Berry v. Blackard Construction Co.

300 N.E.2d 627, 13 Ill. App. 3d 768, 1973 Ill. App. LEXIS 2108
CourtAppellate Court of Illinois
DecidedAugust 9, 1973
Docket11951
StatusPublished
Cited by15 cases

This text of 300 N.E.2d 627 (Berry v. Blackard Construction Co.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Berry v. Blackard Construction Co., 300 N.E.2d 627, 13 Ill. App. 3d 768, 1973 Ill. App. LEXIS 2108 (Ill. Ct. App. 1973).

Opinion

Mr. JUSTICE SIMKINS

delivered the opinion of the court:

This is an appeal from two judgments entered in two cases which were consolidated in trial court, and in which the issues were tried without a jury.

On November 6, 1969, appellant Blackard Construction Co. filed suit against appellee Richard Berry, d/b/a Berco & Associates and Great American Insurance Company (Berry’s surety) alleging that Berry had breached a contract for the construction of certain facilities in Camelot Addition and sought damages for repairs of Berry’s faulty work, the cost of completion of the work following Berry’s refusal to proceed with the job, and consequential damages. As to this suit the trial judge found Blackard Construction Co. guilty of anticipatory breach of the contract and entered judgment in favor of Berry.

On February 13, 1970, the appellee Richard Berry, d/b/a Berco & Associates sued the appellant Blackard Construction Co., Richard Blackard, Yvonne Blackard and others having interests in Camelot Addition, a subdivision in Decatur, Illinois. Berry alleged breach of contract and sought to enforce his rights under the Mechanic’s Lien statute. The trial judge found in Berry’s favor and awarded him a mechanic’s lien in the sum of $20,940.64.

Richard D. Blackard, during the period of time in question, was the sole stockholder and President of Blackard Construction Company. He and his wife Yvonne Blackard originally purchased the land which became Camelot Addition. On June 2, 1969, Blackard and his wife entered into an agreement with Blackard Construction Company providing that all work on Camelot Addition (including the work to be performed by appellee Berry) would be completed by February 1, 1970. Blackard Company was to develop the subdivision, supervise the installation of all improvements and was granted the option to purchase the improved lots and to promote sales. On June 16, 1969, Blackard Company and Berry entered into a contract pursuant to which Berry was to construct sanitary sewers, storm drainage, water mains and alternate streets for the Camelot Addition. The first paragraph of the agreement incorporated, by reference, Standard Specifications for Water and Sewer Main Construction in Illinois, first edition, August 1, 1967, a publication by the Illinois Society of Professional Engineers and other related groups interested in the titled subject. The book contains 152 pages. The contract further provided that “The work * * * shall be completed in 180 work days. * * * Work days shall be determined by the Engineer.” Other pertinent paragraphs provided as follows:

“4. PROGRESS PAYMENT. BLACKARD shall make payment on account of the contract as provided therein as follows:
On or about the 15th day of each month, an amount equal to 90% of the value, based upon the contract price of labor and materials, incorporated in the work up to the last day of the preceding month, as certified to by Warren E. Hagan, as engineer, less the aggregate of previous payments.
5. ACCEPTANCE AND FINAL PAYMENT. Final payment shall be due thirty days after substantial completion of the work, provided the work be then fully completed and the contract fully performed.
Upon receipt of written notice that the work is ready for final inspection and acceptance, the Engineer shall promptly make such inspection and when he finds the work acceptable under the contract and the contract fully performed, he shall promptly issue a final certificate under his own signature, stating that the work provided for in this contract has been completed and is accepted by him under the terms and conditions thereof, and that the entire balance found to be due BERCO, and noted in said final certificate, is due and payable.
Before issuance of final payment BERCO shall submit evidence satisfactory to Warren E. Hagan, Engineer, that all payrolls, material bills, and other indebtedness connected with the work have been paid or otherwise satisfied.”

Berry was to commence work by June 23, 1969. He was paid, pursuant to the above-recited paragraph 4 of the contract, a progress payment of $6,470.28 for work completed through July 1, 1969; he received a progress payment of $16,661.46 for work completed, from July 1, 1969, to August 1, 1989, and a third progress payment in the amount of $37,855.05 for work completed from August 1, 1969, to September 1, 1969. Warren Hagan, engineer for Blackard testified, with reference to the progress payments as follows:

“Q. In connection with this contract, did you on a monthly basis prepare what was called an Engineer’s Payment Estimate?
HAGAN: Yes.
J. And what was meant to be covered by the estimates on a monthly basis?
HAGAN: The estimates were to cover all of the work installed in the project.
Q. Did those estimates reflect whether or not.the work was installed in accordance with the contract?
HAGAN: No, they did not.’”

Hagan then prepared a fourth progress payment report for Blackard which indicated payment due Berry in the amount of $35,756.13. This fourth progress payment report encompassed some 320 lineal feet of 12 inch sewer pipe. Hagan testified, with reference to this report as follows:

"Q. Am I correct in assuming that at the time you prepared this it was your best judgment, without having actually measured, that there was 320 lineal feet of the 12 inch sewer pipe installed on the ground?
Hagan: Approximately 320 feet, yes.
Q. And by showing it there you did not mean to state to anyone that it had been completed in the sense that it had been tested and accepted by the city, did you?
A. That it had been tested or accepted by our office or the city.
Q. That it was simply installed in the ground?
A. Simply in place."

Blackard then refused to pay the $35,756.13 shown to be due Berry according to the fourth progress payment report, advising Berry on October 7, 1969, that “* * # Payments are to be made on work in place and accepted. The sewer is not acceptable. Therefore, payment for sewer work in place and not accepted will not be made.” On October 22, Blackard advised Berry that he had ten days in which to correct defects in the sewer fine. Berry did no further work on the job after October 17, 1969, stating that his only reason was Blackard’s refusal to pay the $35,756.13. Thereafter, on November 3, 1969, Blackard declared the contract forfeited, took over the project and completed it.

Blackard first urges that the trial court erred in finding that it breached the contract by “anticipatory repudiation in view of the express terms of the contract.” It is undisputed that in October, 1969, some of the work in place was not in a condition to be finally acceptable.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

People Ex Rel. Daley v. Strayhorn
518 N.E.2d 1047 (Illinois Supreme Court, 1988)
Stan D. Bowles Distributing Co. v. Pabst Brewing Co.
317 S.E.2d 684 (Court of Appeals of North Carolina, 1984)
Dunaway v. Department of Labor
440 N.E.2d 231 (Appellate Court of Illinois, 1982)
National Boulevard Bank v. Citizens Utilities Co.
438 N.E.2d 471 (Appellate Court of Illinois, 1982)
First National Bank v. Canton Council of Campfire Girls, Inc.
401 N.E.2d 1293 (Appellate Court of Illinois, 1980)
O'Brien v. Board of Education of School District No. 189
388 N.E.2d 1104 (Appellate Court of Illinois, 1979)
Carlson v. Cremeens
364 N.E.2d 114 (Appellate Court of Illinois, 1977)
Aronson Furniture Co. v. Johnson
365 N.E.2d 61 (Appellate Court of Illinois, 1977)
Wheaton National Bank v. Aarvold
348 N.E.2d 520 (Appellate Court of Illinois, 1976)
Kern Hotel & Tavern, Inc. v. Home Insurance
332 N.E.2d 197 (Appellate Court of Illinois, 1975)
Cornue v. Weaver
331 N.E.2d 148 (Appellate Court of Illinois, 1975)
Urban Investment & Development Co. v. Maurice L. Rothschild & Co.
323 N.E.2d 588 (Appellate Court of Illinois, 1975)

Cite This Page — Counsel Stack

Bluebook (online)
300 N.E.2d 627, 13 Ill. App. 3d 768, 1973 Ill. App. LEXIS 2108, Counsel Stack Legal Research, https://law.counselstack.com/opinion/berry-v-blackard-construction-co-illappct-1973.