Big H Construction, Inc. v. Richard S. Hensley

Court of Appeals of Texas·Decided March 31, 2011·No. 01-10-00379-CV·Published

Opinion

Opinion issued March 31, 2011.   

In The

Court of Appeals

For The

First District of Texas

————————————

NO. 01-10-00379-CV

———————————

Big H Construction, Inc., Appellant

V.

Richard S. Hensley, Appellee

On Appeal from the County Court at Law Number Three

Galveston County, Texas

Trial Court Case No. 61,298

MEMORANDUM OPINION

          In this construction contract dispute, Big H Construction, Inc. appeals a judgment granted in favor of Richard and Katherine Hensley.  Big H Construction contends that the trial court erred in granting a summary judgment under section 53.160 of the Texas Property Code on the day of trial because it did not receive timely notice of the hearing on the motion.  See Tex. Prop. Code Ann. § 53.160 (West 2009).  We agree.  We therefore reverse and remand. 

Background

          In September 2007, Big H Construction and Richard Hensley executed a written contract, in which Big H Construction agreed to improve the Hensley residence in exchange for $3,000.  Richard Hensley made a down payment of $1,500 and agreed to pay another $1,500 when Big H Construction completed its work.  In October 2007, Big H Construction filed an affidavit with the Galveston County Clerk to perfect a mechanic’s and materialman’s lien of $1,500 on the Hensley residence.  In the affidavit, the president of Big H Construction averred that Richard Hensley had failed to pay the $1,500 balance due on the contract, even though Big H Construction had completed the improvements.    

          In August 2009, the Hensleys sued for a declaratory judgment to set aside Big H Construction’s lien affidavit and for attorney’s fees.   Big H Construction filed a general denial and asserted counterclaims against Richard Hensley based on his failure to pay the outstanding $1,500 on the contract and on the theory of quantum meruit for improvements that it made to the Hensley residence.  The Hensleys answered the counterclaims, arguing that the contract was void.  Big H Construction requested a jury trial, and the court set the case for trial in March 2010.     

          On March 9, 2010, the Hensleys filed a summary motion under section 53.160 of the Texas Property Code, asking that the trial court declare Big H Construction’s lien and contract invalid and unenforceable.  See Tex. Prop. Code Ann. § 53.160 (West 2009) (allowing party objecting to mechanic’s and materialman’s lien as invalid or unenforceable to file summary motion to remove lien).  On the same day, they allegedly served Big H Construction with the motion.  In the motion, the Hensleys contended that the lien was invalid and unenforceable because: (1) Katherine Hensley did not also sign the contract for the improvement on their residence, as section 53.254(c) of the Texas Property Code requires, and (2) Big H Construction did not file the contract with the county clerk, as section 53.254(e) of the Texas Property Code requires.  See Tex. Prop. Code Ann.                  § 53.254 (West 2009).  They also asserted that Big H Construction also did not deliver a disclosure statement to Richard Hensley before he executed the contract, as section 53.255 of the Texas Property Code requires.  See Tex. Prop. Code Ann. § 53.255 (West 2009).  

          Eight days later, on March 17, 2010, the date of trial, the trial court held a pretrial hearing and considered the Hensleys’ summary motion.  According to the Hensleys, the only issue for the trial court to decide was the attorney’s fees that they incurred in invalidating the lien.  In response, Big H Construction moved to strike the summary motion because the Hensleys failed to give 21-days’ notice of a hearing on the motion, as section 53.160(c) of the Texas Property Code requires.  See Tex. Prop. Code Ann. § 53.160(c) (West 2009).    

          The trial court denied Big H Construction’s motion to strike in a written order and granted the Hensleys’ summary motion.  The court dismissed the jury panel and held a hearing on the attorney’s fees.  The court entered a judgment in favor of the Hensleys along with findings of fact and conclusions of law.  In the judgment, the court decreed that the contract between the parties was void and unenforceable, and the mechanic’s and materialman’s lien was void.  It also awarded the Hensleys attorney’s fees.

Discussion

Appellate Jurisdiction

          We review issues affecting our appellate jurisdiction sua sponte.  M.O. Dental Lab v. Rape, 139 S.W.3d 671, 673 (Tex. 2004).  Here, the trial court’s judgment does not explicitly address Big H Construction’s quantum meruit claim.  But, at the hearing on their summary

Free access — add to your briefcase to read the full text and ask questions with AI

Big H Construction, Inc. v. Richard S. Hensley, (Tex. Ct. App. 2011).

Big H Construction, Inc. v. Richard S. Hensley (Big H Construction, Inc. v. Richard S. Hensley) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

M.O. Dental Lab v. Rape
139 S.W.3d 671 (Texas Supreme Court, 2004)
White v. Wah
789 S.W.2d 312 (Court of Appeals of Texas, 1990)
May v. Nacogdoches Memorial Hospital
61 S.W.3d 623 (Court of Appeals of Texas, 2001)
Rios v. Texas Bank
948 S.W.2d 30 (Court of Appeals of Texas, 1997)
Lehmann v. Har-Con Corp.
39 S.W.3d 191 (Texas Supreme Court, 2001)
Chadderdon v. Blaschke
988 S.W.2d 387 (Court of Appeals of Texas, 1999)