Bertone v. Department of Public Utilities

583 N.E.2d 829, 411 Mass. 536
CourtMassachusetts Supreme Judicial Court
DecidedJanuary 6, 1992
StatusPublished
Cited by16 cases

This text of 583 N.E.2d 829 (Bertone v. Department of Public Utilities) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bertone v. Department of Public Utilities, 583 N.E.2d 829, 411 Mass. 536 (Mass. 1992).

Opinion

Greaney, J.

Mario Bertone and Joan Bertone (Bertones) appeal from an order of the Department of Public Utilities (department) granting summary judgment to the Hull Municipal Lighting Plant (HMLP), and denying their request as interveners for summary judgment. The department’s order was entered in connection with a petition by HMLP to determine the validity of its contribution-in-aid-of-construction (hook-up charge) provisions which were applied to collect a charge from the Bertones as a condition of the supply of electrical service to their condominium project. The department concluded essentially that the provisions requiring payment of a hook-up charge were valid, and that the charge assessed was neither unlawfully discriminatory nor lacking in sufficient standards for proper application. A single justice of this court reserved and reported the case to the full court. We agree with these conclusions. We also reject the Bertones’ ar *538 gument that the hook-up charge constitutes an unlawful tax. Consequently, we affirm the order of the department.

Facts included in a joint stipulation of facts (filed by the parties to establish a basis for summary judgment), and other information based on materials in the record before the department, disclose the following.

a. The background of the dispute. HMLP is a municipal electric department established pursuant to St. 1891, c. 370. In 1986, HMLP served approximately 5,120 retail customers, and in 1986 had total sales of approximately 32,000,000 kilowatt-hours, yielding revenues of approximately $3,302,000. In 1985, HMLP had a peak load of 7.5 megawatts.

On July 15, 1985, HMLP’s board adopted the provisions in issue as paragraphs 25 and 26 of its general terms and conditions. These provisions took effect on August 1, 1985, and required, in paragraph 25, as a condition of the supply of electrical service, the payment of a hook-up charge by those seeking a hookup at a location not previously serviced by HMLP. Paragraph 26 provides that a customer seeking new or expanded service is required to pay an initial study fee to be credited against the final amount later calculated for the hook-up charge. 3

The Bertones are the developers of Nantascot, a condominium building in Hull containing sixty-six residential units and one commercial unit. The Bertones requested from HMLP a permanent service hookup for Nantascot in April, 1986. Because Nantascot was a site not previously served by HMLP, it required, pursuant to paragraph 26 of the general terms and conditions, that the Bertones pay a hook-up charge before their project could receive electricity. On or about April 24, 1986, the Bertones paid HMLP $2,500 as an initial study fee under protest.

*539 The Bertones first requested actual service in the fall of 1986, so that they could begin work on the interior of the building. Using figures provided by the Bertones’ electrical engineer, and figures prepared by its own consulting engineer, HMLP calculated the hook-up charge for Nantascot to be $86,849. By letter dated September 26, 1986, HMLP informed the Bertones of the charge and advised that it had to be paid as a requisite to Nantascot’s receiving electrical service. The Bertones have paid the hook-up charge in full with a reservation of their legal rights to have the payment refunded if their challenge to the hook-up charge prevails. The hook-up charge assessed to the Bertones covered the cost of both the general system improvements and the site-specific improvements required to provide electricity to Nantascot. HMLP has not determined the exact cost breakdown between these two categories, but the majority of the fee covered improvements which were not specific to a particular site. Nantascot was substantially completed and ready for occupancy in September, 1987.

b. Background and implementation of the hook-up charge. Throughout the 1970’s and early 1980’s, HMLP’s existing transmission, distribution, and supply system was capable of meeting the load requirements then imposed. Costs for maintenance and routine upgrading of the system were paid from monies collected through the existing rate structure. However, HMLP had determined that a substantial increase in load would necessitate improvements because its system was restricted by limitations on available transmission capacity, distribution equipment, and supply resources.

In 1984, HMLP’s board first became aware that extensive real estate development was planned for Hull. At that time, there were proposals to build approximately 1,500 condominium units over a four or five-year period, an expansion that would impose demands for electricity far beyond the existing capacity of HMLP’s system. As of January 22, 1987, when HMLP filed its petition with the department, the number of proposed condominium units had grown from 1,500 to approximately 2,000. This development could be expected to in *540 crease HMLP’s peak load by at least forty per cent over a very short period of time. Had this growth occurred as anticipated, HMLP’s existing system would have been unable to serve all of the planned load as well as its current load. With this increased load,.HMLP would then either have to refuse to serve new customers, curtail severely the quality and reliability of the supply of electricity that it could provide to existing customers, or both. HMLP estimated that it could be called on to make plant investments from $3,000,000 to $7,000,000, and possibly more, depending on the extent of development in Hull, the energy efficiency of the new construction, and the choice of heating and hot water systems. HMLP expected system improvements to be needed within a short time period.

HMLP further concluded that the use of electricity .for heating, especially in resistance applications, could have severe financial and economic effects on existing and future ratepayers, and indirectly on Hull. HMLP also considered that high utility bills, in addition to being burdensome for future customers, would reduce the resale value of condominium units. In 1985, in order to plan an appropriate response to the projected development, HMLP entered a contract with an expert to analyze the issues raised by such development. Based on extensive analysis and study,.the expert recommended that HMLP impose a hook-up charge for connecting new loads to the system. 4

*541 HMLP also concluded that it would cost approximately $2,500,000 to finance the infrastructure improvements to HMLP’s existing system necessary to accommodate the expected load growth. As a result of the expert’s analysis, and HMLP’s own determinations, HMLP proposed a development facilitation program to implement plans that would: (1) limit new hookups for electric space heating and hot water, and (2) charge applicants seeking a service hookup at a location not previously served by HMLP, as well as existing customers seeking substantially expanded service, a hook-up charge to reflect the costs imposed on HMLP for providing a service hookup and attendant system improvements. 5

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Murphy v. Massachusetts Turnpike Authority
462 Mass. 701 (Massachusetts Supreme Judicial Court, 2012)
Denver Street LLC v. Town of Saugus
970 N.E.2d 273 (Massachusetts Supreme Judicial Court, 2012)
Denver Street LLC v. Town of Saugus
939 N.E.2d 1187 (Massachusetts Appeals Court, 2011)
Silva v. City of Attleboro
908 N.E.2d 722 (Massachusetts Supreme Judicial Court, 2009)
Silva v. City of Fall River
798 N.E.2d 297 (Massachusetts Appeals Court, 2003)
Greater Franklin Developers Ass'n v. Town of Franklin
730 N.E.2d 900 (Massachusetts Appeals Court, 2000)
Corcoran, Mullins & Jennison, Inc. v. Flanagan
10 Mass. L. Rptr. 309 (Massachusetts Superior Court, 1999)
Greater Franklin Developers Ass'n v. Town of Franklin
7 Mass. L. Rptr. 480 (Massachusetts Superior Court, 1997)
Morton v. Town of Hanover
682 N.E.2d 889 (Massachusetts Appeals Court, 1997)
Town of Middleborough v. Middleborough Gas & Electric Department
664 N.E.2d 25 (Massachusetts Supreme Judicial Court, 1996)
Nuclear Metals, Inc. v. Low-Level Radioactive Waste Management Board
656 N.E.2d 563 (Massachusetts Supreme Judicial Court, 1995)
Planning Board of Braintree v. Department of Public Utilities
420 Mass. 22 (Massachusetts Supreme Judicial Court, 1995)
Aiello v. Commissioners of Dukes County
617 N.E.2d 663 (Massachusetts Appeals Court, 1993)
Nuclear Metals, Inc. v. Mayer
1 Mass. L. Rptr. 25 (Massachusetts Superior Court, 1993)
Berry v. Town of Danvers
613 N.E.2d 108 (Massachusetts Appeals Court, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
583 N.E.2d 829, 411 Mass. 536, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bertone-v-department-of-public-utilities-mass-1992.