Black Lake Pipe Line Co. v. Union Construction Co.

520 S.W.2d 486
CourtCourt of Appeals of Texas
DecidedJanuary 23, 1975
DocketNo. 5345
StatusPublished
Cited by1 cases

This text of 520 S.W.2d 486 (Black Lake Pipe Line Co. v. Union Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Black Lake Pipe Line Co. v. Union Construction Co., 520 S.W.2d 486 (Tex. Ct. App. 1975).

Opinions

HALL, Justice

On January 4, 1967, Mobile Pipe Constructors, Inc., and Dillingham Construction Company, joint venturers known as Mobile Pipe-Dillingham (hereinafter called “MPD”) agreed in writing to construct an 8⅝" diameter pipe line, extending approximately 125 miles from a place in Natchi-toches Parish, Louisiana, to a point in Hardin County, Texas, for Black Lake Pipe Line Company (“Black Lake”). Substantially all of the work to be performed under the contract was subcontracted by MPD to McCathern, Inc. McCathern retired from the job in July, 1967. MPD thereupon subcontracted to Union Construction Company, Inc., (“Union”) for construction of about 67 miles of the pipeline, and performed the remainder of the work itself. All of the terms and conditions and applicable plans and specifications of the contract between Black Lake and MPD were incorporated into and made a part of the contract between MPD and Union. The contract called upon Black Lake to furnish the needed pipe for this phase of the construction.

The original completion date according to the contract was April 15, 1967. Various extensions were granted by Black Lake to June 15th, to August 1st, and, finally, to August 15th, 1967, for completion of a usable pipeline, plus a reasonable time thereafter for completion of the cleanup work.

[488]*488All of the parties agree that Union and MPD have completed and have been paid for the work contemplated and called for by the terms, plans and specifications of the contracts. However, this lawsuit stems from a dispute between the parties as to just what amount of work was required under the contracts.

Union initiated this suit against Black Lake and MPD for payment of particularized work which it claims was in excess of the work required by its contract. Union pleaded that Black Lake, through its representatives on the job, continuously refused to accept and approve work done by Union under its contract unless and until Union satisfied Black Lake’s representatives by performing work over and above that called for by the contract; that, under the circumstances, these requirements for extra work were arbitrary and capricious and were based upon unreasonable constructions and interpretations of the job plans and specifications; that Union was forced to comply with the requirements for extra work in order to secure acceptance and approval of its work under the contract and to complete the pipeline; that the extra work was therefore obtained by Black Lake under and as a result of business compulsion and economic duress; that the excess work has a reasonable value of $315,910.08; that the requirements and activities by Black Lake “substantially interfered” with Union’s performance of its contract, resulting in its damages in the amount of $315,910.08; that a direct contractual relationship existed between Union and Black Lake because throughout construction of the pipeline Black Lake’s representatives on the job directed and supervised Union’s employees in the work being done, and because Black Lake entered into various agreements with Union, both oral and written, concerning construction of the pipeline; and that Black Lake accepted the benefits of the extra work knowing that Union expected to be paid therefor at the applicable extra work rates and at prices which were fair and reasonable therefor.

Answering Union’s suit, MPD alleged that all of the work for which Union seeks recovery was ordered and required by Black Lake; and that Black Lake, not MPD, is liable therefor. And, in the event Union recovered from MPD, it sought indemnity from Black Lake. MPD then pleaded a cross-claim against Black Lake for payment for specified work allegedly in excess of its written contract. In this regard, MPD’s pleadings were substantially the same as Union’s pleadings, with assertions of economic duress, and arbitrariness on the part of Black Lake. MPD asserted that the reasonable value of its extra work was $346,966.56. Alternatively, MPD alleged that the extra-contractual activities and requirements by Black Lake “substantially interfered” with MPD’s performance of its contract with Black Lake and its subcontractors on the job, resulting in its damages in the amount of $346,966.56.

In alternative pleas, both Union and MPD pleaded for recovery on quantum meruit.

In its answer, Black Lake denied that MPD or Union had performed extra work and pleaded, inter alia, that if they did so, they failed to comply with the “Extra Work” provisions of the contract for establishment and payment of “extra work” claims; and thereby led Black Lake to believe the claims would not be made; and were estopped to make the claims or had waived them.

Trial was to a jury. The following are the effect of the jury’s answers to special issues pertinent to a proper disposition of this appeal.

It found (1), (2) that Black Lake required Union to do more work in connection with terracing and furrowing across a portion of the pipeline right of way than was reasonably necessary to direct the flow of water into natural drainage courses, and, (3), (4) that Black Lake arbitrarily and capriciously refused to approve Union’s terrace and furrow work unless this extra work was done; (6) that this was [489]*489done by Union under duress; (5) that $5,893.51 would reasonably compensate Union for it; and, it failed to find (7), (8) that Union, by its acts, conduct or silence, waived its right to assert a claim for compensation for this work or led Black Lake to believe that such claim would not be made;

It found (10) that Black Lake required Union to remove brush, uprooted tree stumps or brush trimmings from property other than the pipeline right of way, after (11), (12) Black Lake had previously approved the placing of this debris outside the right of way under agreements with adjoining landowners, and (13), (14) that Black Lake arbitrarily and capriciously refused to approve Union’s cleanup phase of the work without the performance of this extra work; (15) that Union did this extra work under duress; (16) that $12,862.94 would reasonably compensate Union for it; and it failed to find (17), (18) that Union, by its acts, conduct or silence, waived its right to assert a claim for compensation for this work or led Black Lake to believe that such claim would not be made;

It found (20), (21) that on or about July 5, 1967, Black Lake required Union to add a “second spread” (meaning a material increase of men and equipment it was using on the job); (23) that this addition was made by Union under duress; (27) that this addition increased Union’s cost of completing the work; and (28) that $109,415.50 would reasonably compensate Union for it; and it failed to find (22) that this requirement was arbitrary or capricious; or (.24) that Union could have completed its 67 miles of the pipeline “ready to receive and transport petroleum products” by August 15, 1967, without the second spread; or (26) that, “but for the acts, conduct and requirements of Black Lake,” Union could have so completed its portion of the pipeline by August 1, 1967, without the second spread; or (25) that prior to June 19, 1967, Black Lake approved August 15, 1967, as the completion date of Union’s 67 miles as a pipeline ready to receive and transport; or (29), (30) that Union, by its acts, conduct, or silence, waived its right to assert a claim for compensation for the second spread expense or led Black Lake to believe that such claim would not be made;

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Black Lake Pipe Line Co. v. Union Construction Co.
538 S.W.2d 80 (Texas Supreme Court, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
520 S.W.2d 486, Counsel Stack Legal Research, https://law.counselstack.com/opinion/black-lake-pipe-line-co-v-union-construction-co-texapp-1975.