Binnings Construction Co. v. Sewerage District No. I of Parish of St. Charles

174 So. 2d 183, 1965 La. App. LEXIS 4506
CourtLouisiana Court of Appeal
DecidedApril 5, 1965
DocketNo. 1822
StatusPublished
Cited by2 cases

This text of 174 So. 2d 183 (Binnings Construction Co. v. Sewerage District No. I of Parish of St. Charles) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Binnings Construction Co. v. Sewerage District No. I of Parish of St. Charles, 174 So. 2d 183, 1965 La. App. LEXIS 4506 (La. Ct. App. 1965).

Opinion

McBRIDE, Judge.

Plaintiff contractor recovered judgment for the final payment ($37,161.52) on a contract for the construction of a sewerage treatment plant and appurtenances at Nor-co, St. Charles Parish, Louisiana, but its claim for damages ($38,402.84) allegedly occasioned by defendant’s delay of the work and the claim for extra work ($745.-95) were denied. Plaintiff appeals.

Defendant (sometimes hereinafter called the “Board”) advertised for bids during [185]*185January, 1959, which were opened March 4, 1959, plaintiff’s being accepted as the lowest. The formal contract was signed April 30, 1959; it consists of 10 pages of Contract Documents (CD), 18 pages of General Conditions (GC) and 59 pages of Detailed Specifications (DS) ; the cost of the job was stipulated to be $368,535; on the same day, plaintiff furnished its contractor’s performance bond.

Under Section 13.00(GC), the Board was required to issue within 10 days an order to the contractor to proceed with the work, after which the contractor had 10 days to commence the job. Section 2.01 (DS) provides : “The General Conditions are a part -of the Specifications and shall apply to all work done unless these Detailed Specifications specifically take exception to certain items of the General Conditions.”

The Board contemplated the marketing of $725,000 of Sewerage Revenue Bonds and $575,000 of Tax Bonds, the aggregate of which issues 'was the requirement to finance the instant contract and another the Board had entered into.

With reference to finances, Section 2.04 (DS) provides:

“Financing of Project: The attention of all Bidders is called to the fact that after bids are received, Sewerage District No. 1 of the Parish of St. Charles will offer revenue and ad valorem tax bonds for sale to finance the cost of the work; that the award of the contract for the construction of a Sewage Treatment Plant and Appurtenances will he made promptly, hut the contract will he subject to the sale and delivery of said bonds; and that obligations of Sewerage District No. 1 of the Parish of St. Charles under the contract thus awarded will be payable solely from proceeds derived from issuance and sale of said bonds.” (Italics ours.)

Thus, the provisions of Section 2.04(DS) “specifically take exception” to Section 13.00 (GC) which pertains to the time the work order was to issue. This meant that although the contract was to be entered into, any execution of the work was to be suspended and held in abeyance until the bonds could be marketed; otherwise, the Board would be unable to meet the progressive payments under its contracts had it issued work orders prior to the disposal of the bonds. Plaintiff contractor knew and thoroughly understood that the execution of the contract was dependent upon financing as contemplated by Section 2.04(DS) for we find in a letter written by its president to the Board on November 24, 1959, it is stated:

“ * * * we understand that the Board cannot legally issue an unqualified Work Order until the Bonds are actually delivered.” (Italics ours.)

The bond market prevailing between March, 1959, and early 1962 was very poor. To demonstrate the softness of the market, the Board’s attorney who prepared the bond transcript testified that the State Bond and Tax Board (see LSA-R.S. 47:1803) authorized a 5% maximum rate of interest on the bonds; however, prior to their actual delivery to the purchaser in July, 1960, further authorization was obtained from said Board to increase the interest on the revenue bonds to 5j)4%, this to satisfy the bond purchaser.

Certain other matters and events which were beyond the Board’s control came to pass and delayed and hindered the floating of the bonds. Not until July 20, 1960, was the Board able to deliver the bonds to the purchaser. On the same day, the work order called for in Section 13.00(GC) was thereupon issued to the contractor, which commenced the work the following day. The job was accepted by defendant on or about December 15, 1961.

All parties concerned were extremely desirous that the job be proceeded with; particularly was the contractor aggrieved by the delay in the issuance of the work order. [186]*186In many letters it complained to the Board, in several of which the Board was notified that the contractor had suffered and would continue to suffer material damages as the result of the non-issuance of the order.

But, the Board was having its troubles. The majority of the bonds are denominated Sewerage Revenue Bonds, which stipulate that their retirement would be from the collection of charges levied for use of the sewer system. It was well-known that if a user neglected to pay the monthly sewer charge, the Board would be at a distinct disadvantage with regard to collection as it had no remedy to effectively enforce payment. It could not “cut off” the service as other utilities might do. The bond buyers were insisting that the sewer charges be collected for defendant’s account by Water Works District No. 1 of the Parish of St. Charles, and it was not until August 20, 1959, that an agreement could be entered into between defendant and the Water Works District whereby the latter would collect sewer charges along with its water bills, thus establishing an effective means of enforcing collection. The Board’s engineer incorporated the agreement between the two utilities in his Engineering Report and Supplement; he testified he collaborated with the bond buyers in completing the report regarding the retirement schedule of the bonds. The first engineer’s report, August 9, 1958, had to be completely re-worked in order to render the bonds marketable.

On July 10, 1959, another event transpired which militated against immediate disposition of the bonds. The case of Johnson v. Sewerage District No. 2 of the Parish of Caddo was filed in the First Judicial District Court, Parish of Caddo; plaintiffs therein sought to have declared null, void and of no effect a special bond and tax election held by Sewerage District No. 2 of the Parish of Caddo, on the ground, inter alia, that the Board of Supervisors of said sewerage district had no right, power or authority to order and hold said election, since the Police Jury of the Parish of Caddo was the governing authority of said sewer-: age district. All parties interested in the bonds comprehended at once the implications of said litigation. The election which authorized the bonds defendant was seeking to sell had been called and held by defendant’s Board, and a decision in the Johnson case favorable to the plaintiffs therein would have nullified the results of said election and anything done pursuant thereto-. On November 18, 1959, the trial court in the Johnson case held that the special bond and tax election ordered by the Board of Supervisors of Sewerage District No. 2, Parish of Caddo, was illegal and without effect. This, of course, only served to compound everyone’s dismay regarding disposal of the bonds issued by defendant.

Defendant’s Board of Supervisors held a meeting at Norco December 7, 1959; besides the three members of the Board in attendance were the president of plaintiff corporation, a representative of the other contractor, defendant’s engineer, defendant’s attorney and the attorneys representing the proposed bond buyers.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Warfield v. Fink & McDaniel Plumbing & Heating
203 So. 2d 827 (Louisiana Court of Appeal, 1967)

Cite This Page — Counsel Stack

Bluebook (online)
174 So. 2d 183, 1965 La. App. LEXIS 4506, Counsel Stack Legal Research, https://law.counselstack.com/opinion/binnings-construction-co-v-sewerage-district-no-i-of-parish-of-st-lactapp-1965.