Black Diamond Development, Inc. v. Thompson

979 So. 2d 47, 2007 Ala. LEXIS 160, 2007 WL 2285882
CourtSupreme Court of Alabama
DecidedAugust 10, 2007
Docket1060334
StatusPublished
Cited by14 cases

This text of 979 So. 2d 47 (Black Diamond Development, Inc. v. Thompson) is published on Counsel Stack Legal Research, covering Supreme Court of Alabama primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Black Diamond Development, Inc. v. Thompson, 979 So. 2d 47, 2007 Ala. LEXIS 160, 2007 WL 2285882 (Ala. 2007).

Opinion

Black Diamond Development, Inc. ("BDD"), appeals from a judgment in favor of Patrick G. Thompson, in Thompson's breach-of-contract action against BDD. We affirm.

I. Factual Background
On May 19, 1997, the parties in this case executed a document purporting to be an "Agreement for Purchase of Interest" in a condominium "development project in Mt. Crested Butte, Colorado," which BDD was contemplating at that time (hereinafter referred to as "the sell-back agreement"). The sell-back agreement stated, in pertinent part:

"In consideration of cash value received from Patrick G. Thompson . . . in the amount of $38,000.00, . . . Black Diamond Development, Inc., does hereby sell a two percent (2) interest of the net proceeds or profit from the condominium project to be built in Mt. Crested Butte, Co. In the event the purchaser desires to sell-back his interest, during the construction process, he may do so by giving a thirty day written notice and will receive his principle [sic] investment, plus fifteen percent interest (15% APR) calculated from the date of this agreement."

(Emphasis added.) The sell-back agreement was signed by Thompson and by Steve McCay, as president of BDD.

The next day, Thompson sent BDD $38,000 (hereinafter referred to as "the first installment"). McCay used the money to reimburse himself for his expenditures in procuring engineering reports, soil tests, and plans and specifications, and in traveling in connection with the contemplated condominium-development project. On July 8, 1997, Thompson sent BDD an additional $62,000 (hereinafter referred to as "the second installment"). McCay used the money from the second installment in a manner similar to the first installment. Both transactions were brokered by Gordon Berlant, who is not a party in this case.

In conjunction with the second installment, Thompson and BDD executed a second document purporting to evidence the parties' agreement as to their respective rights and responsibilities arising out of BDD's receipt and use of the $62,000 (hereinafter referred to as "the July document"). The parties have been unable to produce the original of the July document,or even a legible copy of the original. In the only copy produced in this case, approximately one-third of the text is illegible.

BDD never broke ground on the condominium project. According to McCay, the project was ultimately abandoned when another developer purchased property in Mt. Crested Butte that BDD considered key to the financial success of the project. On April 8, 2004, Thompson wrote a letter to McCay; that letter stated, in pertinent part:

"Promise was made on agreements dated May 19, 1997, for an investment in the amount of $38,000.00 and an additional installment in the amount of $62,000.00 dated July 8, 1997, which totaling $100,000.00, would . . . culminate into owning 5.5% interest in the Mt. Crested Butte, Co., project. I hereby request to have my principal investment of $100,000.00 plus 15% interest per year (15% APR) calculated from the date of the agreement to be returned to me. You have 30 days to fulfill your obligation based on the term[s] of the agreement."

*Page 50

(Emphasis added.) On July 27, 2004, Thompson sued BDD, alleging breach of contract and seeking damages in the amount of $206,259.96. Specifically, he sought the return of the $100,000 principal, plus interest at the rate of 15%. The case was tried without a jury on the basis of documentary evidence and oral testimony.

At trial, counsel for BDD objected to introduction of the July document, arguing that, because of its illegibility, it had no probative value. More specifically, he stated:

"When I received the complaint, my first response was, I sent him a letter asking him for a better copy because I could not read it. And if you look at [it], you cannot read it either. I cannot tell whether — I cannot tell who is — or who would owe who, or if it was only supposed to be repayment in the event the project took off or made any money. You cannot tell. You can see bits and pieces of it, but you cannot tell from that [document] what happened."

The trial court stated: "I will overrule your objection and accept it for whatever it is worth. Whether I can read it or not remains to be seen, I suppose." (Emphasis added.) Ultimately, the trial court awarded Thompson $235,950, which included the principal and interest thereon at the rate of 15% through the date of the judgment, and BDD appealed.

As BDD frames the issues on appeal, this Court is faced with two issues. The threshold issue concerns the construction of a key phrase in the sell-back agreement relating specifically to the first installment. An issue regarding recovery of the second installment arises only if the phrase in the sell-back agreement is construed adversely to BDD.

II. Construction of the Sell-Back Agreement
It is undisputed that the parties agreed that Thompson would be entitled to repayment of his first installment of $38,000, plus interest at the rate of 15%, if his request for repayment was made "during the construction process." In other words, it is undisputed that Thompson would be entitled to repayment of his first installment at 15% interest if the sell-back agreement was triggered by BDD's work in procuring engineering reports, soil tests, and plans and specifications, and in traveling in connection with the contemplated condominium-development project. BDD, however, contends that the sell-back agreement was never triggered, because, it insists, "construction" on the project was never begun. According to BDD, the phrase "during the construction process" does not include such activities as procuring engineering reports, soil tests, and plans and specifications, and traveling. The resolution of this issue thus involves a matter of contract construction.

"`[W]e apply a de novo review to a trial court's determination of whether a [written] contract is ambiguous and to a trial court's determination of the legal effect of an unambiguous contract term.'" Young v. Pimped,882 So.2d 828, 830 (Ala. 2003) (quoting Winkleblack v.Murphy, 811 So.2d 521, 525-26 (2001)). "[A] contract is not ambiguous simply "`because the parties allege different constructions of [it]."'" Avis Rent A Car Systems, Inc. v.Heilman, 876 So.2d 1111, 1122 (Ala. 2003) (quoting Exparte University of South Alabama, 812 So.2d 341,345 (Ala. 2001), quoting in turn Yu v. Stephens,591 So.2d 858, 859 (Ala. 1991)). A contract is ambiguous only if it is "susceptible of more than one reasonable meaning,"FabArc Steel Supply, Inc. v. Composite Constr. Sys.,Inc., 914 So.2d 344, 357 (Ala. 2005) (emphasis added), and "`it is presumed that parties intend to makereasonable contracts.'" BellSouth Mobility, Inc.v. Cellulink, Inc., *Page 51 814 So.2d 203, 216 (Ala. 2001) (quoting Weathers v.Weathers, 508 So.2d 272, 274 (Ala.Civ.App.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

James O'Shea v. OMI Holdings Inc.
Eleventh Circuit, 2023
Once Upon a Time, LLC v. Chappelle Properties, LLC
209 So. 3d 1094 (Supreme Court of Alabama, 2016)
Barko Hydraulics, LLC v. Michael Shepherd
167 So. 3d 304 (Supreme Court of Alabama, 2014)
BLACK WARRIOR MINERALS, INC. v. John FAY, Jr.
82 So. 3d 650 (Supreme Court of Alabama, 2011)
Scrushy v. Tucker
70 So. 3d 289 (Supreme Court of Alabama, 2011)
Kennedy v. Boles Investments, Inc.
53 So. 3d 60 (Supreme Court of Alabama, 2010)
Jewett v. Boihem
23 So. 3d 658 (Supreme Court of Alabama, 2009)
Dabbs v. FOUR TEES, INC.
36 So. 3d 542 (Court of Civil Appeals of Alabama, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
979 So. 2d 47, 2007 Ala. LEXIS 160, 2007 WL 2285882, Counsel Stack Legal Research, https://law.counselstack.com/opinion/black-diamond-development-inc-v-thompson-ala-2007.