Bivins Construction v. State Contractors' Board
This text of 809 P.2d 1268 (Bivins Construction v. State Contractors' Board) is published on Counsel Stack Legal Research, covering Nevada Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinions
[282]*282OPINION
By the Court,
Appellant, a general contractor, hired Pipes Paving to provide grading and paving at the Red Rock Vista Phase II and Phase III sites in Clark County. Pipes Paving completed work on Phase II and seventy-five to eighty percent of the work on Phase III. A dispute between appellant and Pipes Paving resulted in Pipes Paving’s discharge. Thereafter, appellant failed to pay Pipes Paving any money owed on the contract.
Pipes Paving brought a complaint before respondent State Contractors’ Board (hereinafter “Board”). Appellant counterclaimed for costs incurred in completing the job after Pipes Paving’s dismissal. A hearing was held on March 16, 1989. The Board ordered that appellant’s license be suspended until Pipes Paving was paid the full amount it sought. A reprimand was placed in appellant’s file with the Board for violation of NRS 624.3012(2).1 The Board took no action on appellant’s counterclaim.
At the hearing, appellant’s cross-examination of William Pipes was limited because members of the Board believed it was exceeding the scope of direct examination. Appellant contends that this limitation was reversible error. We agree. NRS 233B.123(4)2 expressly permits cross-examination on any matter, [283]*283even where such matter was not covered in direct examination. The Nevada Administrative Procedures Act (NAPA) also provides for judicial reversal of agency decisions made upon unlawful procedure. NRS 233B.135(3)(c).
We find no merit in respondent’s contention that appellant’s failure to formally object to the curtailment of his cross-examination precludes reversal on judicial review. The minimum procedural requirements established by the NAPA may not be ignored. Gibson Co. v. Archie, 92 Nev. 234, 235, 548 P.2d 1366, 1367 (1976). The rudiments of fair play must be observed in administrative hearings. Checker, Inc. v. Public Serv. Comm’n, 84 Nev. 623, 634, 446 P.2d 981, 988 (1968). The right to cross-examine witnesses in an adjudicatory proceeding is one of fundamental importance. Its denial in this case amounted to a violation of due process.
When reviewing an administrative board’s actions, our review, like that of the district court, is limited to the record below and to whether the board acted arbitrarily or capriciously. McCracken v. Fancy, 98 Nev. 30, 31, 639 P.2d 552, 553 (1982). The record in this case reveals several instances of arbitrary and capricious action by the respondent. In addition to its premature curtailment of appellant’s cross-examination of Mr. Pipes, the Board refused to allow Bivins to call witnesses or cross-examine other witnesses presented by Pipes Paving. It improperly cut off the examination of witnesses who were called. Documents which may have been relevant to appellant’s defense were not admitted. The totality of these incidents reinforces our opinion that reversal is warranted.
The record in this case leaves us with the impression that respondent was more concerned with conforming to the time allotment it had established for conducting the hearing than with affording due process to the parties. The procedural rights of parties before an administrative body cannot be made to suffer for reasons of convenience or expediency. Checker, Inc. v. Public Serv. Comm’n, 84 Nev. at 634, 466 P.2d at 988.
We are also troubled by the Board’s assumption of what was essentially a judicial role in the resolution of this dispute. Its suspension of appellant’s contractor’s license pending payment of [284]*284Pipes Paving’s claim was tantamount to the award of contract damages in a contested case. The Board does not have the authority to impose damages upon parties subject to its licensing authority. See NRS 624.300(1). The parties’ claims and counterclaims regarding their contract raised legal issues properly resolvable only by a court of law, if not by the parties themselves. We trust the Board will be mindful of these implications in its future decision-making.
Accordingly, we believe the court below erred in dismissing appellant’s petition for judicial review.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
809 P.2d 1268, 107 Nev. 281, 1991 Nev. LEXIS 40, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bivins-construction-v-state-contractors-board-nev-1991.