OPINION
WRIGHT, Judge.
In this appeal of the district court’s entry of summary judgment, appellants Berne Area Alliance for Quality Living, et al. (collectively BAA), challenge the district court’s determination that respondents Dodge County and its Board of Commissioners did not act arbitrarily and capriciously in concluding that an environmental impact statement (EIS) for the construction of a hog confinement facility was not required. The county argues that Minn.Stat. § 116D.04, subd. 2a(d) (2004), exempts the proposed facility from environmental review. BAA counters that because that statute was enacted after the county’s EIS decision, it cannot be applied here, and that, even if the statute does apply, it is not satisfied. BAA also contends that the Minnesota Pollution Control Agency (PCA), not the county, is the responsible governmental unit for permit approval. We affirm in part and reverse in part.
FACTS
Mark Finstuen, who had a feedlot for 35 steers, applied for a conditional use permit (CUP) and other permits that would allow him to build and operate a hog feedlot that, while having a capacity of significantly more than 1,000 animal units (AUs), would be used to house only 995 AUs, including the 35 steers. His proposal included a plan for applying the manure produced by the feedlot, in lieu of fertilizer, to surrounding land in such a manner that there would be no net increase in the amount of nitrates applied to the land. After considering Finstuen’s application, his Environmental Assessment Worksheet (EAW), and other environmentally related information, the county made a negative declaration regarding the need for an EIS for the proposed project and granted the application. BAA sued the county, seeking a declaratory judgment that an EIS was required. Both sides moved for summary judgment. Although it did not initially question the county’s authority to determine the need for an EIS, BAA argued in support of its summary judgment motion that the responsible governmental unit (RGU) for decisions regarding the EIS and issuance of the permits was the PCA, rather than the county.
The district court denied BAA’s motion for summary judgment and granted the county’s motion. The district court ruled that (a) the capacity of the proposed feedlot exceeds 1,000 AUs; (b) because the capacity of the proposed feedlot exceeds 1,000 AUs, Minn.Stat. § 116D.04, subd. 2a(d) (2004), which exempts from environmental review proposed feedlots having a capacity of fewer than 1,000 AUs, did not apply; (c) the county was the proper RGU to issue Finstuen’s permits; and (d) the county’s negative declaration regarding the need for an EIS was not arbitrary or capricious. BAA appealed, and the county filed a notice of review, arguing that the exemption in Minn.Stat. § 116D.04, subd. 2a(d), applies here.
ISSUES
I. Is a proposed feedlot that is capable of holding more than 1,000 animal units but [580]*580will actually hold fewer than 1,000 animal units exempt from environmental review under Minn.Stat. § 116D.04, subd. 2a(d)(1) (2004)?
II. Did the county have the authority to grant permits for construction and operation of the proposed feedlot?
ANALYSIS
When reviewing a summary judgment affirming a negative declaration regarding the need for an EIS, we focus “on the proceedings before the decision-making body ... not the findings of the [district] court.” Iron Rangers for Responsible Ridge Action v. Iron Range Res., 531 N.W.2d 874, 879 (Minn.App.1995), review denied (Minn. July 28, 1995). Our review of an agency’s consideration of environmental factors is limited, and we will intervene only when the record suggests “the agency has not taken a ‘hard look’ at the salient problems” and its decision lacks “articulated standards and reflective findings.” White v. Minn. Dep’t of Natural Res., 567 N.W.2d 724, 730 (Minn.App.1997) (quoting Reserve Mining Co. v. Herbst, 256 N.W.2d 808, 825 (Minn.1977)), review denied (Minn. Oct. 31, 1997); see also Minn. Ctr. for Envtl. Advocacy v. Minn. Pollution Control Agency, 644 N.W.2d 457, 465 (Minn.2002) (stating that appellate court has limited review of agency’s decision).
I.
“Where there is potential for significant environmental effects resulting from any major governmental action, the action shall be preceded by a detailed [EIS] prepared by the [RGU].” Minn.Stat. § 116D.04, subd. 2a (2004). After BAA initiated this action, the legislature amended the environmental-review statute to exempt from review feedlots with a capacity of fewer than 1,000 AUs. 2003 Minn. Laws ch. 128, art. 3, § 40. The parties dispute whether the amended statute applies here and, if it does, whether the exemption applies.
A.
We begin with an analysis of the applicability of the amended statute. The United States Supreme Court has stated that “[w]hen the intervening statute authorizes or affects the propriety of prospective relief, application of the new provision is not retroactive” and is, therefore, permitted. Landgraf v. USI Film Prods., 511 U.S. 244, 273-74, 114 S.Ct. 1483, 1501, 128 L.Ed.2d 229 (1994). Under Minn.Stat. § 116D.04, subd. 10 (2004), adverse EIS determinations may be challenged in a declaratory judgment action, as happened here. Because the amendment to Minn.Stat. § 116D.04, subd. 2a, precludes environmental review of certain proposed feedlots, the amendment “affected” the availability of the relief BAA sought (a declaratory judgment requiring environmental review in the form of an EIS). Thus, applying the new statute is not improperly retroactive, and the amended statute applies here.
B.
Having concluded that the amended statute is applicable, we next consider whether the proposed feedlot is exempt from environmental review. To be exempt from environmental review under the amended statute, a proposed feedlot must, among other things, have “a capacity of less than 1,000 [AUs.]” Minn.Stat. § 116D.04, subd. 2a(d)(1)(i). The crux of the parties’ disagreement is whether “capacity” is to be measured physically or legally. BAA argues that “capacity” is measured by the number of AUs that the proposed project can actually accommodate (physical capacity). The county counters that “capacity” is measured by the [581]*581number of AUs that Finstuen may, under the relevant permits, house in the project (legal capacity).
The relevant statutes and rules do not define “capacity.” To support its argument that “capacity” means legal capacity, the county cites Finstuen’s “Minnesota Pollution Control Agency Permit Application for an Animal Feedlot or Manure Storage Area.” While the application refers to “maximum capacity,” it does not define “capacity.” Also, reading “capacity” for purposes of the exemption as legal capacity, rather than physical capacity, is inconsistent with certain feedlot rules. For example, feedlot permit applications must contain “a list of all animal types, and the maximum number of animals of each animal type that can be confined
Free access — add to your briefcase to read the full text and ask questions with AI
OPINION
WRIGHT, Judge.
In this appeal of the district court’s entry of summary judgment, appellants Berne Area Alliance for Quality Living, et al. (collectively BAA), challenge the district court’s determination that respondents Dodge County and its Board of Commissioners did not act arbitrarily and capriciously in concluding that an environmental impact statement (EIS) for the construction of a hog confinement facility was not required. The county argues that Minn.Stat. § 116D.04, subd. 2a(d) (2004), exempts the proposed facility from environmental review. BAA counters that because that statute was enacted after the county’s EIS decision, it cannot be applied here, and that, even if the statute does apply, it is not satisfied. BAA also contends that the Minnesota Pollution Control Agency (PCA), not the county, is the responsible governmental unit for permit approval. We affirm in part and reverse in part.
FACTS
Mark Finstuen, who had a feedlot for 35 steers, applied for a conditional use permit (CUP) and other permits that would allow him to build and operate a hog feedlot that, while having a capacity of significantly more than 1,000 animal units (AUs), would be used to house only 995 AUs, including the 35 steers. His proposal included a plan for applying the manure produced by the feedlot, in lieu of fertilizer, to surrounding land in such a manner that there would be no net increase in the amount of nitrates applied to the land. After considering Finstuen’s application, his Environmental Assessment Worksheet (EAW), and other environmentally related information, the county made a negative declaration regarding the need for an EIS for the proposed project and granted the application. BAA sued the county, seeking a declaratory judgment that an EIS was required. Both sides moved for summary judgment. Although it did not initially question the county’s authority to determine the need for an EIS, BAA argued in support of its summary judgment motion that the responsible governmental unit (RGU) for decisions regarding the EIS and issuance of the permits was the PCA, rather than the county.
The district court denied BAA’s motion for summary judgment and granted the county’s motion. The district court ruled that (a) the capacity of the proposed feedlot exceeds 1,000 AUs; (b) because the capacity of the proposed feedlot exceeds 1,000 AUs, Minn.Stat. § 116D.04, subd. 2a(d) (2004), which exempts from environmental review proposed feedlots having a capacity of fewer than 1,000 AUs, did not apply; (c) the county was the proper RGU to issue Finstuen’s permits; and (d) the county’s negative declaration regarding the need for an EIS was not arbitrary or capricious. BAA appealed, and the county filed a notice of review, arguing that the exemption in Minn.Stat. § 116D.04, subd. 2a(d), applies here.
ISSUES
I. Is a proposed feedlot that is capable of holding more than 1,000 animal units but [580]*580will actually hold fewer than 1,000 animal units exempt from environmental review under Minn.Stat. § 116D.04, subd. 2a(d)(1) (2004)?
II. Did the county have the authority to grant permits for construction and operation of the proposed feedlot?
ANALYSIS
When reviewing a summary judgment affirming a negative declaration regarding the need for an EIS, we focus “on the proceedings before the decision-making body ... not the findings of the [district] court.” Iron Rangers for Responsible Ridge Action v. Iron Range Res., 531 N.W.2d 874, 879 (Minn.App.1995), review denied (Minn. July 28, 1995). Our review of an agency’s consideration of environmental factors is limited, and we will intervene only when the record suggests “the agency has not taken a ‘hard look’ at the salient problems” and its decision lacks “articulated standards and reflective findings.” White v. Minn. Dep’t of Natural Res., 567 N.W.2d 724, 730 (Minn.App.1997) (quoting Reserve Mining Co. v. Herbst, 256 N.W.2d 808, 825 (Minn.1977)), review denied (Minn. Oct. 31, 1997); see also Minn. Ctr. for Envtl. Advocacy v. Minn. Pollution Control Agency, 644 N.W.2d 457, 465 (Minn.2002) (stating that appellate court has limited review of agency’s decision).
I.
“Where there is potential for significant environmental effects resulting from any major governmental action, the action shall be preceded by a detailed [EIS] prepared by the [RGU].” Minn.Stat. § 116D.04, subd. 2a (2004). After BAA initiated this action, the legislature amended the environmental-review statute to exempt from review feedlots with a capacity of fewer than 1,000 AUs. 2003 Minn. Laws ch. 128, art. 3, § 40. The parties dispute whether the amended statute applies here and, if it does, whether the exemption applies.
A.
We begin with an analysis of the applicability of the amended statute. The United States Supreme Court has stated that “[w]hen the intervening statute authorizes or affects the propriety of prospective relief, application of the new provision is not retroactive” and is, therefore, permitted. Landgraf v. USI Film Prods., 511 U.S. 244, 273-74, 114 S.Ct. 1483, 1501, 128 L.Ed.2d 229 (1994). Under Minn.Stat. § 116D.04, subd. 10 (2004), adverse EIS determinations may be challenged in a declaratory judgment action, as happened here. Because the amendment to Minn.Stat. § 116D.04, subd. 2a, precludes environmental review of certain proposed feedlots, the amendment “affected” the availability of the relief BAA sought (a declaratory judgment requiring environmental review in the form of an EIS). Thus, applying the new statute is not improperly retroactive, and the amended statute applies here.
B.
Having concluded that the amended statute is applicable, we next consider whether the proposed feedlot is exempt from environmental review. To be exempt from environmental review under the amended statute, a proposed feedlot must, among other things, have “a capacity of less than 1,000 [AUs.]” Minn.Stat. § 116D.04, subd. 2a(d)(1)(i). The crux of the parties’ disagreement is whether “capacity” is to be measured physically or legally. BAA argues that “capacity” is measured by the number of AUs that the proposed project can actually accommodate (physical capacity). The county counters that “capacity” is measured by the [581]*581number of AUs that Finstuen may, under the relevant permits, house in the project (legal capacity).
The relevant statutes and rules do not define “capacity.” To support its argument that “capacity” means legal capacity, the county cites Finstuen’s “Minnesota Pollution Control Agency Permit Application for an Animal Feedlot or Manure Storage Area.” While the application refers to “maximum capacity,” it does not define “capacity.” Also, reading “capacity” for purposes of the exemption as legal capacity, rather than physical capacity, is inconsistent with certain feedlot rules. For example, feedlot permit applications must contain “a list of all animal types, and the maximum number of animals of each animal type that can be confined within each lot, building, or area at the animal feedlot[J” Minn. R. 7020.0505, subp. 4(A)(4) (2003) (emphasis added). The common meaning of “that can be confined” suggests physical capacity, rather than legal capacity. Also, the “expansion” of a feedlot is defined as “construction or any activity that has resulted or may result in an increase in the number of animal units that an animal feedlot is capable of holding or an increase in storage capacity of a manure storage area.” Minn. R. 7020.0300, subp. 11a (2003) (emphasis added). Given the definition of “expansion,” construing “capacity” in this provision as legal capacity, rather than as physical capacity, would equate an application to increase the number of animal units being housed at an under-utilized feedlot with the construction of a new feedlot.
Thus, we reject the county’s argument that “capacity” refers to legal capacity, rather than physical capacity, not only because this creates incongruence between both of these rules, but also because such construction is inconsistent with the common meaning of the statutory term. See Minn.Stat. § 645.08(1) (2004) (stating that words in statutes are to be construed according to their “common and approved usage”); Minn.Stat. § 645.001 (2004) (stating that provisions of chapter 645 “govern all rules becoming effective after June 30, 1981[,]” unless specifically provided otherwise). We conclude that the “capacity” for determining whether a proposed project is exempt from environmental review under Minn.Stat. § 116D.04, subd. 2a(d), is physical capacity rather than legal capacity. And it is undisputed here that the physical capacity of the proposed the feedlot exceeds 1,000 AUs. The proposed feedlot, therefore, is not exempt from environmental review.
II.
In its motion for summary judgment, BAA asserted that the PCA, rather than the county, should have addressed whether an EIS was required. The district court ruled that the county was the RGU for addressing that question. In its request for reconsideration, BAA challenged this determination, and the district court declined to address it because motions for reconsideration are disfavored and because BAA’s argument on the point was unfocused. On appeal, BAA again argues that the PCA, rather than the county, was the RGU and should have determined whether an EIS was required.
It is undisputed that Finstuen’s proposed project requires a permit from an RGU. “Any Minnesota county board may, by resolution, with approval of the [PCA], assume responsibility for processing applications for permits required by the [PCA] under this section for livestock feedlotsf.]” Minn.Stat. § 116.07, subd. 7 (2004); accord Minn. R. 7020.1500 (2003). Regarding the jurisdiction of administrative agencies generally, the Minnesota Supreme Court has stated:
[582]*582Jurisdiction of an administrative agency consists of the powers granted it by statute. Lack of statutory power betokens lack of jurisdiction. It is therefore well settled that a determination of an administrative agency is void and subject to collateral attack where it is made either without statutory power or in excess thereof.
McKee v. County of Ramsey, 310 Minn. 192, 195, 245 N.W.2d 460, 462 (1976) (quoting State ex rel. Spurck v. Civil Serv. Bd., 226 Minn. 253, 259, 32 N.W.2d 583, 586 (1948)). Because a county’s assumption of the responsibility to process feedlot permit applications is derivative of the PCA’s authority to process those applications, the county’s authority to process applications for feedlot permits is necessarily subject to the same limits on its authority and jurisdiction. Questions of an agency’s jurisdiction and authority over a particular area are subject to de novo review. Frost-Benco Elec. Ass’n v. Minn. Pub. Utils. Comm’n, 358 N.W.2d 639, 642 (Minn.1984).
A county assuming the responsibility to process feedlot permit applications is referred to as a “delegated county.” See Minn. R. 7020.0300, subp. 9a (2003) (defining “[d]elegated county” as one that has “received authorization pursuant to part 7020.1600,subpart 3a, item C, to implement an animal feedlot program”); see also Minn. R. 7020.1600, subp. 3aC (2003) (stating that, to assume responsibility for administering a feedlot program, county must, among other things, “[rjeceive written authorization from the commissioner [of the PCA] to administer the [feedlot program]”). And “processing” a feedlot permit application “may include, at the option of the county board, issuing, denying, modifying, imposing conditions upon, or revoking permits pursuant to the provisions of this section or rules promulgated pursuant to it[.]” Minn.Stat. § 116.07, subd. 7(b).
Here, the county’s written decision not to require an EIS states that it is the RGU “as a delegated County in partnership with the [PCA.] ” This delegation occurred pursuant to the county’s Resolution for the Establishment of a County Animal Feedlot Program dated April 17, 1980. Under the PCA-approved Permit Application Processing Procedure associated with that delegation, the county agreed to forward to the director of the PCA “all animal feedlot permit applications” in certain categories, including “[a]nimal feedlots of 1,000 animal units or more[.]” While Finstuen’s proposed animal feedlot has a capacity of more than 1,000 AUs, it will house only 995 AUs. And Finstuen has indicated that, at present, he does not plan to increase the number of AUs housed at the proposed facility. Therefore, it could be argued that Finstuen’s proposed facility does not run afoul of the limits on the scope of the authority that the PCA delegated to the county. However, we reject this argument as inconsistent with the rules.
Delegated counties “shall” process permit applications as set forth in Minn. R. 7020.1600,subp. 4aA-D (2003). Minn. R. 7020.1600,subp. 4a (2003). Under these provisions, “[t]he county feedlot pollution control officer shall forward to the commissioner [of the PCA] for issuance all permit applications and all other applicable documents, comments, and recommendations” in several categories of applications, including “all facilities that are required to apply for a permit under part 7020.0405, subpart 1, item A or B[.]” Minn. R. 7020.1600,subp. 4aB(1). Minn. R. 7020.0405, subp. 1A, B(1) (2003), require a National Pollutant Discharge Elimination System permit for feedlots fitting the definition of a “concentrated animal feeding operation” (CAFO), and a “State disposal system” permit for “the construction and [583]*583operation” of a non-CAFO feedlot or manure storage area “capable of holding 1,000 or more [AUs] or the manure produced by 1,000 or more [AUs].” (Emphasis added.)
Although the record does not address whether Finstuen’s proposed feedlot is a CAFO, the record is uncontroverted that Finstuen’s application proposes the construction and operation of a feedlot that is “capable” of holding more than 1,000 AUs. Thus, if the proposed feedlot is a CAFO, it requires a permit under Minn. R. 7020.0405, subp. 1A; and if it is not a CAFO, it requires a permit under Minn. R. 7020.0405, subp. 1B(1). Because in either case the proposed feedlot requires a permit under rule 7020.0405, subpart 1, item A or B, the county was required to forward Finstuen’s permit application to the PCA. Minn. R. 7020.1600, subp. 4aB(1).
The county lacked authority to issue permits for Finstuen’s proposed feedlot and was required to forward Finstuen’s permit application to the PCA. We, therefore, reverse the county’s grant of Fin-stuen’s permit application. In light of our decision that the PCA, not the county, is the RGU, we need not address the parties’ disputes as to other aspects of the county’s processing of Finstuen’s feedlot permit application.
DECISION
Because Mark Finstuen’s proposed feedlot is physically capable of housing more than 1,000 animal units, and because Minn. Stat. § 116D.04, subd. 2a(d) (2004), exempts from environmental review only feedlots that are physically capable of housing fewer than 1,000 animal units, the statute does not exempt Finstuen’s proposed feedlot from environmental review. Dodge County has assumed responsibility to process feedlot applications under Minn. Stat. § 116.07, subd. 7 (2004). However, because Finstuen’s proposed feedlot is of a type listed in Minn. R. 7020.0405, subp. 1A, B (2003), Minn. R. 7020.1600, subp. 4aB (2003), rendered the PCA the responsible governmental unit and required the county to forward Finstuen’s feedlot permit application to the PCA.
Affirmed in part and reversed in part.