Bernardini v. Stefanowicz Corp.

349 A.2d 287, 29 Md. App. 508, 1975 Md. App. LEXIS 343
CourtCourt of Special Appeals of Maryland
DecidedDecember 31, 1975
Docket305, September Term, 1975
StatusPublished
Cited by8 cases

This text of 349 A.2d 287 (Bernardini v. Stefanowicz Corp.) is published on Counsel Stack Legal Research, covering Court of Special Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bernardini v. Stefanowicz Corp., 349 A.2d 287, 29 Md. App. 508, 1975 Md. App. LEXIS 343 (Md. Ct. App. 1975).

Opinion

Moore, J.,

delivered the opinion of the Court.

The question we are here asked to resolve is whether, in connection with the granting of specific performance of contracts for the purchase of lots upon which single-family residential units were to be constructed, the purchasers were entitled to an award of compensation measured not only by their out-of-pocket losses, but also by the “fair market net rental value” * 1 of their dwellings during the period of delay in construction. The Chancellor, Saíne, J., made a total award to the appellants of $20,875, constituting their out-of-pocket losses plus interest on their deposits. They assert on appeal that the award should not have included interest on their deposits but should have included an additional sum of $27,498, representing the fair market net rental value of their homes. There is no cross-appeal by the appellee builder-developer, The Stefanowicz Corporation.

The factual context in which the issue is joined is as follows: Between February and September, 1971 some ten families entered into written agreements with Stefanowicz for the purchase of lots in the Bolling Green development of Catonsville in Baltimore County. The lots were to be improved by dwellings “in substantial accordance” with *510 specified types of existing Model Homes. The purchase prices varied from approximately $27,500 to approximately $32,500 with completion dates 4 to 6 months from the dates of the respective agreements. In practically all instances, deposits of $2,000 were made and each purchaser was to secure his own financing.

None of appellants’ homes was ready on the dates originally specified. The delays were attributed by the builder to a variety of factors. Hurricane Agnes and other heavy rains in 1972 prevented routine progress from being made; the terrain was discovered to contain previously undetected obstacles, including rock formation and subterranean springs; and several of Stefanowicz’s subcontractors did not complete their work on time.

Nonetheless, when 7 of the 10 families instituted an equitable action on February 14, 1973 in the Circuit Court for Baltimore County, 2 the builder ultimately admitted liability and entered into ten 3 separate stipulations, in most of which the out-of-pocket losses were agreed upon; and in all of which the fair market net rental value of the respective homes was established. These stipulations provide the essential factual basis for this appeal, the parties having further stipulated pursuant to Maryland Rule 1026 c 2 that no part of the transcript of testimony at a hearing before Judge Raine on December 11, 1974 was necessary for the appeal. (The latter hearing was for the limited purpose of taking testimony with respect to certain claims for out-of-pocket losses upon which the parties were unable to stipulate and, it appears, to receive argument on the question of whether fair market rental value was also an appropriate measure of damages.)

The 10 stipulations reflect delays in construction ranging from 8 months to 17 months. The out-of-pocket losses, “reasonable and foreseeable,” agreed to have been sustained

*511 because of these delays, included some or all of the following items in the case of each family:

1. Forfeiture of rent bonus.
2. Furniture storage.
3. Child’s (school) registration fee.
4. Cost of disposable diapers.
5. Child’s commutation — extra travel expenses.
6.. Interim telephone installation.
7. Increase in laundry bills because equipment in storage.
8. Extra moving expense.
9. Mortgage interest increase.
10. Loss of postponement of capital gains on sale of former house.
11. Cost of obtaining clothing and other personal possessions from storage.
12. Additional commuting expense (by husband) to place of employment.
13. Forfeiture of child’s school registration fee.
14. Increase in child’s school tuition.
15. Increase in automobile insurance (difference between city and county rates).
16. Loss of apartment deposit.
17. Expenditure to “buy out” apartment tenant.

After the court hearing on December 11, 1974, Judge Raine also allowed one of the petitioners, an F.B.I. agent, damages for loss of U. S. Government reimbursement in the sum of $1291 for relocation costs. The claim had expired because of petitioner’s inability to move into the new house.

It was further stipulated that the builder believed that the measure of damages for its admitted liability was limited to these out-of-pocket expenses. The parties also stipulated, however, an amount of compensation based upon fair market net rental value in the case of each family purchaser, should the Chancellor deem such further award appropriate. Thus, in the case of appellants Bernardini, it was stipulated that:

(a) the length of delay for which the builder was accountable was 14 months;
*512 (b) the fair market rental value was $305 per month, or $4,270;
(c) the builder’s proper offset on the balance of the unpaid purchase price, at 6% per annum, was $2,190;
(d) the purchaser was entitled to recover simple interest at 6% per annum on the fair market net rental value of the dwelling from September 1, 1972 through December 1, 1974, in the total sum of $576;
(e) the final additional amount which would be due to Mr. and Mrs. Bernardini under this theory was $2,656. 4

The Chancellor, in a written opinion filed on February 20, 1975, rejected the appellants’ claims to awards based upon the theory of fair market net rental value but, as previously stated, did allow recovery of out-of-pocket losses, plus interest on the purchasers’ deposits. Judge Raine stated:

“After intensive study and consideration of the matter the court believes that the proper measure of damages are the reasonable and foreseeable expenses that the Complainants were required to make because of the Respondent’s delay in completing the dwellings.[ 5 ] The Complainants argue that in addition to these damages they should be awarded compensation for the loss of use and enjoyment of their homes, and seek to equate this with the net rental value of the dwellings during the period of delay.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Azat v. Farruggio
875 A.2d 778 (Court of Special Appeals of Maryland, 2005)
Giannetti v. Cornillie
530 N.W.2d 121 (Michigan Court of Appeals, 1995)
Montgomery Village Associates v. Mark
620 A.2d 975 (Court of Special Appeals of Maryland, 1993)
Godwin v. Lindbert
300 N.W.2d 514 (Michigan Court of Appeals, 1980)
Archway Motors, Inc. v. Herman
394 A.2d 1228 (Court of Special Appeals of Maryland, 1978)
Reis v. Sparks
547 F.2d 236 (Fourth Circuit, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
349 A.2d 287, 29 Md. App. 508, 1975 Md. App. LEXIS 343, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bernardini-v-stefanowicz-corp-mdctspecapp-1975.