B&L Drywall, LLC. v. R.L. Turner Corporation

Indiana Court of Appeals·Decided July 15, 2024·No. 23A-PL-02962·Published

Opinion

IN THE

Court of Appeals of Indiana FILED

B & L Drywall, LLC,

Jul 15 2024, 9:24 am

Appellant CLERK Indiana Supreme Court

Court of Appeals

and Tax Court

v.

R.L. Turner Corporation,

Appellee

July 15, 2024

Court of Appeals Case No.

23A-PL-2962

Appeal from the Boone Circuit Court The Honorable Lori N. Schein, Judge Trial Court Cause No.

06C01-1910-PL-1505

Opinion by Judge Bailey

Chief Judge Altice and Judge Mathias concur.

Bailey, Judge.

Case Summary [1] B&L Drywall, LLC (“B&L”) appeals the order granting summary judgment

and damages to R.L. Turner Corp. (“RLTC”) for B&L’s breach of contract. We affirm.

Issues [2] B&L raises the following two issues:

I. Whether the trial court erred when it denied B&L’s motion for summary judgment and granted RLTC’s motion for summary judgment.

II. Whether the trial court’s damages award is erroneous.

Facts and Procedural History [3] On March 29, 2018, RLTC, the Contractor, and B&L, the Subcontractor,

entered into a written subcontract (“the Contract”)1 for B&L to do drywall work for RLTC at The Whittaker Inn (“the Project”). The work was to be done “in full accordance with the Plans, Specifications,[2] and any issued Addendum

1 The Contract refers to itself as both “the Contract,” “the Subcontract,” and “the Subcontract Documents.” To avoid confusion, we refer to it solely as “the Contract.” 2 The Contract—and both parties on appeal—refer repeatedly to the “plans,” “specifications,” and/or “drawings.” Appellee’s App. v. II at 5-23. However, neither party points to where in the designated

Court of Appeals of Indiana | Opinion 23A-PL-2962 | July 15, 2024 Page 2 of 13 documents for this project.” Appellee’s App. v. II at 5, “THE WORK.” The “Scope” of the work was, in relevant part:

Provide labor/materials/equipment complete, provided in strict accordance with the plans and specifications[,] for the following:

All drywall work, including finishing to Level 4 and 5 finishes on walls and ceilings as indicated on drawings and per the specifications and industry standards, in all areas.

Id., “Scope.” The “[w]ork associated with th[e] scope will be completed per RL Turner’s project schedule(s).” Id.; see also id. at 18, § 9.5 (“Subcontactor shall perform work in accordance with [the] schedule provided by Contractor.”). The “Contract Sum” to be paid by RLTC to B&L for performance of the work was $141,770.00. Id. at 6.

[4] Section 7.3 of the Contract states, in relevant part, “The Contractor may, without cause, order the Subcontractor in writing to suspend, delay[,] or interrupt the Work of this Subcontract in whole or in part for such period of time as the Contractor may determine[, and] the Subcontractor shall be entitled to an equitable adjustment of the Subcontract Time and Subcontract Sum.” Id. at 17. Section 5.2 provides, in relevant part,

The Subcontractor may be ordered in writing by the Contractor, without invalidating this Subcontract, to make changes in the Work within the general scope of this Subcontract, consisting of additions, deletions, or other revisions…. [with t]ime being

evidence those plans, specifications, and/or drawings are located, and we were unable to locate those documents in the record.

Court of Appeals of Indiana | Opinion 23A-PL-2962 | July 15, 2024 Page 3 of 13

adjusted accordingly. The Subcontractor, prior to the commencement of such changed or revised Work, shall submit promptly to the Contractor written copies of a claim for adjustment to the Subcontract Sum and Subcontract Time or the claim is deemed waived.

Id. at 16. Section 5.3 of the Contract states, in pertinent part, “The Subcontractor shall make all claims to the Contractor for additional cost, extensions of time and damages for delays or other causes in accordance with the Subcontract Documents, but in no event later than 14 days of the event that gives rise to the claims…. Claims not properly submitted will be rejected.” Id.

[5] Section 7.2 of the Contract provides, in relevant part:

If the Subcontractor persistently or repeatedly fails or neglects to carry out the Work in accordance with the Subcontract Documents or to otherwise perform in accordance with this Subcontract and fails within forty-eight hours (48 Hrs) after receipt of written notice to commence and continue correction of such default or neglect with diligence and promptness, the Contractor may supplement Subcontractor’s workforce without prejudice to any other remedy, terminate the Subcontract[,] and finish the Subcontractor’s Work by whatever method the Contractor may deem expedient.

Id. at 17.

[6] Section 3.3.1 of the Contract provides that the Contractor may recover from the Subcontractor “consequential costs” and “actual damages” caused by the Subcontractor. Id. at 8. Furthermore, “[i]f the Subcontractor defaults … the Contractor may … make good such deficiencies and may deduct the reasonable cost thereof from the payments … due the Subcontractor.” Id., § 3.4.1. The “Subcontractors will be back-charged for any additional cost and damages incurred by the Contractor due to the [S]ubcontractor’s inability to complete the performance of their scope of work.” Id. at 16, § 5.4(a); see also id. at 20, § 11.8.1 (“Subcontractor agrees that [C]ontractor may withhold or deduct from any sums due [S]ubcontractor under the [C]ontract for claims[,] damages, back- charges or other offsets that [C]ontractor may have against [S]ubcontractor on this project or any other contract or project.”). In addition, “Subcontractor agrees to pay Contractor for all legal fees incurred by Contractor resulting from Subcontractor’s default, claims against Subcontractor, or Subcontractor’s noncompliance with any Contract provisions.” Id. at 22, § 15.8.

[7] B&L performed a small amount of the work prior to December 2018 but could not do more before that time due to the work of other subcontractors. In December 2018, RLTC notified B&L to begin the bulk of the scope of work on the Project. B&L objected to the sequencing of the work—specifically, it objected that mechanical equipment had already been installed at the Project before (rather than after) the drywall was to be installed, and B&L therefore refused to proceed with drywalling as requested. However, B&L did not file a written claim for adjustment to the Subcontract Sum and/or Subcontract Time. On December 31, 2018, RLTC notified B&L in writing that B&L had “48 hours to rectify the Default. After such time [RLTC] will find an alternate contractor and B&L will be responsible for any and all costs associated with rectifying the Default.” Id. at 50.

[8] B&L did not take any action within forty-eight hours of RLTC’s December 31 written notice. Thereafter, RLTC engaged a replacement contractor to complete B&L’s work on the Project for a total cost of $283,260.00. The replacement contractor finished the work and the Project passed inspection by the County.

[9] On October 8, 2019, RLTC sued B&L for breach of contract, seeking damages and attorney’s fees. Specifically, RLTC alleged that B&L breached the contract by “fail[ing] to complete the work of the Contract.” Id. at 3. RLTC sought a damages award of the difference between the price paid to the replacement contractor and the amount of the Contract Sum ($141,770)), plus an award of legal fees. Each party moved for summary judgment. Following a hearing on the motions, the trial court granted RLTC’s motion for summary judgment and denied B&L’s motion.

Free access — add to your briefcase to read the full text and ask questions with AI

B&L Drywall, LLC. v. R.L. Turner Corporation, (Ind. Ct. App. 2024).

B&L Drywall, LLC. v. R.L. Turner Corporation (B&L Drywall, LLC. v. R.L. Turner Corporation) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related