Bethlehem Fabricators, Inc. v. Wills, Taylor & Mafera Corp.

248 A.D. 331, 289 N.Y.S. 96, 1936 N.Y. App. Div. LEXIS 6146
CourtAppellate Division of the Supreme Court of the State of New York
DecidedJuly 2, 1936
StatusPublished
Cited by3 cases

This text of 248 A.D. 331 (Bethlehem Fabricators, Inc. v. Wills, Taylor & Mafera Corp.) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bethlehem Fabricators, Inc. v. Wills, Taylor & Mafera Corp., 248 A.D. 331, 289 N.Y.S. 96, 1936 N.Y. App. Div. LEXIS 6146 (N.Y. Ct. App. 1936).

Opinion

Hagaety, J.

On the 15th day of June, 1933, the non-appealing defendant, Wills, Taylor & Mafera Corporation, hereinafter called the contractor, entered into a construction contract with the State. The plaintiff furnished labor and materials for the fabrication and erection of the structural steel work required and, on the 1st day of October, 1934, filed its hen in the sum of $16,615. The following day the contractor discharged this and two other liens upon application pursuant to subdivision 6 of section 21 of the Lien Law, with the result that the Comptroller of the State retained the sum of $26,000 as the amount claimed by the lienors, plus interest,: costs and expenses. There is no confusion here because of the merged interests of the two alien lienors, as they have stipulated, to waive all rights to become parties to this action. The con- ■ tention of the People is that other and subsequent lienors should' be made parties to this action. Although the appellant states in' its brief that prior as well as subsequent liens were filed, all prior ' hens were discharged or secured by separate funds at the time the contractor made his application in this instance and, of course, it J [333]*333was essential to the granting of the application that moneys commensurate with the amount of all liens then outstanding be retained.

Section 21 of the Lien Law provides eight different methods by which a hen against the amount due a contractor for the construction of a pubhc improvement may be discharged. Three of them deal with the creation of a special fund or security, namely, under the fourth subdivision of section 21, by deposit of a sufficient sum of money; under the fifth, by the fifing of an undertaking, and, under the sixth, that invoked here, by an order directing the Comptroller to retain sufficient moneys, viz.: “ 6. Where a contractor has to his credit with the State or with a municipal corporation, a sum of money by reason of an estimate due and payable to him, and where payment of such estimate is withheld because a notice of hen has been filed against his interest in said money, and where said money is in excess of the amount claimed in the notice of hen, the contractor may apply without notice to the Supreme Court of this State or to any justice thereof or to the county judge of any county, for an order directing the Comptroller of the State or the financial officer or person with whom the hen is filed, to retain from such estimate a sum of money, which shah not be less than the amount claimed by the henor, with interest thereon for one year and such additional amount as the justice deems sufficient to cover all costs and expenses and to immediately pay over the balance of such estimate to the contractor. The amount sq retained shall be held by the Comptroller or such financial officer or other officer or person until the hen is discharged as otherwise provided in this section. The application for the order may be made upon a verified petition or upon other written proofs showing a proper case therefor.”

We are of opinion that the sum of money retained pursuant to this subdivision is earmarked for the discharge of the affected hen and constitutes the sole fund to which the henor may look for payment and to which he has a primary right, to the exclusion of other and subsequent henors. We deem it the equivalent of the fund created pursuant to subdivision 4 of the same section of the Lien Law. In Arrow Iron Works, Inc., v. Greene (260 N. Y. 330) the contractor had proceeded under subdivision 4 of section 21 of the Lien Law by placing on deposit a sum sufficient to cover the outstanding hen and, by so doing, released and obtained a sum of money otherwise due him. It was subsequently adjudged that costs and disbursements and an extra allowance brought the sum due the henor to a greater amount than the deposit, and the henor sought the excess from other funds of the contractor, which funds other henors also claimed. The Court of Appeals held that the henor could look only to the specific fund. Judge Kellogg writes [334]*334(pp. 337, 338): “ The purpose of the provision is to free the moneys remaining payable from the claim of the lienor, so that thereafter the State may safely make payments to the contractor or other lienors, as it may be advised. This result would not be achieved if, after the making of the deposit, the lienor might recover from the general fund the costs and disbursements of a foreclosure action which the deposit was not sufficient to satisfy. The reason that the present plaintiff must suffer rests in the fact that the order of, discharge provided for an insufficient deposit, and from that order the plaintiff took no appeal. We think that the plaintiff may have no other relief than the payment to it of the sum deposited; that neither the ‘ earned ’ nor 1 unearned ’ items, due upon the contract, are subject to any claim by the plaintiff.”

If this be so, then the converse must also be true, and the other lienors, necessarily subsequent in time, who have recourse to the general funds of the contractor, may not also share proportionately in the only fund available to the lienor whose hen created the specific fund. It will be observed that the creation of this fund, working the discharge of the lien as to the balance of the moneys, is accomplished at the instance of and for the benefit of the contractor and is a right which may be exercised by him irrespective of the attitude of the lienor.

In support of its contention that the specific fund is available not only to the lienor whose lien caused its creation but to all other lienors, the appellant relies upon subdivision 4 of section 25, reading: (4) There shall be no priority among labor lienors, as a class or among other lienors as a class, and any moneys available for distribution among lienors of any class shall be distributed pro rata in accordance with their respective valid liens.”

This subdivision is undoubtedly intended to create equality of distribution among lienors irrespective of the time of the filing of the hen, but we are of opinion that its application is of necessity limited to the funds of the contractor that are available for general distribution purposes, and that it is without application to funds that have been earmarked for payment of a specific hen or hens in ' accordance with section 21. The appellant, however, cites authorities in the First and Third Departments to the contrary and in support of its contention, with which we are constrained to disagree.

In International Harvester Co. v. Whelan (247 App. Div.,215) the contractor, as here, procured, under subdivision 6 of section 21 of the Lien Law, a court order authorizing the Comptroller to pay over the balance of certain estimates that remained after deduction of moneys to cover outstanding liens, which deducted sum was to be retained until their discharge. The Third Department holds [335]*335that the henors whose liens were covered by this fund may share therein only proportionately with other henors. The Arrow Iron Works, Inc., Case (supra)

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Alberene Stone Co. v. Board of Education
162 Misc. 659 (New York Supreme Court, 1937)
Hanfgarn v. Mark
249 A.D. 816 (Appellate Division of the Supreme Court of New York, 1937)
Bethlehem Fabricators, Inc. v. Wills, Taylor & Mafera Corp.
5 N.E.2d 187 (New York Court of Appeals, 1936)

Cite This Page — Counsel Stack

Bluebook (online)
248 A.D. 331, 289 N.Y.S. 96, 1936 N.Y. App. Div. LEXIS 6146, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bethlehem-fabricators-inc-v-wills-taylor-mafera-corp-nyappdiv-1936.