Betzel v. State Farm Lloyds

480 F.3d 704, 67 Fed. R. Serv. 3d 792, 2007 U.S. App. LEXIS 4581, 2007 WL 603036
CourtCourt of Appeals for the Fifth Circuit
DecidedFebruary 28, 2007
Docket05-10903
StatusPublished
Cited by90 cases

This text of 480 F.3d 704 (Betzel v. State Farm Lloyds) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Betzel v. State Farm Lloyds, 480 F.3d 704, 67 Fed. R. Serv. 3d 792, 2007 U.S. App. LEXIS 4581, 2007 WL 603036 (5th Cir. 2007).

Opinion

PATRICK E. HIGGINBOTHAM, Circuit Judge:

This is a dispute controlled by Texas law between a homeowner and his insured over coverage for a mold-damage claim. Kurt Betzel appeals from a district court order excluding his late-designated expert witnesses and from a district court order granting State Farm’s motion for summary judgment. We reverse and remand.

I

A

Kurt Betzel bought his home in Arlington, Texas in 1991 and insured it with State Farm. In December 2001, Betzel notified State Farm that mold was growing on the sheet rock near his leaking A/C registers. State Farm opened a claim and sent Michael King, an insurance adjuster, to inspect Betzel’s home. King confirmed the A/C leak and found another in the kitchen, for which he opened a second claim. King found mold in several places and noted in the State Farm Activity Log, “We have confirmed that we have a covered loss.” Six months later, State Farm opened a third and fourth claim, one for a shower-drain leak and another for a sewer leak. The first two claims were for losses that occurred while an HO-B policy was in effect. The third and fourth claims were for losses occurring under an HO-162A policy.

Kurt Betzel hired Blackmon Mooring, a company recommended by State Farm, to do the remediation work. After three months of work, and after three failed environmental-clearance tests, Betzel fired Blackmon Mooring. He then hired Paul Frantz, one of his late-designated experts, to finish the job. The house passed its clearance test on December 30, 2002.

With remediation finally complete, Bet-zel hired Jan Matlock, the original builder, *706 to rebuild the house. Matlock is Betzel’s other late-designated expert. State Farm estimated the cost to rebuild Betzel’s house at $23,419.45. Matlock’s estimate of $145,000.00 was much higher — and that was before more mold was discovered.

So Betzel brought Paul Frantz back in, several times, during the re-build to remove the “hidden mold” that Matlock had discovered. Because of these unforeseen problems and because of an increase in the cost of materials, Matlock’s estimate jumped to $212,260.92. State Farm had already paid more than $160,000 to Betzel for remediation, living expenses, and repair. Betzel estimated that another $132,000 would be necessary to finish the work. He hired a lawyer, who sent State Farm a letter, demanding $275,000 as full and final satisfaction of Betzel’s claims. On November 17, 2003, a State Farm claims representative responded by denying further coverage and explaining that “the payments issued are appropriate and sufficient for the necessary remediation and rebuild of Mr. Betzel’s home with regard to covered losses.”

B

Betzel sued State Farm in Tarrant County District Court for breach of the insurance contract, breach of the duty of good faith and fair dealing, and violation of articles 21.21 and 21.55 of the Texas Insurance Code. State Farm removed based on diversity.

On September 28, 2004, the federal district court entered a scheduling order which provided:

Each party shall designate experts by filing a written designation including the name, address, and telephone number of each expert who may be called to testify and make the disclosures required by Fed.R.Civ.P. 26(a)(2) by serving the required written reports at least 120 days before the pretrial conference date .... Strict compliance with the terms of this Order ... is required.

The pretrial conference was originally set for July 5, 2005; Betzel’s designation deadline was therefore March 6, 2005. Nearly three months after that deadline, on May 23, 2005, Betzel filed a motion, opposed by State Farm, styled “Plaintiffs Motion To Allow Opinion Testimony From Certain Witnesses.” Betzel’s motion sought to elicit expert testimony from Matlock and Frantz. This motion came three weeks after State Farm filed its motion for summary judgment; one week after the deadline to file Daubert motions; three days after State Farm had deposed Matlock (as a fact witness); and immediately after State Farm had deposed Frantz (also as a fact witness).

The district court denied the plaintiffs motion on June 10, 2005. Five days later, the district court granted State Farm’s motion for summary judgment, ruling that Betzel had marshaled no evidence to support his contractual claim, because “[t]he only summary judgment evidence plaintiff points to in support of his breach of contract claims is the deposition testimony of his general contractor, Mrs. Matlock, that ‘in her opinion it would cost $212,260 to rebuild the home.’ ” The district court accordingly found no triable issue of fact on the question of cost to repair, since “this court has already ruled that plaintiff may not elicit expert testimony as a result of his failure to comply with the court’s [scheduling order].”

Betzel appeals from the district court’s order excluding his experts and from the district court’s order granting summary judgment to State Farm. 1

*707 II

We hold that the district court abused its discretion in excluding Betzel’s late-designated witnesses. 2 We review such exercises of discretion by considering four factors: “(1) the explanation for the failure to identify the witness; (2) the importance of the testimony; (3) potential prejudice in allowing the testimony; and (4) the availability of a continuance to cure such prejudice.” 3

The first factor plainly favors State Farm. Indeed, Betzel concedes that he offered no explanation to the district court for his failure to timely designate. 4 We take seriously this lack of explanation, having held, for example, that exclusion of expert witnesses “is particularly appropriate” where the party has “failed to provide an adequate explanation for their failure to identify them expert within the designated timetable.” 5 We reverse, nevertheless, because the three remaining factors strongly favor Betzel.

The second factor is the importance of the excluded testimony. Betzel urges that his experts’ testimony is “very important,” although he refuses, of course, to concede that he must lose on summary judgment without it. State Farm responds that the testimony is unimportant because neither expert was even qualified to opine about mold causation.

The expert testimony is essential. Putting aside State Farm’s contention that neither expert is qualified to segregate covered losses from non-covered losses, 6 the two experts are still necessary to Bet-zel’s case, particularly to his proof of the cost to rebuild his house. Without his experts, Betzel cannot prove damages.

Of course, this court has applied this second factor in unexpected ways, sometimes even standing it on its head. In Geiserman, we “assume[d] arguendo

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
480 F.3d 704, 67 Fed. R. Serv. 3d 792, 2007 U.S. App. LEXIS 4581, 2007 WL 603036, Counsel Stack Legal Research, https://law.counselstack.com/opinion/betzel-v-state-farm-lloyds-ca5-2007.