutko, (Me. Super. Ct. 2021).

Opinion

STATE OF MAINE BUSINESS AND CONSUMER DOCKET CUMBERLAND, ss. Location: Portland DKT. NO. BCDWB-CV-2020-29

RUSSELL BLACK, et al., ) ) Plaintiffs, ) ) v. ) DECISION AND ORDER ) (14 M.R.S.A. § 5953 & M.R. Civ. P. 80C) ) ANDY CUTKO, et al., ) Defendants. )

In 1993 the people of Maine decided that their public lands were worthy of constitutional

protection. Through their ratification of Article IX, Section 23 of the Maine Constitution,

designated public lands cannot be “reduced” or their “uses substantially altered” unless two

thirds of both houses of the Maine Legislature agree to any such change. The central question

presented in this case is whether certain decisions made in 2014 and 2020 by the Bureau of

Public Lands (“BPL”), the Executive Branch agency that holds title to the lands for the benefit of

all Maine people, complied with this unique and consequential Amendment.

In analyzing this question, a number of significant issues of first impression have been

identified by the Court and the parties. The Court therefore encouraged the parties at various

stages of this litigation to agree to a Report of at least some of those questions directly to the

Law Court pursuant to Rule 24 of the Maine Rules of Appellate Procedure. However, the parties

could not agree on a Stipulated Record which would permit the Court to make such a report

under Rule 24(a), and BPL decided not to move for such a Report under Rule 24(c) after the

Court ruled against it on a potentially dispositive issue.

1 Plaintiffs in this action challenge BPL’s 2014 and 2020 decisions to lease to Central

Maine Power Company (“CMP”) 1 portions of two parcels of public reserved land to construct

part of the New England Clean Energy Connect transmission corridor. The lands at issue are

located in the Upper Kennebec Region, specifically in West Forks Plantation and Johnson

Mountain Township.

Pending before the Court are the parties’ respective motions for judgment on Plaintiffs’

Declaratory Judgment claim and Plaintiffs’ Rule 80C appeal. Both have been fully briefed and

are now before the Court for decision. Plaintiffs are represented by Attorneys James Kilbreth,

David Kallin, Adam Cote, and Jeana McCormick. Defendants Andy Cutko and BPL are

represented by Assistant Attorneys General Lauren Parker and Scott Boak. Defendants CMP and

NECEC Transmission, LLC are represented by Attorneys Nolan Reichl and Matthew Altieri.

BACKGROUND

Maine’s historical practices regarding its management of public land provide context to

the issues presented. A more detailed discussion of that history is outlined in the Court’s orders

dated December 21, 2020 and March 17, 2021 and are incorporated by reference, but is

summarized briefly as follows. After acquiring approximately 7 million acres from

Massachusetts upon statehood, Maine sold or gave away all but 400,000 acres of this land,

mostly prior to 1890. The remaining 400,000 acres of public land were reserved in each of

Maine’s unorganized townships as approximately 1000 acre lots. Over the years, the State leased

1 CMP assigned the 2020 lease to NECEC Transmission, LLC in early 2021. NECEC Transmission was joined as a defendant in this case. The Court will refer to them collectively as CMP for the sake of consistency with prior orders in the case.

2 these public reserved lands at virtually no cost to camp owners, paper companies, and timber

companies. In the early 1970s, a reporter published a series of articles in the Portland Press

Herald that called attention to Maine’s historical management practices and alleged abuses of the

public lot leasing program.

In the years that followed, various legal and political efforts were undertaken to preserve

the public reserved lands and to ensure their availability for the public’s use for generations to

come. The culmination of these efforts, legally speaking, was the 1993 Amendment to the Maine

Constitution, see Me. Const. art. IX, § 23. The Amendment states as follows: “State park land,

public lots or other real estate held by the State for conservation or recreation purposes and

designated by legislation implementing this section may not be reduced or its uses substantially

altered except on the vote of 2/3 of all the members elected to each House.” Id. The legislation

implementing the Amendment designated “public reserve lands” for this constitutional

protection, and the West Forks Plantation and Johnson Mountain Township parcels fall within

this category. 12 M.R.S.A. §§ 598-B(2-A)(D), 1801(8).

In addition, the Legislature declared when enacting 12 M.R.S.A. Section 1846(1) in 1997

as follows: “[I]t is the policy of the State to keep the public reserved lands as a public trust and

that full and free public access to the public reserved lands to the extent permitted by law,

together with the right to reasonable use of those lands, is the privilege of every citizen of the

State.” Id. (emphasis added).

In the summer of 2014, CMP approached the Governor’s Office about its proposed

transmission line project and its interest in crossing the West Forks Plantation and Johnson

Mountain Township public lots. R. III0001. BPL and CMP proceeded to negotiate a lease

agreement. During this process, AAG Lauren Parker, David Rodrigues (BPL’s Director of Real

3 Property Management and former Senior Planner), and several others provided input and

comments on the various lease drafts, with Mr. Rodrigues at one point inquiring: “Didn’t we get

a determination from the [Attorney General’s] office that a lease is a contract and the legislature

should not be able to break an existing contract?” R. III0053.

The lease was ultimately signed on December 15, 2014 (“the 2014 lease”). Under the

agreement, BPL agreed to lease to CMP a “three hundred (300) foot wide by approximately one

mile long transmission line corridor” (consisting of roughly 33 acres) located on the West Forks

and Johnson Mountain public lots. R. I0035–36. The lease specified an initial term of 25 years

and established the annual rent at $1400, to be adjusted by an appraisal. 2 Id. BPL did not provide

notice to the Legislature or to the public of its intentions to enter into the lease; it did not seek or

obtain 2/3 legislative approval of the lease; it did not make any contemporaneous written

findings as to why it was not seeking legislative approval; and the lease did not come to light

until—depending on the version of subsequent events believed by different parties—months or

years after it was executed. 3

Additionally, CMP did not obtain a Certificate of Public Convenience and Necessity

(“CPCN”) from the Public Utilities Commission (“PUC”) prior to entering into the 2014 lease as

required by law. See 35-A M.R.S.A. § 3132(13). Rather, the CPCN process commenced after the

2 On June 22, 2015, the lease was amended to increase the annual lease payment from $1400 to $3680. R. I0061. 3 The 2014 lease was briefly mentioned in BPL’s annual report to the Legislature’s Joint Standing Committee on Agriculture, Conservation, and Forestry, dated March 1, 2016. Specifically, BPL noted: “During 2015 the Bureau saw increased requests for new powerline corridor leases across its lands, reflecting continued interest in wind generation for supplying more ‘green’ energy to the demand centers in southern New England.” R. VII0158. “One lease completed in FY 2015 involves a 300-foot corridor 4,700 feet in length crossing two small public lots in the Forks area.” Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Phelps v. United States
274 U.S. 341 (Supreme Court, 1927)
Coleman v. Miller
307 U.S. 433 (Supreme Court, 1939)
Raines v. Byrd
521 U.S. 811 (Supreme Court, 1997)
Saunders v. Tisher
2006 ME 94 (Supreme Judicial Court of Maine, 2006)
Storer v. Department of Environmental Protection
656 A.2d 1191 (Supreme Judicial Court of Maine, 1995)
Cushing v. State
434 A.2d 486 (Supreme Judicial Court of Maine, 1981)
Fitzgerald v. Baxter State Park Authority
385 A.2d 189 (Supreme Judicial Court of Maine, 1978)
Tomer v. Maine Human Rights Commission
2008 ME 190 (Supreme Judicial Court of Maine, 2008)
Campaign for Sensible Transportation v. Maine Turnpike Authority
658 A.2d 213 (Supreme Judicial Court of Maine, 1995)
Gould v. Greylock Reservation Commission
215 N.E.2d 114 (Massachusetts Supreme Judicial Court, 1966)
LaFleur Ex Rel. Anderson v. Frost
80 A.2d 407 (Supreme Judicial Court of Maine, 1951)
Carl L. Cutler Co. v. State Purchasing Agent
472 A.2d 913 (Supreme Judicial Court of Maine, 1984)
Maine v. Shalala
81 F. Supp. 2d 91 (D. Maine, 1999)
Bonney v. Stephens Memorial Hospital
2011 ME 46 (Supreme Judicial Court of Maine, 2011)
Maine Senate v. Secretary of State
2018 ME 52 (Supreme Judicial Court of Maine, 2018)
Wawenock, LLC v. Department of Transportation
2018 ME 83 (Supreme Judicial Court of Maine, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
Black v. Cutko, Counsel Stack Legal Research, https://law.counselstack.com/opinion/black-v-cutko-mesuperct-2021.