Bennett Veneer Factors, Inc. v. Brewer

441 P.2d 128, 73 Wash. 2d 849, 1968 Wash. LEXIS 703
CourtWashington Supreme Court
DecidedMay 16, 1968
Docket38843
StatusPublished
Cited by39 cases

This text of 441 P.2d 128 (Bennett Veneer Factors, Inc. v. Brewer) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bennett Veneer Factors, Inc. v. Brewer, 441 P.2d 128, 73 Wash. 2d 849, 1968 Wash. LEXIS 703 (Wash. 1968).

Opinion

Neill, J.

Plaintiff (appellant) brings an action for damages and loss of profits claiming that defendants have breached a contract wherein plaintiff was given a preemptive right to purchase all logs which defendants cut from two particular tracts of United States Forest Service lands. At the conclusion of plaintiff’s case on the issue of liability, *850 defendants moved to dismiss on the grounds that plaintiff had failed “to substantiate the essential allegations of the complaint.” 1 The motion was granted and plaintiff appeals.

A separate trial was contemplated on the damages issue. CR. 42 (b), RCW vol. O.

Plaintiff sets out seven assignments of error, mainly challenging the trial court’s findings of fact, but admits that all assignments involve essentially a single question, namely, whether there was substantial evidence that the parties had entered into a valid contract, breached by the defendants, whereby plaintiff had a first refusal right to purchase certain logs from the defendants.

The trial judge announced in his oral opinion that he was weighing the evidence. Therefore, we are governed in this appeal by the rule set forth in Cowitz v. Miller, 68 Wn.2d 637, 414 P.2d 795 (1966):

When the trial court has weighed the evidence and has apprized this court by findings of fact of the evidence it found credible or of the facts it found which would prevent plaintiff from recovering, this court will accept the findings of fact as verities unless we determine that there is no credible and substantial evidence to support the findings. We cannot, however, substitute our findings for those of the trial court.

The issues presented to us arise from a rather complicated background of financial difficulties involving a veneer plant (Fish Veneer, Inc.), the plaintiff (a veneer broker who attempted to assist Fish Veneer), and the defendants who were also involved in Fish Veneer’s financial troubles. In 1960, Fish Veneer’s predecessor in interest obtained two timber contracts from the United States Forest Service. *851 That contractor then employed defendants to construct logging roads on these timber tracts. In 1963, plaintiff contracted for the purchase of the entire production of the Fish Veneer plant and at this time also loaned Fish Veneer approximately $40,000 for operational funds. To secure this loan, plaintiff took an assignment of the two government timber contracts and assignments of Fish Veneer’s accounts receivable. Further, plaintiff agreed to pay Lacey Plywood Company the balance owing by Fish Veneer on a machinery contract. Fish Veneer was also in arrears on a $350,000 Small Business Administration loan. In fact, continuation of Fish Veneer plant operations was in jeopardy. Plaintiff, apparently in order to obtain the veneer production from this plant, entered into a plan whereby it rented the Fish Veneer plant, furnished logs or money for logs, and in return received the veneer. Fish Veneer’s creditors were to be paid through the rentals to be paid by plaintiff. This plan later became part of a state court composition in Lewis County.

Before this financing scheme could be put into operation, defendants advised Fish Veneer by letter of May 5, 1964, that delinquent road construction costs of $167,991.36 must be paid before any further logging would be permitted in the government tracts.

On May 15, 1964, a meeting was held at which all involved parties were either present or represented by counsel. At this meeting, defendants produced an estimate showing the prices at which the timber remaining to be cut from the government tracts would have to be sold in order to produce a profit. These estimates were $75 per thousand board feet for fir and $50 per thousand board feet for hemlock. At this meeting defendants’ counsel dictated (and subsequently mailed to plaintiff) a letter summarizing the agreement reached by the parties, to wit: defendants would take over the government timber contracts and log the tracts; all road construction indebtedness to defendants would be cancelled; defendants would assume and pay the Small Business Administration loan; and “That all logs pro *852 duced under the Forest Service contracts and in the entire area will be offered to Bennett Veneer Factors on a first-refusal basis ” (Italics ours.)

The parties to this financing and operations arrangement, with the exception of plaintiff, met again on June 2, 1964, at which time defendants offered to sell the logs to plaintiff at prices of $80 for fir and $56 for hemlock. During the meeting, defendants’ counsel telephoned plaintiff’s counsel in Seattle and relayed the new price quotation to him. Plaintiff’s attorney then called plaintiff in Oregon regarding this offer. Plaintiff refused the offer. There is a dispute as to whether the new price quotation related to all the subject logs or to only a portion thereof. The trial court found that all the logs were included in the higher quotations, and that plaintiff did not communicate to defendants that its rejection of the new prices related to less than all the logs. It is not disputed that, during their telephone conversation, the attorneys for plaintiff and defendants discussed the difference between the prices being quoted to plaintiff and a $3-per-thousand lower price being quoted by defendants to other potential buyers. The trial court found that the prices quoted in the May 15th estimate were not firm or agreed prices, but were only an indication of a price level at which a profit could be made.

The defendants thereafter refused to sell plaintiff any logs. Due to a log shortage in the area, plaintiff was unable to purchase logs elsewhere and was unable to continue to operate the Fish Veneer plant.

Plaintiff contends that defendants entered into a contract to sell the logs to a third party at a price less than that quoted to plaintiff on June 2d, and that such contract was executed prior to the June 2d price quotation to plaintiff. The trial court found, however, that this sale and sales of logs to other third parties occurred subsequent to June 2d. The log sales subsequently made by defendants to third parties were essentially at prices of $77 for fir and $53 for hemlock, thus giving rise to plaintiff’s contention that defendants violated the “first refusal right” portion of the *853 May 15th agreement. Plaintiff produced testimony that it would have paid the $77 and $53 on June 2d.

Among the findings challenged by the plaintiff is finding of fact No. 11:

The Court finds there was no meeting of the minds on the claim proposed by plaintiff that it had a continuous right of first refusal and no contract between the parties enforceable by the plaintiff, nor any breach of any contract by the defendants.

This paragraph contains mixed findings of fact and conclusions of law and is somewhat sketchy and ambiguous. Nevertheless, we will read this finding in context with the court’s other findings and in light of the court’s oral opinion. Northern Pac. Ry. v. Washington Util. & Transp. Comm’n,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Borton & Sons, Inc. v. Burbank Properties, LLC
444 P.3d 1201 (Court of Appeals of Washington, 2019)
Estate of Garth Benjamin Peterson
Court of Appeals of Washington, 2013
Chevalier v. Woempner
290 P.3d 1031 (Court of Appeals of Washington, 2012)
Kelly v. Ammex Tax and Duty Free Shops West, Inc.
256 P.3d 1255 (Court of Appeals of Washington, 2011)
Brotherson v. Professional Basketball Club, LLC
604 F. Supp. 2d 1276 (W.D. Washington, 2009)
Manufactured Housing Communities v. State
13 P.3d 183 (Washington Supreme Court, 2000)
Manufactured Housing Communities v. State
951 P.2d 1142 (Court of Appeals of Washington, 1998)
Unlimited Equipment Lines, Inc. v. Graphic Arts Centre, Inc.
889 S.W.2d 926 (Missouri Court of Appeals, 1994)
Old National Bank v. Arneson
776 P.2d 145 (Court of Appeals of Washington, 1989)
Yates v. State Board for Community College Education
54 Wash. App. 170 (Court of Appeals of Washington, 1989)
David Meyers, Inc. v. Anderson
739 P.2d 102 (Court of Appeals of Washington, 1987)
Interlake Porsche + Audi, Inc. v. Bucholz
728 P.2d 597 (Court of Appeals of Washington, 1986)
King v. Bilsland
727 P.2d 694 (Court of Appeals of Washington, 1986)
Rajala v. Allied Corp.
66 B.R. 582 (D. Kansas, 1986)
Saunders v. Callaway
708 P.2d 652 (Court of Appeals of Washington, 1985)
Feider v. Feider
699 P.2d 801 (Court of Appeals of Washington, 1985)
Wilson v. Whinery
678 P.2d 354 (Court of Appeals of Washington, 1984)
Matson v. Emory
676 P.2d 1029 (Court of Appeals of Washington, 1984)
Franklin County Sheriff's Office v. Sellers
646 P.2d 113 (Washington Supreme Court, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
441 P.2d 128, 73 Wash. 2d 849, 1968 Wash. LEXIS 703, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bennett-veneer-factors-inc-v-brewer-wash-1968.