Bennington v. Inland Investments Co.

956 P.2d 1028, 153 Or. App. 209, 1998 Ore. App. LEXIS 421
CourtCourt of Appeals of Oregon
DecidedApril 1, 1998
DocketCCV9310376; CA A88183
StatusPublished
Cited by1 cases

This text of 956 P.2d 1028 (Bennington v. Inland Investments Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bennington v. Inland Investments Co., 956 P.2d 1028, 153 Or. App. 209, 1998 Ore. App. LEXIS 421 (Or. Ct. App. 1998).

Opinion

WARREN, P. J.

In this case, James and Cynthia Bennington (Benningtons) were awarded specific performance of a land sale contract with Inland Investment Company, Inc. (Inland).1 Inland appeals various aspects of the judgment. We affirm.

On June 1, 1990, Inland contracted to sell approximately 20 acres of unimproved property to Benningtons for $39,500, including an option on an adjoining strip. Benning-tons paid $10,000 down and contracted to pay $300 per month beginning in July 1990. In the contract, Inland promised to grade the access road to the property and provide a survey of the property by August 1,1990. Inland agreed that if these were not done the Benningtons could deduct $1,800 for the failure to grade and $1,500 for failure to provide the survey from their monthly payments.

Inland failed to grade the road by August 1, 1990; however, at the request of Benningtons, the grading was completed in October 1990. The survey required by the contract was not completed by August 1,1990, but was provided to Benningtons during the summer of 1991. Believing that Inland had violated both contract provisions, Benningtons began withholding payments in October 1990 and did not resume their monthly payments.

Before entering into the contract with Benningtons, Inland had deeded ownership of the standing and downed timber on the property to Clear Lumber Manufacturing Corp. (Clear Lumber) with the right to remove standing and downed timber until December 29, 1991. Benningtons were aware of Clear Lumber’s timber deed. Inland, however, warranted to Benningtons that before closing, Inland would repurchase the standing timber and transfer that ownership interest as part of the contract. Inland assured Benningtons that the standing timber would not be cut. In fact, Inland’s [212]*212owner mistakenly believed that he had reacquired his interest in the timber and did purport to convey the standing timber to Benningtons. After Benningtons entered into the contract, Clear Lumber continued to cut standing timber on the property. The trial court valued the removed timber at $11,319.

Benningtons attempted to exercise their option to purchase the adjoining strip of land in November 1990. Inland refused to honor the option agreement, because, believing that Benningtons were in breach of the contract for failing to make their monthly payments, it had sold the property to Mukhtiar Dhillon.

On August 31, 1993, Inland mailed to Benningtons’ attorney a notice of default and forfeiture pursuant to ORS 93.915(4). Inland claimed that Benningtons were in default for failure to make their $300 monthly payments after August 1,1990.2 The notice provided that, unless the default was cured within 60 days of the date of the notice, the contract would be canceled and deemed null and void. As a sixth affirmative defense and first counterclaim, Inland asserted at trial that, because Benningtons did not cure the default within 60 days, their interest in the property was forfeited. Benningtons, in their seventh claim for relief, requested an order of the court enjoining Inland from declaring a forfeiture of their interest in the property. Benningtons asserted that Inland had failed to comply with the forfeiture requirements of ORS 93.905 et seq and that Inland was in breach of the contract at the time of the attempted forfeiture.

After a trial to the court, the court held that Inland’s failure to complete the survey required pursuant to the contract was a substantial and material breach and that Benningtons properly withheld five consecutive monthly payments from October 1990 through February 1991, or the total sum of $1,500. The court also held that Inland’s failure to complete the grading was a technical breach of the contract but that that breach was cured by Benningtons directing [213]*213Inland’s workers to finish the grading in October 1990. Additionally, the court held that Benningtons were excused from resuming their monthly payments after February 1991, for: (1) Inland’s failure to honor the exercise of Benningtons’ option; (2) Inland’s “selling” of the option property to Dhillon; (3) Inland’s failure to preserve the standing timber promised to Benningtons; and (4) Inland’s failure to perform its survey, grading and cleanup within the time promised in the agreement.

Before trial, Benningtons deposited with the court $41,000 as evidence of their ability to perform the contract fully. In its judgment, the trial court granted Benningtons specific performance and made the following setoffs and adjustments to the contract price. The original contract price was $39,500. At signing, Benningtons paid a down payment of $10,000, which left an unpaid balance as of June 1,1990, of $29,500. The court valued the improperly harvested trees at $11,319 and subtracted that amount from the contract price, leaving $18,181. Benningtons made two monthly payments of $300, of which $297.44 was credited toward the principal amount. The court also allowed a $1,500 setoff for Inland’s failure to timely complete the survey, leaving a total of $16,383.56 due on the contract plus $7,590.30 in interest from August 1, 1990. Benningtons were awarded attorney fees of $20,417.12 and costs of $1,222.91. After setting off the contract amount, plus interest, against the attorney fees and costs, Benningtons owed Inland $2,333.83.

Dhillon, in his cross-claim against Inland, was awarded $10,150.06, which represented $1,350.65 for his loss of the option property and $8,799.50 in attorney fees and costs. The court ordered that the $2,333.83 then owing from Benningtons to Inland would be taken out of the money the Benningtons had tendered to the court and ordered it paid to Dhillon in partial satisfaction of his judgment against Inland. The remaining amount tendered to the court was given back to Benningtons as a consequence of the credits against the purchase price described above. Dhillon received a judgment for the remaining amount, $7,816.32, against Inland.

Inland makes various assignments of error. First, Inland asserts that its forfeiture of the contract, pursuant to [214]*214ORS 93.915, was not stayed during these proceedings and that Benningtons lost any claim of ownership to the property 60 days after the notice of forfeiture was sent. Second, Inland argues that the court erred by setting off the amount Benningtons owed Inland on the contract against Benning-tons’ attorney fees judgment against Inland, effectively giving Benningtons an unfair priority over the funds. Third, Inland argues that its attorneys’ lien, which was filed before the judgment, has priority over the funds that were owed to Inland on the contract price. Fourth, Inland argues that the court erred by measuring the damages for the wrongfully removed timber in terms of stumpage value rather than the change in the retail market value of the land. In response to all assignments of error, Benningtons assert that Inland waived its right to appeal.

Benningtons contend that Inland has waived its right to appeal by accepting the benefits of the judgment. The general rule is that a party cannot claim the benefit of a judgment and at the same time appeal from it. Pac. Gen. Contrs. v. Slate Const. Co., 196 Or 608, 611, 251 P2d 454 (1952).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Heine v. Bank of Oswego
144 F. Supp. 3d 1198 (D. Oregon, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
956 P.2d 1028, 153 Or. App. 209, 1998 Ore. App. LEXIS 421, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bennington-v-inland-investments-co-orctapp-1998.