Bertha Hillman v. Emerson Loga, III

697 F.3d 299, 2012 WL 4465194, 2012 U.S. App. LEXIS 20351
CourtCourt of Appeals for the Fifth Circuit
DecidedSeptember 28, 2012
Docket11-60868
StatusPublished
Cited by27 cases

This text of 697 F.3d 299 (Bertha Hillman v. Emerson Loga, III) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bertha Hillman v. Emerson Loga, III, 697 F.3d 299, 2012 WL 4465194, 2012 U.S. App. LEXIS 20351 (5th Cir. 2012).

Opinion

HIGGINSON, Circuit Judge:

Plaintiffs-Appellants appeal the district court’s grant of summary judgment in favor of Defendants-Appellees, based on the district court’s finding that the 24-month *301 construction obligations in the Purchase Agreements 1 were not illusory and, therefore, the parties’ contracts are exempted from the Interstate Land Sales Full Disclosure Act, 15 U.S.C. § 1701, et seq., (“ILSA”).

FACTS AND PROCEEDINGS

Plaintiffs-Appellants (“Purchasers”) each owned condominium units at the Village at Henderson Point (the “Village”) located in Pass Christian, Mississippi. Hurricane Katrina destroyed the condominium complex in August 2005. In early 2007, Purchasers retained Lacote, LLC (“Lacote”) to rebuild the complex in the same location. Lacote was made up of three members, Emerson P. Loga, III (“Loga”) and Dennis Stieffel (“Stieffel”), and Douglas Johnson (“Johnson”). 2

In furtherance of the plan to develop and construct the new condominium complex, Lacote acquired the Village property from the Purchasers. The purchase was financed through Trustmark National Bank (“Trustmark”), which received a first position lien on the property and committed to provide construction financing for the project.

Prior to construction, Purchasers executed Purchase Agreements and made deposits with Lacote for the purchase of individual units once the complex was completed. The Purchase Agreements stipulated that construction of the units would be completed within- two years of the execution of the Agreements.

Construction began in January 2008, but Lacote did not have adequate funding and stopped construction in June of that year, when the project was only 35% complete. 3 Lacote thus obtained a second construction loan from SI Realty Enterprises, Inc. (“SI Realty”) in the amount of $1.5 million. SI Realty secured its loan with a second position lien through a deed of trust against the property.

Trustmark allegedly backed out of its commitment to finance the project and Lacote thereafter could not make its loan payments to SI Realty. SI Realty purchased Trustmark’s first lien and foreclosed on the property in January 2009. La-cote filed for, and has been discharged from, bankruptcy.

Purchasers filed the instant lawsuit in May 2010 alleging that Loga, Stieffel, and Johnson, as individual members of Lacote, violated the anti-fraud provisions of the ILSA, 15 U.S.C. § 1703(a)(2). 4 The parties filed cross-motions for summary judgment and the district court granted sum *302 mary judgment in favor of Loga and Stieffel. The district court concluded that because the Purchase Agreements contain an obligation to complete construction within two years, the sales are exempt from the ILSA’s requirements, see 15 U.S.C. § 1702(a)(2), and Loga and Stieffel therefore cannot- be held liable under the ILSA.

STANDARD OF REVIEW

This court reviews “a district court’s grant of summary judgment de novo, applying the same standards as the district court.” Noble Energy Inc. v. Bituminous Cas. Co., 529 F.3d 642, 645 (5th Cir.2008). Summary judgment is thus proper when “there is no genuine dispute as to any material fact and the .movant is entitled to judgment as a matter of law.” Fed.R.Civ.P. 56(a). “Where the record taken as a whole could not lead a rational trier of fact to find for the non-moving party, there is no genuine issue for trial.” Matsushita Elec. Indus. Co. v. Zenith Radio Corp., 475 U.S. 574, 587, 106 S.Ct. 1348, 89 L.Ed.2d 538 (1986) (citation omitted). “Doubts are to be resolved in favor of the nonmoving party, and any reasonable inferences are to be drawn in favor of that party.” Gowesky v. Singing River Hosp. Sys., 321 F.3d 503, 507 (5th Cir. 2003).

The district court correctly stated that interpretation of the ILSA is governed by federal law, see Kamen v. Kemper Fin. Servs., Inc., 500 U.S. 90, 97, 111 S.Ct. 1711, 114 L.Ed.2d 152 (1991), and that state law (in this case, the law of Mississippi) governs the interpretation of the Purchase Agreements. ACS Constr. Co. of Miss. v. CGU, 332 F.3d 885, 888 (5th Cir.2003).

DISCUSSION

The district court ruled that the Purchase Agreements are exempt from the ILSA because the language imposing a 24-month construction term requirement brings the agreements within the ILSA’s two-year building exemption. 5 The two-year building exemption is found in § 1702(a)(2) of the ILSA and states in relevant part:

(a) Sale or lease of lots generally
Unless the method of disposition is adopted for the purpose of evasion of this chapter, the provisions of this chapter shall not apply to — ...
(2) the sale or lease of any improved land on which there is a residential, commercial, condominium, or industrial building, or the sale or lease of land under a contract obligating the seller or lessor to erect such a building thereon within a period of two years ....

15 U.S.C. § 1702(a)(2). Each of the Purchase Agreements states in relevant part:

COMPLETION DATE AND CONSTRUCTION.
a. Notwithstanding any other provision of this Agreement, construction of the Unit shall be completed on or before twenty-four (24) months or less from the date of execution of this Purchase Agreement OR a Certificate of Occupancy has been issued by the relevant building authority, whichever is sooner, provided, however, that SELLER shall not be responsible for delays caused by circumstances recognized by Mississippi *303 law to constitute impossibility of performance, such as war, strikes, insurrection, Acts of God, or unanticipated shortage of building materials.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brown v. Muzyka
W.D. Texas, 2025
Bissell v. Mata
W.D. Texas, 2025
Umg Recordings, Inc. v. Grande Commc'ns Networks, LLC
384 F. Supp. 3d 743 (W.D. Texas, 2019)
Kristensen v. United States
372 F. Supp. 3d 461 (W.D. Texas, 2019)
CBX Res., LLC v. ACE Am. Ins. Co.
320 F. Supp. 3d 853 (W.D. Texas, 2018)
Parrish v. Premier Directional Drilling, L.P.
280 F. Supp. 3d 954 (W.D. Texas, 2017)
In Re Louisiana Crawfish Producers
852 F.3d 456 (Fifth Circuit, 2017)
Kueber v. City of San Antonio
197 F. Supp. 3d 917 (W.D. Texas, 2016)
Johnson v. United Healthcare of Texas, Inc.
167 F. Supp. 3d 825 (W.D. Texas, 2016)
Lloyd v. Birkman
127 F. Supp. 3d 725 (W.D. Texas, 2015)
Chartis Specialty Insurance v. Tesoro Corp.
113 F. Supp. 3d 924 (W.D. Texas, 2015)
Ripple v. Marble Falls Independent School District
99 F. Supp. 3d 662 (W.D. Texas, 2015)
Brandon v. Sage Corp.
61 F. Supp. 3d 632 (W.D. Texas, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
697 F.3d 299, 2012 WL 4465194, 2012 U.S. App. LEXIS 20351, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bertha-hillman-v-emerson-loga-iii-ca5-2012.