Bill's Coal Co. v. Board of Public Utilities

682 F.2d 883, 34 U.C.C. Rep. Serv. (West) 166
CourtCourt of Appeals for the Tenth Circuit
DecidedJuly 6, 1982
DocketNos. 82-1297, 82-1303
StatusPublished
Cited by1 cases

This text of 682 F.2d 883 (Bill's Coal Co. v. Board of Public Utilities) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bill's Coal Co. v. Board of Public Utilities, 682 F.2d 883, 34 U.C.C. Rep. Serv. (West) 166 (10th Cir. 1982).

Opinion

LOGAN, Circuit Judge.

Bill’s Coal Company, Inc. and related parties (“Bill’s Coal”) appeal the trial court’s order dissolving an injunction it previously had issued compelling the Board of Utilities of the City of Springfield, Missouri (“the Utility”) to continue purchasing its coal requirements from Bill’s Coal in accord with the long-term contract the Utility entered [884]*884into with Bill’s Coal in 1970, as amended, clarified, and restated in 1979. In March 1980 the Utility informed Bill’s Coal it was invoking the contract’s termination clause. Bill’s Coal responded by bringing this diversity action charging the Utility with breach of contract, and requesting damages and injunctive relief.

With the parties’ agreement, the trial court granted an injunction requiring both parties to perform under the contract pending further developments. The parties agreed to try the dispute to the court, which conducted the proceedings in three phases. At the end of the trial’s second phase, the court granted the Utility’s motion to dissolve the injunction because it found Bill’s Coal had committed a bad faith breach and repudiation of the contract when it repeatedly urged an interpretation of the termination clause it knew was contrary to the parties’ intent when they signed the 1979 contract amendment. Bill’s Coal appealed the order dissolving the injunction, which it has a right to do even though the litigation has not yet ended. See 28 U.S.C. § 1292(a). We ordered the appeal accelerated and, in the interim, ordered the injunction restored.

As amended, the contract calls for Bill’s Coal to furnish all coal the Utility requires for its operations, with a specified annual minimum of 495,000 tons, and a maximum of 605,000 tons. By the end of each calendar year, Bill’s Coal must tell the Utility what price it will charge for the fiscal year beginning the following April 1. The termination clause provides that after receiving Bill’s Coal’s price quote, the Utility has until the end of March to solicit bids from other coal companies. If a company able to meet the contract specifications submits a bid at least 25% under Bill’s Coal’s price, the Utility can terminate its contract with Bill’s Coal effective March 31; if the bid is at least 15% less, the effective date of termination will be the following March 31. The termination clause provides that if invoked, Bill’s Coal can require the Utility to provide written evidence of the bid that allows it to terminate the contract.

The contract provides Bill’s Coal is to quote its price F.O.B. its Garland, Kansas mine. The Utility then pays for transporting the coal to Springfield, Missouri. The trial court’s “bad faith” finding arose with regard to language in the termination clause that requires the price comparison to be between Bill’s Coal’s quoted price and a competitor’s “delivered price.” Both Bill’s Coal and the Utility agree they understood the comparison was to be between the price Bill’s Coal quoted F.O.B. Garland plus the freight costs the Utility could expect to incur, and the price the competitor quoted plus the freight costs the Utility could expect to incur, j.e., in both cases the total costs delivered to the Utility’s coal yard in Springfield. However, apparently with an eye toward possible litigation or compromise of various disagreements between the parties over contract terms, Bill’s Coal, at its attorney’s suggestion, took the “position” — -which it maintained through the early stages of the litigation — that according to the contract, the Utility could not invoke the termination clause unless a competitor’s bid plus the expected freight costs for delivery to Springfield was at least 15% less than Bill’s Coal’s price F.O.B. Garland, without any addition for freight costs from Garland. When Bill’s Coal expressed that view to the Utility’s general manager, the general manager rejected the interpretation and said if Bill’s Coal maintained that position, he would “see them in court” — which he did.

After receiving Bill’s Coal’s price quote for the fiscal year commencing April 1, 1980, and the bids solicited from other coal companies, the Utility claimed the bids it received gave it a right to terminate its contract with Bill’s Coal. It notified Bill’s Coal it was exercising its right to terminate the contract effective March 31 of the subsequent year, 1981 (the 15% option). Apparently unsure of its position, the Utility simultaneously brought a declaratory relief action to determine its rights and obligations under the contract. Immediately thereafter, Bill’s Coal filed suit, claiming the Utility had breached the contract, and the Utility raised the same charge in a [885]*885counterclaim. The declaratory judgment action and the two breach of contract allegations were consolidated for trial in three phases: Phase I to interpret the 1979 amended and restated agreement; Phase II to determine whether either party was in breach; and Phase III to calculate any damages due.

The parties have agreed that Missouri law applies to this action. During discovery, Bill’s Coal inadvertently gave the Utility a document setting forth the attorney’s plan for adopting the “position” with respect to interpreting the termination clause. The Utility then added to its counterclaim a cause of action for breach of the obligation to act in good faith, which the Uniform Commercial Code (UCC) implies in all contracts. See 20A Mo.Ann.Stat. § 400.-1-203 (Vernon).

At the end of Phase I of the trial, the court found that the termination clause was ambiguous and that the parties intended to compare Bill’s Coal’s price plus freight to Springfield with the price quoted by a competitor plus freight. At the end of Phase II of the trial, the court ordered the injunction dissolved, even though it found that Bill’s Coal’s occasional shipments of substandard coal were not a material breach of the contract, and that the Utility had not properly exercised the contract’s termination clause — the only issues litigated other than the allegation based upon Bill’s Coal’s “position” on the bid price required for termination. The court lifted the injunction because it concluded that Bill’s Coal’s “position” was unjustified; that if the Utility had accepted the interpretation Bill’s Coal asserted, the Utility would have found it virtually impossible to exercise the termination clause; and that Bill’s Coal had adopted the “position” in bad faith. The court found that the plan was a breach of the good faith obligation and, furthermore, amounted to a repudiation of the contract because it manifested an intention not to abide by the terms of the contract. The trial court concluded that whether viewing the “position” either as a breach or a repudiation, the Utility was entitled to the remedy of cancelling the contract. Therefore, the court granted the Utility’s motion to dissolve the injunction.

Bill’s Coal raises three objections to the court’s dissolution of the injunction because of a bad faith breach and repudiation. First, Bill’s Coal contends Missouri courts have not and would not recognize a right of action based on a contracting party’s failure to comply with the UCC’s good faith obligation. Second, because the trial court found Bill’s Coal’s interpretation of the termination clause was “plausible,”1 the court erred in concluding Bill’s Coal had acted in bad faith.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
682 F.2d 883, 34 U.C.C. Rep. Serv. (West) 166, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bills-coal-co-v-board-of-public-utilities-ca10-1982.