Biomass One, L.P. v. S-P Construction

799 P.2d 152, 103 Or. App. 521, 1990 Ore. App. LEXIS 1292
Court of Appeals of Oregon·Decided October 3, 1990·No. 87-1724-J-2; CA A61560·Published·Cited by 13 cases

Opinion

*524 RIGGS, J.

S-P Construction and Aetna Insurance Co. (Aetna) appeal a summary judgment against them on their third party complaint and the award of attorney fees to Industrial Indemnity Company (IIC). Bulk Handling Systems (BHS) and IIC cross-appeal the amount of attorney fees that they were awarded. We affirm on the appeal and on the cross-appeal.

S-P Construction (plaintiff) 1 was employed by Biomass One, L.P. (Biomass One), as the general contractor to construct a power plant. Plaintiff subcontracted with BHS to manufacture and install a fuel handling system for the power plant. IIC issued a surety bond to BHS in connection with the Biomass One project.

Biomass One and others brought an action against plaintiff, Aetna and others alleging that plaintiff had breached its contract for the construction of the power plant. Plaintiff filed a third party claim against BHS and IIC, BHS’s surety, alleging that BHS is liable for any of plaintiffs liability to Biomass One for defects in the fuel handling system manufactured and installed by BHS. The trial court granted a summary judgment to BHS and IIC against plaintiff on the ground that the claim against them had not been brought within the time provided in the subcontract. Plaintiff appeals from that judgment. The trial court awarded attorney fees to BHS and IIC; plaintiff also appeals IIC’s entitlement to attorney fees. BHS and IIC cross-appeal the amount of attorney fees, claiming that they are entitled to more than the trial court awarded.

The trial court granted the summary judgment on the basis of paragraph 23 of the subcontract, which provides, in part:

*525 “Limitation of Time for Commencement of Claims - SubContractor hereby agrees that any claim or question arising under the terms of this Contract, whether directly or indirectly, and as to which Sub-Contractor may wish to institute arbitration proceedings pursuant to the provision of this contract shall be barred unless asserted by Sub-Contractor of [sic] the commencement of such arbitration proceedings pursuant to the terms of this contract within six months after any inaction the parties do further agree that any claim or cause of action of any kind arising out of or connected with this Contract, directly or indirectly, shall further be barred with respect to the institution of proceedings in a court of law unless asserted by the commencement of an action within one year after any inaction or omission or the occurrence of any matter to which such claim or cause of action relates.”

The trial court concluded that that paragraph required plaintiff to bring its action within one year after BHS had ceased performance. Plaintiff argues that the paragraph is a single, unambiguous sentence and that the time limitation for bringing an action applies only to the subcontractor, BHS, not to it as the general contractor. In the alternative, it argues that, if the provision is ambiguous, the intent of the parties is a question of fact that precludes a summary judgment.

A contract provision is ambiguous if it “has no definite significance or if it is capable of more than one sensible and reasonable interpretation.” Oakridge Cablevision v. First Interstate Bank, 65 Or App 640, 646, 673 P2d 532 (1983). A provision is not ambiguous simply because the parties disagree as to its interpretation. Port of Portland v. Water Quality Insurance Syndicate, 796 F2d 1188, 1194 (9th Cir 1986).

The provision cannot reasonably be interpreted as ambiguous because of a lack of punctuation that is obviously a typographical error. 2 “[P]unctuation or the absence of punctuation will not of itself create ambiguity.” Mattison, Inc. v. W. F. Larson, Inc., 529 SW2d 271, 273 (Tex Civ App 1975); accord American Fruit Purveyors v. Avis Rent-A-Car Systems, *526 118 Ga App 840, 165 SE2d 879 (1968). The sentence is readable only if a semicolon is inserted after the phrase “within six months after any inaction” and before “the parties do further agree.” Without that punctuation, the sentence is not ambiguous; it just makes no sense. When punctuation is inserted, the sentence is capable of only one sensible and reasonable interpretation: The one year limitation applies to both plaintiff and BHS.

Plaintiff next argues that, even if the one year limit applies to it, it filed its third party complaint within that time, because it filed it within a year after Biomass One filed the original complaint in this action. Plaintiff asserts that, because its claim against BHS and IIC is that they are liable for any liability that plaintiff may have to Biomass One, the filing of the Biomass One complaint is the “inaction or omission or the occurrence * * * to which such claim or cause of action relates.” 3 Defendants respond that the claim or cause of action is the alleged breach of the subcontract, which occurred, at the latest, in April, 1986. Thus, they argue, the third party complaint, filed in October, 1987, was not timely.

Plaintiffs claim is denominated “breach of contract.” It alleges that BHS breached the subcontract in various particulars and that, if plaintiff is held liable to Biomass One for those deficiencies, BHS and IIC are liable to it for those damages. Plaintiff argues that the cause of action relates “directly and solely to the claims and causes of action asserted by Biomass One.” The limitation on actions arises from the contract and is governed by the language of the contract. The contract does not measure the time limit from the time that the cause of action accrues; it measures it from the “inaction or omission or the occurrence * * * to which [the] claim or cause of action relates.” The occurrence to which this cause of action relates is defendants’ performance of the contract. When defendants stopped work on the project, any breach, either because of incomplete performance or inadequate performance, was complete. The one year time limit began to run on that date. 4

*527 Plaintiff also argues, on the basis of City of Reedsport v. Hubbard et ux., 202 Or 370, 274 P2d 248 (1954), that, because any damages that it suffered were contingent and not “discernible” until the filing of the third party complaint, it would have been premature to have brought the action before the Biomass One complaint was filed. The case is inapposite. When the action was brought in City of Reedsport, the defendant was not in default under the contract. Therefore, no cause of action yet existed, and the action should have been dismissed as premature. Here, however, the alleged breach occurred before Biomass One brought its action against plaintiff. According to the limitation of action clause in the contract, the time began to run when the breach occurred. Because the action was not brought within one year thereafter, the trial court correctly entered judgment for defendants on the third party complaint. 5

Free access — add to your briefcase to read the full text and ask questions with AI

Biomass One, L.P. v. S-P Construction, 799 P.2d 152, 103 Or. App. 521, 1990 Ore. App. LEXIS 1292 (Or. Ct. App. 1990).

799 P.2d 152 (Biomass One, L.P. v. S-P Construction) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Stonecrest Properties, LLC v. City of Eugene
382 P.3d 539 (Court of Appeals of Oregon, 2016)
Bates v. Bankers Life & Casualty Co.
993 F. Supp. 2d 1318 (D. Oregon, 2014)
Hatkoff v. Portland Adventist Medical Center
287 P.3d 1113 (Court of Appeals of Oregon, 2012)
Nuhome Investments, LLC v. Weller
2003 WY 171 (Wyoming Supreme Court, 2003)
Quality Contractors, Inc. v. Jacobsen
911 P.2d 1268 (Court of Appeals of Oregon, 1996)
Rogue Federal Credit Union v. Phillips
855 P.2d 1146 (Court of Appeals of Oregon, 1993)
National Chiropractic Mutual Insurance v. Morgan
840 P.2d 732 (Court of Appeals of Oregon, 1992)
Biomass One, L.P. v. S-P Construction
799 P.2d 158 (Court of Appeals of Oregon, 1990)