Berloni SpA v. Della Casa, LLC

972 So. 2d 1007, 2008 Fla. App. LEXIS 46, 2008 WL 34821
CourtDistrict Court of Appeal of Florida
DecidedJanuary 2, 2008
Docket4D06-3862
StatusPublished
Cited by18 cases

This text of 972 So. 2d 1007 (Berloni SpA v. Della Casa, LLC) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Berloni SpA v. Della Casa, LLC, 972 So. 2d 1007, 2008 Fla. App. LEXIS 46, 2008 WL 34821 (Fla. Ct. App. 2008).

Opinion

972 So.2d 1007 (2008)

BERLONI S.P.A., Appellant,
v.
DELLA CASA, LLC, Appellee.

No. 4D06-3862.

District Court of Appeal of Florida, Fourth District.

January 2, 2008.

*1008 Nancy Little Hoffmann of Nancy Little Hoffmann, P.A., Pompano Beach, and Joanne Fanizza of Law Offices of Joanne Fanizza, P.A., Fort Lauderdale, for appellant.

*1009 Joseph L. Rebak and Maria N. Vernace of Tew Cardenas LLP, Miami, for appellee.

WARNER, J.

In a breach of contract action for goods sold, the trial court reduced an award to the appellant for what the appellee claimed were amounts covered by partial releases. The court also refused to award prejudgment interest to the appellant. We hold that the trial court erred in reducing the award and in not awarding prejudgment interest from the date of the filing of, the complaint.

Berloni S.p.A., an Italian corporation, and Della Casa, LLC, a Florida company, entered into an agreement whereby Berloni agreed to supply the kitchens and bathrooms to Della Casa for a condominium project known as the Continuum. Although the agreement required payment within sixty days of the product's arrival in Miami, in any event payment was due within 120 days of the issuance of the bill of lading. Berloni provided kitchens for other projects of Della Casa, but no other written agreements were signed with respect to other projects.

In August and December 2002 Berloni executed final releases for two projects, the Continuum and Gables Club projects. It also executed partial releases in January 2003 to obtain payment of some amounts owed on other projects, including Murano Grande.

The parties' relationship soured. Della Casa did not make payments to Berloni, and it claimed overpricing and defective workmanship. Berloni filed suit against Della Casa in July 2003, alleging that it had failed to pay for the kitchens. Della Casa answered and raised payment and release as an affirmative defense, attaching the releases. The case was tried before a jury, and the issue of the validity of the releases was submitted to the jury, although a motion for directed verdict was reserved by the, trial court.[1] The jury awarded damages to Berloni for unpaid amounts in connection with projects including Murano Grande but awarded no damages for the Continuum and Gables Club projects. The verdict totaled $2,142,075.63, which included $975,590.83 for the Murano Grande claim.

Della Casa moved for a new trial on several grounds, including that the jury awarded damages for Murano Grande for amounts covered by the partial releases. Its attorney maintained that "the jury just blew it on this." He claimed that the express provision of the partial releases provided for the release of all work done prior to their execution. Berloni argued that the jury had considered the releases, noting that the court had instructed the jury to give effect to the releases and that the jury had not awarded Berloni all that was requested on the Murano claim. The trial court granted Della Casa's motion to that extent and reduced the Murano Grande award by $891,266.12, which constituted work Berloni performed prior to the execution of the partial releases.

Berloni moved for an award of prejudgment interest. The trial court denied the award, because the issue had not been submitted to the jury and the amount was hotly disputed. Berloni appeals the resulting final judgment, arguing both the reduction of the Murano Grande claim and the failure to award prejudgment interest.

*1010 I. Reduction of Verdict Because of Release

The trial court's interpretation of a contract is a matter of law subject to a de novo standard of review. Gossett & Gossett, P.A. v. Mervolion, 941 So.2d 1207, 1210 (Fla. 4th DCA 2006); Atlanta Jet v. Liberty Aircraft Servs., LLC, 866 So.2d 148, 150 (Fla. 4th DCA 2004). However, "[w]here there are two reasonable interpretations of an agreement, the question is one for the trier of fact." McDonald v. McDonald, 731 So.2d 132, 133 (Fla. 4th DCA 1999). See also AT & T Wireless Servs. of Fla., Inc. v. WCI Cmtys., Inc., 932 So.2d 251, 255 (Fla. 4th DCA 2005).

The language of an agreement is to be construed most strongly against its drafter. Fla. State Tpk. Auth. v. Indus. Constr. Co., 133 So.2d 115, 117 (Fla. 2d DCA 1961). Della Casa drafted the partial releases, and they contained the following language:

For and in consideration of the payment of $ [amount filed in] . . . the sufficiency of which is hereby acknowledge[d], the Undersigned does hereby waive, release and relinquish [any] and all rights, claims, demands, liens, claims, for relief, causes of action and the like, whether arising at law, under a contract, in tort, in equity or otherwise, which the Undersigned has now or may have had arising out of the performance of work or the furnishing of materials by the undersigned for the above stated amount, pursuant to the contract with DELLA CASA, LLC in connection with the construction of The Murano Grande (the "Project").

(emphasis added). Berloni executed three partial releases on the Murano Grande project, each with the identical language. This language could mean either that claims with respect to all prior work are released, or that Berloni releases only claims with respect to work performed for the amount of payment and no more. Thus, given both possible interpretations, the issue was submitted to the trier of fact.

Although the releases were an affirmative defense, Della Casa did not move for a directed verdict at the close of its case on this ground and did not object to the jury instruction regarding the effect of the releases. In fact, in closing argument Della Casa did not even argue that the partial releases precluded payment for almost all of the Murano Grande payments. Its attorney only mentioned the final releases and suggested a zero verdict for the Continuum and Gables Club project. The jury complied.

The evidence presented by Berloni showed that the jury's award was slightly less that the difference between the amount Berloni billed on Murano Grande less the amount of payments made by Della Casa, for which partial releases were given. Even though the amounts do not completely align, the jury asked whether it could make individual adjustments in the amounts it found due. The court instructed that it could do so. In any event the jury awarded an amount less than Berloni claimed was due.[2] The jury thus gave Della Casa credit for payments actually made. It did not give credit for all work done prior to the partial release. This was a permissible interpretation of the meaning of the release, and at trial Della Casa did not argue otherwise.

Because the partial release issue was properly submitted to the jury, and there was competent substantial evidence supporting its verdict, the trial court erred in directing a verdict post-trial and reducing *1011 Berloni's recovery. On remand, the final judgment in the full amount of the damages awarded should be reinstated.

II. Failure to Award Prejudgment Interest

In its final judgment, the court denied Berloni's request for prejudgment interest because it failed to submit the issue of entitlement to prejudgment interest to the jury. Accordingly, the court found that it waived any claim it may have asserted to recover prejudgment interest. The court noted Berloni's reliance on Argonaut Insurance Co. v. May Plumbing Co.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

ARNE LANGSETMO v. KRISTEN MARIE METZA
District Court of Appeal of Florida, 2022
THE STERLING VILLAGES OF PALM BEACH LAKES v. JOEL LACROZE
District Court of Appeal of Florida, 2018
SP Healthcase Holdings, LLC v. Surgery Center Holdings, LLC
208 So. 3d 775 (District Court of Appeal of Florida, 2016)
Arizona Chemical Company, LLC v. Mohawk Industries, Inc., and Aladdin etc.
197 So. 3d 99 (District Court of Appeal of Florida, 2016)
Citizens Property Insurance Corporation v. Nunez
194 So. 3d 1064 (District Court of Appeal of Florida, 2016)
Current Builders of Florida, Inc. v. Certified Lower Keys Plumbing
105 So. 3d 582 (District Court of Appeal of Florida, 2012)
Crittenden v. Davis
89 So. 3d 1098 (District Court of Appeal of Florida, 2012)
Wood v. Unknown Personal Representative of the Estate of Burnette
56 So. 3d 74 (District Court of Appeal of Florida, 2011)
Reimbursement Recovery, Inc. v. Indian River Memorial Hospital, Inc.
22 So. 3d 679 (District Court of Appeal of Florida, 2009)
McCarthy v. Estate of Krohn
16 So. 3d 193 (District Court of Appeal of Florida, 2009)
Jablonski v. St. Paul Fire and Marine Ins. Co.
645 F. Supp. 2d 1101 (M.D. Florida, 2009)
Detroit Diesel Corp. v. Atlantic Mutual Insurance Co.
18 So. 3d 618 (District Court of Appeal of Florida, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
972 So. 2d 1007, 2008 Fla. App. LEXIS 46, 2008 WL 34821, Counsel Stack Legal Research, https://law.counselstack.com/opinion/berloni-spa-v-della-casa-llc-fladistctapp-2008.