Billy J. Davis, Gary Davis, and B.J. David Builder, Inc. v. John Crockett and Jennifer Crockett

Court of Appeals of Texas·Decided October 13, 2022·No. 13-21-00326-CV·Published

Opinion

NUMBER 13-21-00326-CV

COURT OF APPEALS

THIRTEENTH DISTRICT OF TEXAS

CORPUS CHRISTI – EDINBURG

BILLY J. DAVIS, GARY DAVIS, AND B.J. DAVIS BUILDER, INC., Appellants,

v.

JOHN CROCKETT AND JENNIFER CROCKETT, Appellees.

On appeal from the 24th District Court of Victoria County, Texas.

MEMORANDUM OPINION

Before Chief Justice Contreras and Justices Benavides and Tijerina Memorandum Opinion by Justice Benavides

In this construction dispute, appellants Billy J. Davis, Gary Davis, and B.J. Davis

Builder, Inc. appeal from summary judgment entered in favor of appellees John and Jennifer Crockett that was based, in part, on appellants’ deemed admissions. As a

preliminary matter, appellants now question whether the judgment was a final appealable

judgment. To the extent the judgment was final, appellants contend summary judgment

was improper because: (1) the trial court abused its discretion in denying appellants’

motion to withdraw the deemed admissions; (2) regardless, the evidence was insufficient

to support various aspects of the judgment; (3) the trial court improperly rendered

judgment against the individual appellants for damages caused by the corporation; (4) the

damages awarded against the individual appellants, including attorney fees, were

otherwise excessive and not supported by competent evidence; and (5) the summary

judgment hearing was held without appellants’ trial counsel, who did not receive notice of

the hearing.1 We reverse and remand.

I. BACKGROUND

B.J. Davis Builder Inc. (the Company) is a Texas corporation in the residential

construction business. Billy J. Davis (B.J.) is the Company’s president and chief operating

officer, and his son, Gary Davis, served as vice president during the relevant period.

According to the Crocketts’ live pleading, in 2017, they contracted with the

Company for the construction of a new home in Victoria, Texas. Shortly after the Crocketts

moved in, cracks began appearing throughout the interior and exterior of the house, and

doors began to stick and not latch. The Crocketts retained an independent engineer who

“determined that the foundation has experienced downward movement in the center of

the residence due to inadequate compaction of the soil on the lot prior to the foundation

1In their brief, appellants have listed eight issues, several of which are multifarious and repetitive. We have reorganized and consolidated some of the issues for clarity. 2 being poured by [the Company].”

In May of 2019, the Company and the Crocketts entered a new agreement

whereby, among other terms, the Company agreed to buy back the house for the

purchase price, build the Crocketts a new house, and finance the new construction. As

part of the agreement, the Crocketts paid the Company $12,197.50 for changes and

upgrades to the new house.

After several months of minimal progress on the new construction and

unsatisfactory explanations for the delays, the Crocketts sent the Company a formal

notice of default. When the Company failed to respond to the notice or account for the

twelve-thousand-dollar payment, the Crocketts filed suit against the Company and its two

officers on March 26, 2020. According to the petition, when Gary negotiated the new

contract on behalf of the Company, he knew the Company was financially incapable of

performing the agreement because the Company had defaulted on other contracts with

customers and failed to pay subcontractors, resulting in liens against those properties.

The Crocketts’ claims included breach of contract and warranty and a request for

an accounting against the Company and negligent misrepresentation against B.J. and

Gary. Against all three appellants, the Crocketts alleged violations of the Texas Deceptive

Trade Practices Act and Texas Construction Trust Fund Statute; fraudulent inducement,

common law fraud, and fraud in a real estate transaction; and breach of fiduciary duty.

The petition was accompanied by forty-nine requests for admissions, many of

which asked appellants to admit liability under the Crocketts’ various theories of recovery.

For example, request number twenty-five asked: “Admit that [the Company] knowingly

3 made material misrepresentations of fact to the Crocketts about [the Company’s] ability

to complete the Contract attached as Exhibit A.”

Appellants’ then-counsel filed an original answer with a general denial but failed to

respond to the Crocketts’ requests for admissions. Approximately two months later, the

Crocketts filed a motion for partial summary judgment, contending that appellants’ liability

on each claim had been conclusively established by their deemed admissions. The

Crocketts further argued that appellants were precluded from offering any evidence

contrary to their admissions.

Within a week, appellants filed a motion to substitute counsel and a motion to

withdraw the deemed admissions. The motion to withdraw explained that appellants’

original counsel “failed to observe that the [Crocketts] had submitted a Request for

Disclosure and Requests for Admissions attached to the original petition and that a time

requirement for response to those items was in play.” According to appellants, their failure

to timely respond was due to “the oversight of their first counsel . . . rather

than . . . conscious indifference.” Along with the motion, appellants included responses to

the requests for admissions, which, unsurprisingly, denied the Crocketts’ various requests

to admit liability. The Crocketts opposed the motion to withdraw, primarily arguing that

appellants failed to demonstrate good cause with evidence, such as an affidavit from their

counsel.

Several months later, on October 26, 2020, the trial court considered the

competing motions during a hearing. The trial court denied appellants’ motion to withdraw

the deemed admissions and granted the Crocketts’ motion for partial summary judgment.

4 The Crocketts later moved for summary judgment on damages. The trial court

granted the motion and entered a written “Final Judgment” awarding the Crocketts

damages, attorney fees, and conditional appellate attorney fees against all three

appellants. The judgment contains the following language:

• This judgment is final and there are no other parties or causes of action outstanding.

• All writs and process for the enforcement and collection of this Judgment or the costs of Court may be issued as necessary.

• Any other relief requested in this case that was not previously granted or ordered herein is hereby DENIED.

Thereafter, appellants filed a verified motion for new trial, reiterating that they did

not timely respond to the Crocketts’ requests for admissions only because their original

counsel “overlooked” them. The trial court denied the motion, and this appeal ensued.

II. FINALITY

By what we consider to be their first issue, appellants question whether the

judgment was final and appealable. While acknowledging that the judgment contains

some finality language, appellants nonetheless contend in their brief that such language

is not “clear and unequivocal” because the judgment lacks an express statement that the

judgment is “appealable.” We find that the judgment is final and that we therefore have

jurisdiction over the appeal.

A. Applicable Law

Free access — add to your briefcase to read the full text and ask questions with AI

Billy J. Davis, Gary Davis, and B.J. David Builder, Inc. v. John Crockett and Jennifer Crockett, (Tex. Ct. App. 2022).

Billy J. Davis, Gary Davis, and B.J. David Builder, Inc. v. John Crockett and Jennifer Crockett (Billy J. Davis, Gary Davis, and B.J. David Builder, Inc. v. John Crockett and Jennifer Crockett) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Wheeler v. Green
157 S.W.3d 439 (Texas Supreme Court, 2005)
In Re Burlington Coat Factory Warehouse of McAllen, Inc.
167 S.W.3d 827 (Texas Supreme Court, 2005)
United States Fidelity & Guaranty Co. v. Goudeau
272 S.W.3d 603 (Texas Supreme Court, 2008)
Qwest Communications Corp. v. AT & T CORP.
24 S.W.3d 334 (Texas Supreme Court, 2000)
Morgan v. Timmers Chevrolet, Inc.
1 S.W.3d 803 (Court of Appeals of Texas, 1999)
Lehmann v. Har-Con Corp.
39 S.W.3d 191 (Texas Supreme Court, 2001)
Armstrong v. Collin County Bail Bond Board
233 S.W.3d 57 (Court of Appeals of Texas, 2007)
North River Insurance Co. of New Jersey v. Greene
824 S.W.2d 697 (Court of Appeals of Texas, 1992)
Young v. Hodde
682 S.W.2d 236 (Texas Supreme Court, 1984)
Time Warner, Inc. and Time Warner Cable, LLC v. Dulio Gonzalez
441 S.W.3d 661 (Court of Appeals of Texas, 2014)
Carpenter v. Cimarron Hydrocarbons Corp.
98 S.W.3d 682 (Texas Supreme Court, 2002)
Marino v. King
355 S.W.3d 629 (Texas Supreme Court, 2011)
In re Roman
554 S.W.3d 73 (Court of Appeals of Texas, 2018)