Binnings Construction Co. v. Louisiana Life Insurance Co.

139 So. 2d 561, 1962 La. App. LEXIS 1774
CourtLouisiana Court of Appeal
DecidedApril 2, 1962
DocketNo. 256
StatusPublished
Cited by9 cases

This text of 139 So. 2d 561 (Binnings Construction Co. v. Louisiana Life Insurance Co.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Binnings Construction Co. v. Louisiana Life Insurance Co., 139 So. 2d 561, 1962 La. App. LEXIS 1774 (La. Ct. App. 1962).

Opinion

REGAN, Judge.

Plaintiff, B innings Construction Company, Inc., instituted this suit against the defendant, the Louisiana Life Insurance Company, endeavoring to recover the sum of $5,968.10, representing the balance due on a building contract, under which plaintiff renovated the interior and exterior of a building owned by defendant at 2107 Dry-ades Street in the City of New Orleans.

The defendant admitted plaintiff had performed the contract; however, it denied that there was any balance due. Then, assuming the position of plaintiff in re-convention, it asserted that plaintiff was indebted unto it for $20,391.46, which is the total of the following claims :

a.) Liquidated damages for failure to timely complete the exterior of the building $ 1,050.00
b.) Liquidated damages for failure to timely complete the interior of the building 18,285.46
c.) Credit for the substitution of obeche plywood for white birch 756.32
d.) Damage to draperies caused by leak in plumbing due to plaintiff’s faulty workmanship 300.00
e.) Cost of repairing plumbing leak 665.00

From a judgment awarding plaintiff the sum of $4,246.78, which recognized the validity of all of defendant’s claims in reconvention other than the two for liquidated damages, the defendant has appealed. The plaintiff answered the appeal, asserting that the trial judge improperly recognized defendant’s claim in reconvention.

The contract which is the subject of this litigation totalled $131,005.70 and the payment to the contractor was $125,037.60, leaving a balance due of $5,968.10. It does not appear that this balance is contested. Defendant, in effect, admits the balance should have been due, but asserts it is more than offset by liquidated damages and credits due under the contract.

The question of paramount importance posed for our consideration by virtue of this appeal is whether the trial judge properly rejected defendant’s claim for liquidated damages.

In view of the fact that the contract contains different conditions relating ' to the renovation of the interior and the exterior of the building, for the sake of simplicity, we shall discuss each separately.

[563]*563With respect to the exterior work, the pertinent provisions of the building contract, executed on January 22, 1957, read:

“All work on the exterior of the building, including all stone and granite facing, aluminum louvers and trims, ceramic tile panels, aluminum entrances, stairs and stair halls shall be completed before March 18, 1957.”
and
“Should the contractor fail to substantially complete that portion of the work on the exterior of the building and the stairs as stipulated under Article (2) Item (1) on or before March 18, 1957 both parties to the contract mutually agree that the contractor shall pay the Owner as acknowledged liquidated damages the sum of twenty five dollars ($25.00) for each and every day he is delinquent, which amount shall be reported by architect, who will deduct same from any balance due * * *."

It is conceded by both litigants herein that time was of the essence in completion of the exterior of the building and the stairs. The date of March 18, 1957 was the stated deadline since the defendant owner was to host a national insurance convention, scheduled March 18th through the 20th.

Work commenced during the early part of February and shortly thereafter the owner and architect, Edward Tsoi, advised plaintiff that it wished to import a ceramic tile from Italy to be used on the building’s exterior, which was a change from the tile the architect had originally specified. The contractor advised that importing the material may cause a four to six week delay; despite this knowledge the owner still insisted upon its use.

On March 14, 1957, Tsoi inspected the job and thereafter addressed a letter to plaintiff, in which he observed that plaintiff would not complete the exterior work by March 18 as the contract required. He wrote that he intended to deduct liquidated damages of $25 per day for each day the plaintiff failed to complete the renovation thereafter; however, he made this concession :

“It is understood that you will not be penalized for the delay on the ceramic tile panel, since we gave you permission to ship this material from Italy. You will also be given credit for days with inclement weather when no exterior work could properly be done.”

Counsel for defendant asserts that the exterior was not finished until April 29, 1957; however, plaintiff contends it had been finished by March 29, 1957.

Plaintiff’s president, Clem Binnings, testified that the exterior had been substantially completed by March 29th, and his testimony was supported by two subcontractors, Henry Favrot, who did the stone-masonry work, and William Johnson, who painted the plywood paneling in the stair hallways, which, we reiterate for the purpose of clarity, was included in that portion of the contract relating to exterior work.

Defendant bases its assertion that the exterior was not finished until April 29, 1957, upon the testimony of Tsoi, who insists that the lumber wholesaler shipped an inferior grade of paneling, which was returned and a substitute therefor had to be selected. Obeche was substituted for white-birch plywood and Tsoi contends that he did not even see the sample of obeche until April 2, 1957. Tsoi pointed out that the material then had to be ordered, delivered and installed before the paint could' be applied thereto. Therefore, this portion of the exterior contract could not have been completed on March 29th.

We are compelled to conclude that the exterior was completed by March 29, 1957, since the subcontractors not only testified that the work was completed at that time but also furnished invoices which indi[564]*564cated the jobs had been performed during March of 1957.

Thus, the contractor finished the job eleven days later than the deadline set in the contract and all parties hereto admit that time was of the essence in this instance. Ordinarily, we would be compelled to enforce the penalty clause in the contract, even though the architect neither deducted these damages from his final payment or put plaintiff in default, since our jurisprudence is well settled to the effect that an obligee need not place an obligor in default on a contract before enforcing the penalty clause of a contract where time is of the essence.1

However, in this case the evidence preponderates to the effect that the contractor was delayed in performance by the substitution of imported ceramic tile and by inclement weather, and the architect recognized these delays had occurred in his letter of March 14th and waived penalties therefor. Since performance was only eleven days late, we will not impose the liquidated damages upon plaintiff in the absence of proof to establish how many days delay was occasioned by inclement weather and how many by the delay in the shipment of the tile, in view of the fact that defendant has admitted some delay.

Defendant’s claim for the balance of the liquidated damages is predicated upon the assertion that plaintiff breached that part of the contract which specified that the interior would be completely renovated by July 5, 1957.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

O & M Construction, Inc. v. State, Division of Administration
576 So. 2d 1030 (Louisiana Court of Appeal, 1991)
O & M CONST. v. State, Div. of Admin.
576 So. 2d 1030 (Louisiana Court of Appeal, 1991)
North Central Utilities, Inc. v. East Columbia Water District
497 So. 2d 326 (Louisiana Court of Appeal, 1986)
Pelican Elec. Contractors v. Neumeyer
419 So. 2d 1 (Louisiana Court of Appeal, 1982)
Ray v. Peeples
387 So. 2d 1303 (Louisiana Court of Appeal, 1980)
Howard L. Makofsky, Jr. v. Raymond C. Cunningham, II
576 F.2d 1223 (Fifth Circuit, 1978)
Delta Paving Company v. Woolridge
209 So. 2d 581 (Louisiana Court of Appeal, 1968)
Southern Construction Co. v. Housing Authority of Opelousas
189 So. 2d 454 (Louisiana Court of Appeal, 1966)
Brooks v. Neyrey
167 So. 2d 400 (Louisiana Court of Appeal, 1964)

Cite This Page — Counsel Stack

Bluebook (online)
139 So. 2d 561, 1962 La. App. LEXIS 1774, Counsel Stack Legal Research, https://law.counselstack.com/opinion/binnings-construction-co-v-louisiana-life-insurance-co-lactapp-1962.