Bernard Gloekler Co. v. Carr

79 S.E. 732, 72 W. Va. 720, 1913 W. Va. LEXIS 118
CourtWest Virginia Supreme Court
DecidedSeptember 30, 1913
StatusPublished

This text of 79 S.E. 732 (Bernard Gloekler Co. v. Carr) is published on Counsel Stack Legal Research, covering West Virginia Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bernard Gloekler Co. v. Carr, 79 S.E. 732, 72 W. Va. 720, 1913 W. Va. LEXIS 118 (W. Va. 1913).

Opinion

LYNCH, Judge :

By an action of assumpsit brought in the intermediate court of Kanawha county, plaintiff seeks to recover damages for the breach of a contract between it and the defendant. The Jury first empanelled found for defendant. On writ of error, the circuit court set the verdiet aside and remanded the case. On the second trial the jury, at the direction of the court, found for plaintiff the sum of $469.22, that being the amount claimed by the plaintiff in its bill of particulars and affidavit filed with the-declaration. The intermediate court rendered judgment on the verdiet, which, on writ of error, the circuit court affirmed.

The contract, the breach of which is averred, is, in substance,, that plaintiff proposed in writing to furnish and erect complete-in defendants store certain fixtures, designating each item by name or number o-r otherwise, and adding: “Exposed parts-of above in solid and veneered mahogany; all glass bevel plate,, and all mirrors No. 1 grade same, metal back; all cases to be-all plate — plate shelves 10" marble base; finish — best quality, hand-polished and rubbed. Complete plans, specifications, and details to be submitted and approved by purchaser. Price-$2,145.” Signed: “Bernard Gloekler Co., per Leon Shipman-Accepted — Jas. A. Carr, Carr’s Drug Store.”

On writ of error here, the defendant raises two questions, and' none other: “First: Was the contract sued on intended to be- in truth a contract, or merely a preliminary agreement or order revocable by either party until the fulfillment of certain conditions? Second: If intended by the parties to- be a binding agreement, is it sufficiently certain to afford any basis of enforcing it?” Both of which are in fact questions to be determined by the court.

The argument in support of the first proposition is that, until complete plans, specifications and details were - submitted by plaintiff and approved by defendant, the contract was incomplete — not binding on, and therefore revocable by, either of them. We do not agree-to that conclusion. Nor does Plumbing Co. v. [722]*722Carr, 54 W. Va. 272, or Barrett v. Coal Co., 51 W. Va. 416, cited support it. Neither case asserts any such proposition. They hold that, where work is to be done or materials furnished to the satisfaction of the owner, the latter may withhold final payment if the work and materials are not satisfactory to him, provided his "rejection is in good faith and not fraudulent." If fraudulent and not in good faith, his rejection will not avail to defeat payment. In this case, Carr did not afford plaintiff an opportunity to prepare- and submit plans and specifications for his approval. Within an hour after accepting the order, he arbitrarily sought to revoke it, assigning as the only reason that he had purchased the same fixtures from another company at a materially reduced price. Our opinion is that plaintiff’s offer and defendant’s acceptance have all the necessary elements of a contract binding oh both, notwithstanding the final clause providing for the approval of plans and specifications. These were not made a condition of the offer and acceptance, either in express terms or by implication. Carr, neither in his letter addressed to plaintiff the day after liis acceptance of the order, nor in his testimony, sought to rely on the final clause as an element of the contract of purchase. In the letter, the difference in cost is urged as his reason for the recall of the agreement.

In his testimony, he frankly repeats and emphasizes the same Teason. From his testimony, it is also apparent that he did not ■attach any importance to the plans and specifications as an element of the contract. On the contrary, it is clear that he ■deemed them only a detail of the final completion of the work, the performance of which plaintiff assumed by the agreement— a conclusion in accord with reason and in harmony with a fair interpretation of the agreement. He testifies that “Mr. Ship-man said that -the plans and specifications would come in water colors and show the store as it would appear as you would walk in from the front, set in position; that is the idea I wanted of the store, to know how it would look.” It was “to suit my taste in the matter.” 'The natural and only reasonable inference from 'this statement is that the plans and specifications related only to the manner of doing the work: that is, when completed the fixtures should cause the store to appear attractive to his patrons, and hence be helpful in his business, an advertisement. [723]*723Even after receiving the plans and specifications prepared and forwarded by plaintiff to defendant, he admits he had no objection to them, although he at once returned them to plaintiff.

Our interpretation is sustained, to' some extent, by Sellers v. Greer, 172 Ill. 549, 40 L. R. A. 589; Alderton v. Williams, 139 Mich. 297; Moran Manufacturing Co. v. St. Louis Car Co. (Miss.), 109 S. W. 47; Hinckley v. Pittsburgh Steel Co., 121 U. S. 265. In the Sellers case, the proposal was that Greer was to take all the Greer patents and all special machinery attached to punching machines and all other appliances belonging to the making of spikes, surrender.his stock in M. S. & Co. and to furnish it complete sets of templets for splices, the company to loan machine No. 4 for six months and pay Greer $1,800 towards a new machine for cutting spikes, Greer to fill all the present orders so far as the material on hand would complete them; “This agreement to be put in proper form at as early a date as possible, pending thd return of the company’s attorney to draw up the necessary releases, etc.” The court said: “There is nothing appearing on the face of the contract, nor is there anything in the evidence introduced on the hearing, to sustain the position that the proposal was not intended to be a complete and binding contract. The contract is definite and specific in regard to what was to be done by each of the parties.” The Alderton case holds that “a contract by which it is agreed to change a heading mill into a stave mill and carry on the; business of manufacturing staves is not void for indefiniteness in that it fails to specify the kind of machinery to be bought or the kind of staves to be manufactured.” Here, the fixtures sold are specified in detail. More directly in point is the Moran case. The order proposed by defendant and accepted by plaintiff was: “Enter our order for 1,000 net tons of bar iron at $1.70 per 100 lbs. f. o. b. our works, half card extra; no charge for cutting to length. 5-feet or over; specifications to be furnished during balance of year.” The car company declined to furnish the specifications, inferentially because the price of iron materially decreased before the expiration of the year. The court held that “the contract, in view of the evidence, was mutually binding on both [724]*724parties, specifically stating the quantity, kind and price of the goods sold, and the refusal of the buyer to specify and accept the goods in conformity with the contract was a breach thereof.”

In Hinckley v. Steel Co., the court states the essence of the contract in the syllabus, to the effect that the defendant agreed in writing to purchase from the plaintiff rails to be rolled by the latter “and to be drilled as may be directed,” and to pay for them $58 per ton.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Womble v. Hickson
121 S.W. 401 (Supreme Court of Arkansas, 1909)
Sellers v. Greer
40 L.R.A. 589 (Illinois Supreme Court, 1898)
Moran Bolt & Nut Manufacturing Co. v. St. Louis Car Co.
109 S.W. 47 (Supreme Court of Missouri, 1908)
Barrett v. Coal Co.
41 S.E. 220 (West Virginia Supreme Court, 1902)
Plumbing Co. v. Carr
46 S.E. 458 (West Virginia Supreme Court, 1903)

Cite This Page — Counsel Stack

Bluebook (online)
79 S.E. 732, 72 W. Va. 720, 1913 W. Va. LEXIS 118, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bernard-gloekler-co-v-carr-wva-1913.