Berwind v. Galveston & Houston Investment Co.

50 S.W. 413, 20 Tex. Civ. App. 426, 1899 Tex. App. LEXIS 181
CourtCourt of Appeals of Texas
DecidedFebruary 23, 1899
StatusPublished
Cited by13 cases

This text of 50 S.W. 413 (Berwind v. Galveston & Houston Investment Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Berwind v. Galveston & Houston Investment Co., 50 S.W. 413, 20 Tex. Civ. App. 426, 1899 Tex. App. LEXIS 181 (Tex. Ct. App. 1899).

Opinion

GARRETT, Chief Justice.

This action was brought by the appellant, Edward J. Berwind, against the Houston-and Galveston Investment Company upon certain improvement certificates issued by the city of Houston to the Litho-Carbon Rubber Company for the construction of sidewalks abutting appellee’s property in the Fair Ground addition in the city of Houston, and assigned by said company to the appellant. The work was done under a contract entered into between said Litho-Carbon Rubber Company and the city council, acting under the charter of the city. Appellant prayed for judgment against the appellee for the amount of the certificates, together with interest, costs, and attorney’s fees, and a foreclosure of the lien given by the charter for the payment thereof, alleging also that he was a purchaser of the certificates for a valuable consideration before maturity, and was the legal owner and holder thereof. Appellee’s answer was a general demurrer, general denial, and a special plea denying the authority of the city to issue the certificates, and alleging that the sidewalks built by the contractor were not continuous, connecting, and uninterrupted sidewalks as provided for in the contract, and had not been built in accordance with the specifications therefor; and that the amounts called for in the certificates were more than called for by the contract, plans, and specifications; and that there was a want of consideration. By a supplemental petition the ap *427 pellant demurred to the answer, and also pleaded an estoppel. The case was tried without a jury, and resulted in a judgment against the right of the appellant to recover upon the certificates or for any sum whatever.

By a resolution of the city council of the city of Houston, regularly passed February 11, 1895, after proper reference to the board of public works, as required by the charter, the construction of certain sidewalks was provided for as follows:

“Be it resolved by the city council of Houston:

“Section 1. That it is hereby declared necessary for the public interest that sidewalks be constructed on the following named portions of streets and avenues in the city of Houston where good and sufficient sidewalks of a like character as herein provided do not now exist, viz: West side of Milam Street, from Hadley to Tuam, and on both sides of the following named streets: Milam from Tuam to Stuart, Louisiana from McGown to Stuart, Smith from McGown to Stuart, Brazos from McGown to Elgin, McGown from Main to Brazos, Dennis from Milam to Bagby, Drew from Milam to Burnett, Tuam from Main to Burnett, and Elgin from Main to Brazos.

“Sec. 2. That the sidewalks shall be constructed of stone, cement, or asphalt, and bids shall be solicited for said work to be done according to specifications therefor to be prepared by the city engineer and adopted by the city council.

“Sec. 3. The cost of constructing said improvements, together with the costs of collecting thereof, -shall, as provided in section 24 of the charter of the city of Houston, be wholly defrayed by the owner of the lot or lots, block or blocks, or tracts of land when not divided into lots or blocks, abutting on said portions of said streets and avenues to be so improved, and said improvements shall be paid for in three annual installments of nearly equal amounts not less than $10 each, as may be most convenient.

“Sec. 4. The whole or any portion of the work embraced in this resolution may be included in the same contract or may be divided into separate contracts.”

The resolution was duly advertised in a daily newspaper published in the city of Houston for more than four days, commencing February 13, 1895. The streets were adjacent to each other, and a continuous and connected system of sidewalks was provided for.

After the passage of the resolution the city engineer prepared plans and specifications for the construction of the work in accordance with instructions of the city council given March 11, 1895, and presented them to the council, with the favorable report of the board of pubhc works, and the council adopted them. The plans and specifications provided that the sidewalk pavement should be not less than four inches thick, upon a bed or subgrade regulated and surfaced to the satisfaction of the engineer, and consisting of a layer not less than three inches in depth of hydraulic cement-concrete, over which should be spread rock-asphalt mastic to a thickness of not less than one inch. Specific diree *428 tians were given as to the material to be used, the preparation of the concrete and mastic, the manner of laying the same, and what the character of the finished work should be, but it is not deemed necessary to set out the same more fully here.

On March 11, 1895, the council authorized the mayor to advertise for bids for the construction of the work in accordance with the resolution, bids to be opened March 35, 1895. The advertisement was duly made by publication in a daily newspaper from March 14th until the bids were opened, and on March 35, 1895, the bids were opened by the council and referred to the board of public works, which reported to a meeting held April 1, 1895, and recommended the acceptance of the bid of the LithoCarbon Rubber Company. The report was adopted, and the mayor was authorized to enter into a contract with said company. The contract was executed April 18, 1895, and was in due form for the performance of the work in accordance with the resolution of the council and the plans and specifications of the city engineer. The advertisement for bids required the work to be done according to the specifications prepared by the city engineer, approved by the board of public works, and adopted by the city council March 11, 1895, and one file in the office of the city engineer. On March 18, 1895, pending the advertisement for bids, the specifications adopted March 11, 1895, and which specified the asphalt to be used as “rock asphalt, mastic to consist of natural bituminous limestone, equal to the best imported qualities,” etc., were amended so as to read: “Rock, Trinidad Lake, or other asphalt equally as good in every respect for sidewalk purposes.”

Pending the performance of the work under the contract the case of Higgins v. Bordages, 88 Texas, 455, was finally decided by the Supreme Court holding that assessments for sidewalk improvements were not a lien upon homesteads, and the contractor, in paving the sidewalks mentioned in the resolution, skipped or omitted all parts of sidewalks in front of homesteads except where the owner agreed to pay for the work, and as a consequence the sidewalks were not paved or constructed continuously, but only disconnected parts thereof were constructed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Ranger v. Wier
148 S.W.2d 870 (Court of Appeals of Texas, 1941)
Scanlan v. Continental Inv. Co.
142 S.W.2d 432 (Court of Appeals of Texas, 1940)
Shambaugh v. Anderson
92 S.W.2d 530 (Court of Appeals of Texas, 1936)
Real Estate-Land Title & Trust Co. v. Dildy
92 S.W.2d 318 (Court of Appeals of Texas, 1936)
Uvalde Rock Asphalt Co. v. Langham
68 S.W.2d 646 (Court of Appeals of Texas, 1934)
Webb v. City of Fort Worth Ex Rel. West Texas Const. Co.
23 S.W.2d 791 (Court of Appeals of Texas, 1929)
Harwell v. Jordan Const. Co.
4 S.W.2d 980 (Court of Appeals of Texas, 1928)
Herring v. City of Mexia
290 S.W. 792 (Court of Appeals of Texas, 1926)
City of Lufkin v. Harrell
265 S.W. 179 (Court of Appeals of Texas, 1924)
Manley v. City of Marshfield
172 P. 488 (Oregon Supreme Court, 1918)

Cite This Page — Counsel Stack

Bluebook (online)
50 S.W. 413, 20 Tex. Civ. App. 426, 1899 Tex. App. LEXIS 181, Counsel Stack Legal Research, https://law.counselstack.com/opinion/berwind-v-galveston-houston-investment-co-texapp-1899.