Big Creek Construction, LTD. v. Jim Sinkule, Individually and as Parent and Next Friend of Brent Sinkule, Carlos Cross, Individually as Parent and Next Friend of Darius Cross, Thomas Buchak, Individually and as Parent and Next Friend of John Buchak, and Tony Brown, Individually and as Parent and Next Friend of Tyler Brown

CourtTexas Court of Appeals, 10th District (Waco)
DecidedJanuary 29, 2026
Docket10-24-00224-CV
StatusPublished

This text of Big Creek Construction, LTD. v. Jim Sinkule, Individually and as Parent and Next Friend of Brent Sinkule, Carlos Cross, Individually as Parent and Next Friend of Darius Cross, Thomas Buchak, Individually and as Parent and Next Friend of John Buchak, and Tony Brown, Individually and as Parent and Next Friend of Tyler Brown (Big Creek Construction, LTD. v. Jim Sinkule, Individually and as Parent and Next Friend of Brent Sinkule, Carlos Cross, Individually as Parent and Next Friend of Darius Cross, Thomas Buchak, Individually and as Parent and Next Friend of John Buchak, and Tony Brown, Individually and as Parent and Next Friend of Tyler Brown) is published on Counsel Stack Legal Research, covering Texas Court of Appeals, 10th District (Waco) primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Big Creek Construction, LTD. v. Jim Sinkule, Individually and as Parent and Next Friend of Brent Sinkule, Carlos Cross, Individually as Parent and Next Friend of Darius Cross, Thomas Buchak, Individually and as Parent and Next Friend of John Buchak, and Tony Brown, Individually and as Parent and Next Friend of Tyler Brown, (Tex. Ct. App. 2026).

Opinion

Court of Appeals Tenth Appellate District of Texas

10-24-00224-CV

Big Creek Construction, Ltd., Appellant

v.

Jim Sinkule, Individually and as Parent and Next Friend of Brent Sinkule, Carlos Cross, Individually as Parent and Next Friend of Darius Cross, Thomas Buchak, Individually and as Parent and Next Friend of John Buchak, and Tony Brown, Individually and as Parent and Next Friend of Tyler Brown, Appellees

On appeal from the 66th District Court of Hill County, Texas Judge Lee Harris, presiding Trial Court Cause No. CV510-21DC

SENIOR JUSTICE GABRIEL delivered the opinion of the Court.

MEMORANDUM OPINION

In this interlocutory appeal, appellant Big Creek Construction, Ltd. [Big

Creek] challenges the trial court’s order denying its No-Evidence and

Traditional Motion for Summary Judgment, filed in this suit brought against

it by the appellees, Jim Sinkule, Individually and as Parent and Next Friend of Brent Sinkule, Carlos Cross, Individually and as Next Friend of Darius

Cross, Thomas Buchak, Individually and as Parent and Next Friend of John

Buchak and Tony Brown, Individually and as Parent and Next Friend of Tyler

Brown. In its first issue, Big Creek contends the trial court erred in denying

its summary judgment motion based on section 97.02 of the Texas Civil and

Practice Remedies Code. 1 In its second issue, Big Creek argues that the trial

court erred in overruling its objections to the affidavit of appellee’s expert, D.

Rowland Lamb. Because we conclude that genuine issues of material fact exist

as to the first issue and that we have no jurisdiction to consider the second

issue on an interlocutory appeal, we overrule issue one, dismiss issue two and

affirm the denial of Big Creek’s motion for summary judgment.

I. FACTUAL AND PROCEDURAL BACKGROUND

The event giving rise to this lawsuit was a single-vehicle accident that

occurred in October 2019 on FM 2114 in Hill County, Texas. The issues on

appeal concern a contract and compliance with that contract. In November

2018, appellant, Big Creek contracted with the Texas Department of

Transportation [TxDOT] to recondition and repave portions of FM 2114 in

McLennan and Hill County, Texas.

1 See TEX. CIV. PRAC. & REM. CODE ANN. §51.014(a)(17) (authorizing an appeal from an interlocutory

order denying a contractor’s motion for summary judgment based on TEX. CIV. PRAC. & REM. CODE ANN. §97.002).

Big Creek Constr., Ltd. v. Jim Sinkule, Ind. and as Parent and Next Friend of B.S. Et al. Page 2 The TxDOT contract with Big Creek contained plans and specifications

for the project. The applicable 2014 TxDOT Standard Specifications included:

b. Sequence of Construction

....

4. In 2-mile roadway sections a. Prep and widen subgrade using excavation and embankment b. Reclaim existing material and spread evenly c. Cement treat d. Construct new flexible and prime coat treatment e. Place temporary pavement markings f. Place temporary seeding

5. When full roadway construction is completed, construct HMA (hot mix asphalt) over full width of roadway, backfill pavement edges as necessary.

The TxDOT contract also included Barricade and Construction Standard

General Notes which made it clear which contracting party was responsible for

making the decisions concerning traffic control plans, barricade development,

design and use and who was responsible for performing the work according to

the directives:

2. The development and design of the Traffic Control Plan (TCP) is the responsibility of the Engineer.

4. The contractor is responsible for installing and maintaining the traffic control devices as shown in the plans. The Contractor may not move or change the approximate location of any device without the approval of the Engineer.

Big Creek Constr., Ltd. v. Jim Sinkule, Ind. and as Parent and Next Friend of B.S. Et al. Page 3 ....

9. As necessary, the Engineer will determine the most appropriate traffic control devices to be used.

10. The Engineer has the final decision on the location of all traffic control devices.

The summary judgment record contains the deposition testimony of Josh

Voiles, the TxDOT area engineer for the area where this accident occurred. He

identified the site of the accident as a bridge referred to as Brushy Creek STR

014. He acknowledged that there was some guardrail damage on bridges

included in this job, but nothing that required replacement of the rail itself.

He also explained that when there was “guard fence damage, it’s a best practice

to - - install some type of delineation or notification, whether that’s barrels or

cones or sometimes a sign.” Voiles testified that Eric Hudson was the TxDOT

inspector on this project who served as the “day-to-day eyes and ears on that

job.” Voiles described the allocation of responsibilities between the engineer,

the inspector and the contractor. He detailed that the TxDOT inspector is

someone “trained and certified in traffic control inspections.” He explained

that Hudson would “drive” the project to inspect for safety issues. When one

was identified, if it was something “standard,” such as the need for installation

of barrels, then the inspector could direct the contractor to perform that task

on behalf of the engineer.

Big Creek Constr., Ltd. v. Jim Sinkule, Ind. and as Parent and Next Friend of B.S. Et al. Page 4 Voiles also testified concerning documentation used by inspectors when

they did their daily inspections. He explained that a daily work report [DWR]

would be generated by an inspector that would document the “general work

that’s going on.” Voiles was shown a DWR for the four days preceding the

accident. On the DWR for October 1, 2019, there was a notation that directions

were given to install guardrail damage “signs where SGT is sagging at

guardrails on Brushy Creek STR 014.” (emphasis added) Voiles was shown

the DWRs from the days following October 1st, but preceding the accident, and

from his review, it appeared as though the inspector was looking at the

guardrails daily and made no notations that there was any further issue with

the sagging guardrail. He also expressed that the reports did not reflect any

indication that the directions of October 1st had not been complied with.

However, Voiles did point out a compliance issue on a separate concern. He

acknowledged that on October 4th there were “similar directions” to remove

the windrow material under the guardrail as given the day before.

Voiles explained that TxDOT had a Work Zone Awareness review team

that would pick “a couple of random jobs a month” to serve as an extra set of

eyes on a job to look for minor issues. This team would prepare a report that

TxDOT would then share with the contractors to get issues resolved that had

not been resolved. When presented with a Work Zone Awareness team report

Big Creek Constr., Ltd. v. Jim Sinkule, Ind. and as Parent and Next Friend of B.S. Et al. Page 5 dated October 2nd, Voiles testified that the report showed no indication of any

issues with Brushy Creek STR 014 on that date.

Voiles was shown pictures of the bridge at Brushy Creek STR 014 taken

after the accident on October 5, 2019. He agreed that the pictures depicted

orange barrels with white reflective stripes at each end of the bridge. Voiles

explained that the intent of orange barrels is to “delineate that there is

something there . . .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ford Motor Co. v. Ridgway
135 S.W.3d 598 (Texas Supreme Court, 2004)
Valence Operating Co. v. Dorsett
164 S.W.3d 656 (Texas Supreme Court, 2005)
MacK Trucks, Inc. v. Tamez
206 S.W.3d 572 (Texas Supreme Court, 2006)
Texas a & M University System v. Koseoglu
233 S.W.3d 835 (Texas Supreme Court, 2007)
Houston Municipal Employees Pension System v. Ferrell
248 S.W.3d 151 (Texas Supreme Court, 2007)
Hamilton v. Wilson
249 S.W.3d 425 (Texas Supreme Court, 2008)
Timpte Industries, Inc. v. Gish
286 S.W.3d 306 (Texas Supreme Court, 2009)
Travelers Insurance Co. v. Joachim
315 S.W.3d 860 (Texas Supreme Court, 2010)
Centeq Realty, Inc. v. Siegler
899 S.W.2d 195 (Texas Supreme Court, 1995)
Garcia v. State
17 S.W.3d 1 (Court of Appeals of Texas, 1999)
Quantum Chemical Corp. v. Toennies
47 S.W.3d 473 (Texas Supreme Court, 2001)
Cathey v. Booth
900 S.W.2d 339 (Texas Supreme Court, 1995)
Nowak v. DAS Investment Corp.
110 S.W.3d 677 (Court of Appeals of Texas, 2003)
Nixon v. Mr. Property Management Co.
690 S.W.2d 546 (Texas Supreme Court, 1985)
City of Keller v. Wilson
168 S.W.3d 802 (Texas Supreme Court, 2005)
Walzier v. Newton
27 S.W.3d 561 (Court of Appeals of Texas, 2000)
King Ranch, Inc. v. Chapman
118 S.W.3d 742 (Texas Supreme Court, 2003)
KPMG Peat Marwick v. Harrison County Housing Finance Corp.
988 S.W.2d 746 (Texas Supreme Court, 1999)
Federal Deposit Insurance Corp. v. Lenk
361 S.W.3d 602 (Texas Supreme Court, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
Big Creek Construction, LTD. v. Jim Sinkule, Individually and as Parent and Next Friend of Brent Sinkule, Carlos Cross, Individually as Parent and Next Friend of Darius Cross, Thomas Buchak, Individually and as Parent and Next Friend of John Buchak, and Tony Brown, Individually and as Parent and Next Friend of Tyler Brown, Counsel Stack Legal Research, https://law.counselstack.com/opinion/big-creek-construction-ltd-v-jim-sinkule-individually-and-as-parent-and-txctapp10-2026.