Berry v. Lucas

150 P.3d 424, 210 Or. App. 334, 61 U.C.C. Rep. Serv. 2d (West) 591, 2006 Ore. App. LEXIS 2018
CourtCourt of Appeals of Oregon
DecidedDecember 27, 2006
Docket03CV0307, A124777
StatusPublished
Cited by8 cases

This text of 150 P.3d 424 (Berry v. Lucas) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Berry v. Lucas, 150 P.3d 424, 210 Or. App. 334, 61 U.C.C. Rep. Serv. 2d (West) 591, 2006 Ore. App. LEXIS 2018 (Or. Ct. App. 2006).

Opinion

*336 CRAMER, J. pro tempore

This appeal arises from a contract dispute regarding a manufactured home placed on a lot in Bandon, Oregon. Following a bench trial, the trial court entered a judgment in favor of plaintiffs and awarded damages of $6,535. Defendant appeals and, for the reasons discussed below, we affirm. 1

We take the facts — which are undisputed — from the record and the trial court’s findings in its letter opinion. Defendant is in the business of the retail sale of manufactured homes. In September 2002, plaintiffs and defendant entered into a contract in which plaintiffs agreed to purchase a Redman manufactured home for $69,040. As the trial court explained:

“The contract consisted of a printed form (front and back) and three exhibits. Defendant agreed as part of the contract to deliver and set up the manufactured home on a lot owned by plaintiffs in Bandon, Oregon. The parties contemplated that plaintiffs would be receiving a home suitable for occupancy. The contract provided that plaintiffs would pay 50% down and the balance on delivery. * * *
“As part of the contract, the parties certified that the terms printed on the back side of the contract were part of the contract, and furthermore, plaintiffs acknowledged by signing the contract that they had read and understood the contract and received a copy of the contract.”

Plaintiffs mailed a check for one-half of the purchase price to defendant in September 2002 and mailed a check for the remaining balance in early November.

The manufactured home was delivered in two sections to plaintiffs’ lot on November 15, 2002, and placed on a *337 concrete slab that had been constructed by plaintiffs’ contractor. About a month later — before the home had been completed and prepared for occupancy — it suffered severe storm damage. The trial court found:

“As of that date, the carpet inside the home had not been laid, railings remained to be installed, sheet rock still needed to be installed and exterior siding on the west end had not yet been installed. * * * [T]he home was not ready to be moved into because set up work remained to be done by the defendant, and its agent, both inside and outside the home. The carpet work, the railings, the sheet rock and the exterior siding were the responsibility of defendant. Neither party had insurance on the manufactured home as of the date of the storm damage. Plaintiffs paid a contractor $6535 to repair the damage.”

Plaintiffs filed this action to recover the repair bill plus lost wages of $350. They first alleged that defendants violated the Unlawful Trade Practices Act (UTPA). In a second count, plaintiffs alleged that the damage to the manufactured home “was sustained after the manufactured home was shipped to the specified destination but before Defendants could tender delivery or Plaintiffs could inspect and potentially accept the goods.” Plaintiffs alleged that defendant refused to repair the wind and rainwater damage and that plaintiffs therefore had to incur the expense of having the repair performed.

The trial court found in defendants’ favor on the UTPA claim and, as noted, dismissed the claims against the individual defendants and entered a money judgment in favor of plaintiffs on the contract claim. Defendant appeals, arguing that the trial court erred in finding in plaintiffs’ favor and awarding damages. Because we agree with the trial court that the risk of loss was on defendant at the time the storm damage occurred, we affirm.

As a general matter, Oregon’s codification of the Uniform Commercial Code (UCC) governs sales contracts of the type involved here. But, “[t]he effect of provisions of the Uniform Commercial Code may be varied by agreement, except as otherwise provided in the Uniform Commercial Code.” *338 ORS 71.1020(3); see also ORS 72.5090(4) (regarding the provision addressing risk of loss in the absence of breach, “[t]he provisions of this section are subject to contrary agreement of the parties”). Defendant acknowledges the general applicability of the UCC, but argues that a provision of the contract governs the risk of loss in this case and is dispositive. We begin with that argument. 2

Paragraph 12 of the sales contract states:

“INSURANCE. Buyer understands that Buyer is not covered by insurance on the unit purchased until accepted by an insurance company, and Buyer agrees to hold Dealer harmless from any and all claims due to loss or damage prior to acceptance of insurance coverage by an insurance company.”

(Underscoring and boldface in original.) Defendant argues that paragraph 12 addresses risk of loss and that resort to the UCC provisions regarding risk of loss therefore is unnecessary. It argues that paragraph 12 “effectively allocates the risk of loss to the buyer before complete performance of the contract.” According to defendant, the risk of loss under paragraph 12 had passed to plaintiffs at the time of the storm damage.

In interpreting a contract, we first examine the text and context to determine if the contract is ambiguous. Batzer Construction, Inc. v. Boyer, 204 Or App 309, 317-18, 129 P3d 773, rev den, 341 Or 366 (2006). Whether a contract is ambiguous presents a question of law. Id. at 317. In addition to examining the text and context of the provision, the court, in determining whether the contract is ambiguous, is also to consider extrinsic evidence of “the circumstances underlying the formation of the contract.” Id. at 317. Finally, if the “provision remains ambiguous after the first two steps have been followed, the court relies on appropriate maxims of construction” to determine the provision’s meaning. Yogman v. Parrott, 325 Or 358, 364, 937 P2d 1019 (1997).

Paragraph 12 does not, on its face, address risk of loss. It follows a heading that reads, “Insurance.” Its text focuses on the effect of insurance coverage, not a time in the *339 transaction that will shift the risk of loss from seller to buyer. 3 Moreover, as plaintiff points out, at the time the parties entered into the contract, the manufactured home had not yet been constructed by the manufacturer. According to plaintiff,

“it seems nonsensical and illogical to force the Plaintiff to bear the risk of loss for a manufactured home that had yet to be manufactured and yet to be placed in the control of the Defendant. * * * It also seems untenable to force the Plaintiff to bear the risk of loss when the Defendant and Defendant’s agents are still working on setting up the manufactured home, in accordance with their contractual duties.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Homes Association of Cedar Hills v. Craig
515 P.3d 379 (Court of Appeals of Oregon, 2022)
Lufkin v. Dept. of Human Services
499 P.3d 833 (Court of Appeals of Oregon, 2021)
Bush v. City of Prineville (A165637)
457 P.3d 324 (Court of Appeals of Oregon, 2020)
Kaste v. Land O'Lakes Purina Feed, LLC
392 P.3d 805 (Court of Appeals of Oregon, 2017)
Country Mutual Insurance v. Pittman
910 F. Supp. 2d 1233 (D. Oregon, 2012)
Harnisch v. College of Legal Arts, Inc.
259 P.3d 67 (Court of Appeals of Oregon, 2011)
State v. Watters
156 P.3d 145 (Court of Appeals of Oregon, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
150 P.3d 424, 210 Or. App. 334, 61 U.C.C. Rep. Serv. 2d (West) 591, 2006 Ore. App. LEXIS 2018, Counsel Stack Legal Research, https://law.counselstack.com/opinion/berry-v-lucas-orctapp-2006.