Bernard v. United Brands Co.

538 N.E.2d 1003, 27 Mass. App. Ct. 415, 1989 Mass. App. LEXIS 320
CourtMassachusetts Appeals Court
DecidedJune 2, 1989
Docket88-P-15, 88-P-561, & 88-P-1239
StatusPublished
Cited by28 cases

This text of 538 N.E.2d 1003 (Bernard v. United Brands Co.) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bernard v. United Brands Co., 538 N.E.2d 1003, 27 Mass. App. Ct. 415, 1989 Mass. App. LEXIS 320 (Mass. Ct. App. 1989).

Opinion

Kaplan, J.

These appeals reduce to a question under rule 60(b) of the Massachusetts Rules of Civil Procedure, 365 Mass. 828 (1974). We mention the previous history.

In 1981, Ronald E. Bernard, claiming to have been injured when a plastics extruder machine exploded at his work station, commenced an action in Superior Court charging negligent design and failure to warn in which he first named United Brands Company (UBC) as defendant and later also asserted his claim against NRM Corporation (NRM). 2 NRM’s predecessor (National Rubber Machinery Co., Inc.) had manufactured the machine. UBC secured dismissal of Bernard’s action against itself on summary judgment (unopposed) but remained in the action in consequence of a cross-claim by NRM for indemnification based upon provisions in an agreement of December 1, 1969, to which UBC’s predecessor (AMK Corporation) was a party. NRM and UBC each moved for summary judgment upon the cross-claim. These motions were denied, as trial appeared necessary to describe the background of the agreement and resolve any ambiguity of its text.

In March, 1985, NRM settled Bernard’s claim against it for $110,000, and in October, 1986, the cross-claim for indemnification was tried (nonjury). The trial judge held for NRM against UBC, writing a memorandum with findings and conclusions. Judgment for $110,000 against UBC entered on March 6, 1987.

UBC attempted on April 8, 1987, to lodge in Superior Court a notice of appeal from the judgment, but the clerk refused to file it because the thirty-day period had been exceeded. UBC had misread and misapplied Mass.R.Civ.P. 6(d), 365 Mass. 748 (1974) (the so-called “mailbox rule”). A judge of the Superior Court on May 5, 1987, allowed UBC’s motion under Mass.R.A.P. 4(c), as amended, 378 Mass. 929 (1979), on grounds of “excusable neglect” to enlarge the time to file its *417 appeal. 3 NRM appealed to our court from the order permitting the late filing. A panel of our court reversed the order, and the Supreme Judicial Court denied further appellate review.

UBC now rallied its forces on two fronts. On December 8, 1987, it appealed to a single justice of our court under Mass.R.A.P. 14(b), as amended, 378 Mass. 939 (1979), to extend for “good cause” its time to appeal from the $110,000 judgment. 4 The single justice referred the application to a panel of the court (which is the present panel) together — if the application be granted — with the appeal from the judgment. NRM opposed the application. It entered an (unnecessary) appeal from the single justice’s order of reference. 5

UBC’s second expedient was to move on February 29, 1988, in the lower court for relief from the judgment under rule 60(b) of the Massachusetts Rules of Civil Procedure. 6 Proof was offered on either side by affidavits. On July 27, 1988, the motion was denied, with memorandum, by the same judge who entered the judgment. UBC appeals the denial.

*418 So we have before us UBC’s application under appellate rule 14(b) (and a nominal appeal, No. 88-P-15, by NRM from the single justice’s order of reference). We shall deny the application, thus aborting an appeal, No. 88-P-561, by UBC from the judgment on the cross-claim. In No. 88-P-1239, we affirm the order denying UBC’s application under rule 60(b).

1. There is argument that the two routes — appellate rules 4(c) and 14(b) — are mutually exclusive in the sense that a party may not resort to 14(b) if he has moved under 4(c) (or perhaps if he has so moved and the motion has been ruled on). So absolutist a view is discountenanced by the remarks in Harvard Community Health Plan, Inc. v. Assessors of Cambridge, 384 Mass. 536, 537 & n.2 (1981). 7 We' need not go so far. We think it should be held as a matter of litigative economy, if nothing else, that where a 4(c) application has been carried (unsuccessfully) through to the Supreme Judicial Court, then a 14(b) application is precluded at least if it is based on substantially the same grounds as the 4(c) application. That would dispose of the 14(b) application here, for UBC in our view has not improved materially on the application it made under rule 4(c) claiming excusable neglect. But, if there is no definite rule of preclusion in such a case and the matter lies in discretion, 8 we would exercise that discretion against *419 reviving the appeal under 14(b). Indeed, we would reach the same end result if we disregarded the prior 4(c) application altogether and considered independently whether good cause had been shown under 14(b).

Our conclusion is strengthened by our examination of the lower court’s interpretation of the indemnity provision leading to the judgment. The interpretation was correct; the judge’s explanatory memorandum is reasoned and convincing.

Under the 1969 agreement AMK Corporation, owning all the shares of NRM, sold these shares for a price to Condec National, Inc. (a wholly owned subsidiary of Condec Corporation). Signatories to the agreement were AMK Corporation, Condec National, Inc., and Condec Corporation. Part of the consideration was a promise by AMK (with certain immaterial exceptions) to indemnify Condec National, Inc., Condec, and NRM from liability “arising from any operations, acts, omissions or conduct of NRM or AMK,” prior to the date of the agreement, to the extent that the “aggregate” of the liability should exceed $175,000. (See agreement, articles X[a] and X[d].) UBC, succeeding to AMK, contended, despite the use of the term “aggregate,” that the indemnification ran only to such liabilities as individually exceeded $175,000. It contended also that a clause (agreement, section 11.02), which set an eighteen-month period following December 1,1969, for asserting claims under the agreement, applied to the indemnification provision, although that provision appeared to be expressly excepted from the clause. 9 The judge, considering the evidence *420 received at trial as well as the relevant texts, rejected both contentions: although the draftsmen, he said, “are not in line for a Pulitzer Prize, ... the expressed intent of the parties and common sense should prevail.” We agree with the judge that the obligation to indemnify extended to the Bernard claim —' the exact point of decision.

2. We have to consider whether the judge (the judge who tried the case) abused his discretion in refusing UBC relief from the judgment on the cross-claim. UBC’s application was based on its production of an agreement of July 31, 1974, between UBC (succeeding AMK) and Condec Corporation (into which Condec National, Inc., had been merged). NRM adhered expressly only to certain provisions of the agreement.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

DANA M. CHILES, Trustee v. THOMAS W. LITTAUER.
Massachusetts Appeals Court, 2024
Commonwealth v. Smith
Massachusetts Supreme Judicial Court, 2023
Masomi v. Madadi
94 N.E.3d 435 (Massachusetts Appeals Court, 2017)
Commonwealth v. Salinger
927 N.E.2d 463 (Massachusetts Appeals Court, 2010)
Troy Industries, Inc. v. Samson Manufacturing Corp.
924 N.E.2d 325 (Massachusetts Appeals Court, 2010)
Magni v. Patriot Home Improvement
2008 Mass. App. Div. 21 (Mass. Dist. Ct., App. Div., 2008)
Commonwealth v. Trussell
862 N.E.2d 444 (Massachusetts Appeals Court, 2007)
Commonwealth v. Barboza
861 N.E.2d 37 (Massachusetts Appeals Court, 2007)
Shaev v. Alvord
848 N.E.2d 438 (Massachusetts Appeals Court, 2006)
Choice Health v. Devcon Enterprises, Inc.
2006 Mass. App. Div. 93 (Mass. Dist. Ct., App. Div., 2006)
Marnerakis v. Phillips, Silver, Talman, Aframe & Sinrich, P.C.
840 N.E.2d 951 (Massachusetts Supreme Judicial Court, 2006)
Girard v. Krupnick
2004 Mass. App. Div. 174 (Mass. Dist. Ct., App. Div., 2004)
Enterprise Rent-A-Car v. Bigelow
2004 Mass. App. Div. 165 (Mass. Dist. Ct., App. Div., 2004)
Rasheed v. Commonwealth
798 N.E.2d 1022 (Massachusetts Supreme Judicial Court, 2003)
Crystal Construction Corp. v. Hartigan
778 N.E.2d 915 (Massachusetts Appeals Court, 2002)
Yanis v. Metropolitan Property & Casualty Insurance
2002 Mass. App. Div. 98 (Mass. Dist. Ct., App. Div., 2002)
Paquette v. Premier Insurance
2000 Mass. App. Div. 250 (Mass. Dist. Ct., App. Div., 2000)
Lawrence Savings Bank v. Garabedian
727 N.E.2d 97 (Massachusetts Appeals Court, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
538 N.E.2d 1003, 27 Mass. App. Ct. 415, 1989 Mass. App. LEXIS 320, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bernard-v-united-brands-co-massappct-1989.