Benham Construction Co. v. Rentz

238 P.2d 927, 69 Wyo. 176, 1951 Wyo. LEXIS 10
CourtWyoming Supreme Court
DecidedDecember 11, 1951
Docket2497
StatusPublished
Cited by8 cases

This text of 238 P.2d 927 (Benham Construction Co. v. Rentz) is published on Counsel Stack Legal Research, covering Wyoming Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Benham Construction Co. v. Rentz, 238 P.2d 927, 69 Wyo. 176, 1951 Wyo. LEXIS 10 (Wyo. 1951).

Opinion

*180 OPINION

Per Curiam

This action arose in consequence of a disagreement between the original contractor and a subcontractor concerning the proper performance of that portion of an original construction contract sublet by the former to the latter. The original contractor, Benham Construction Company, a corporation, plaintiff below and hereinafter usually so designated, or as the “Company” or “appellant” brought the action in the district court of Laramie County, Wyoming, against the subcontractor, C. A. Rentz, hereinafter conveniently referred to as either the defendant, the respondent or by his surname, Rentz. The pleadings of the parties disclose with reasonable clarity their respective claims and the issues made up which the court tried without a jury.

Plaintiff’s petition alleged in substance: Paragraph I that it is a corporation duly functioning under the laws of the State of Wyoming.

In paragraph II that during the year 1949 plaintiff agreed to construct a gymnasium and classrooms for School District No. 6 in Carbon County, Wyoming, in accord with certain plans and specifications.

In paragraph III that in May 1949 responding to a request therefor made by the Company for bids for supplying certain plaster work and material in connection with the project above mentioned the defendant submitted a bid reading:

*181 “C. A. RENTZ
PLASTER AND STUCCO CONTRACTOR
819 West 10th Street
Phone 7622
Cheyenne, Wyo.
May 19, 1949
Benham Construction Co.
1015 E. Lincolnway
Bid — School
Medicine Bow, Wyoming
This bid includes plastering labor only and material except sand and vermicalite. Two (2) ceilings, one each in locker rooms. The rest side walls only to be plastered. Stage and two (2) small halls off stage not to be plastered. Girls and boys locker rooms to be cement plaster of sand finish. Other plaster to be lime sand finish, except for wainscoat five (5) foot to be cement smooth.
$2,450.00”

That it was then orally agreed between the parties that if and when the defendant should complete said work and furnish said materials in a good and workmanlike manner the Company would pay Rentz the sum of $2,450 therefor; that it was also agreed that the plaintiff would furnish necessary sand and vermicalite and coloring material and the defendant would supply all other labor and materials necessary to complete the work properly.

In paragraph IV it is averred that the defendant commenced and carried on the work aforesaid and represented to the plaintiff that he required money to go on with his operations and in continuance of the work; that the Company relying upon defendant’s performance, that he was performing and would perform the work as agreed did, on June 25th, 1949, advance to the said defendant $1,500.

Paragraph V states that plaintiff has performed all *182 the conditions of the agreement to be performed by him.

Paragraph VI of plaintiff’s petition charged that the defendant:

“The defendant failed to comply with his agreement to plaintiff’s damage in the following particulars, in that (1) his work and labor were so unskillful and incompetent and (2) the materials furnished by the defendant were (a) so unsatisfactory and (b) so improperly applied that the plaster walls cracked badly and the plaster crumbled and loosened from the base, and (3) the surfaces of the walls were not lined properly and had an unreasonably uneven and rolling surface, all to such an extent and degree that said work and materials were and are of no value whatever to plaintiff or to said School District No. 6.” (Italics supplied.)

that as a result of these failures on the defendant’s part in performing as agreed, plaintiff was obliged to employ other persons to tear out the work done and materials furnished by defendant and replace same with proper work ánd materials and “to correct the errors made in many cases”; that plaintiff was delayed in completing the job and obtaining payment therefor, being damaged in the sum of $600 for this and in the sum of $1,500 advanced to defendant. Judgment was asked against the defendant in the sum of $2,000 and costs.

To this pleading the defendant filed his answer and cross-petition; the answer admits the allegations of paragraphs Nos. I and III of plaintiff’s petition; admits that during 1949 plaintiff agreed to construct a gymnasium and classrooms for School District No. 6 in Carbon County, Wyoming, and that defendant commenced the work by him to be performed as described in plaintiff’s petition and the payment to him by plaintiff on June 25, 1949, of $1,500 on representation by him that he required such sum of money to carry on his operations.

*183 As to paragraph No. V of plaintiff’s pleading the allegations thereof are denied.

Defendant denies that he failed to comply with his agreement to plaintiff’s damage in the particulars alleged ; also that the work done and materials 'furnished by the defendant were and are of no value to plaintiff or to the said School District No. 6; he denies that as the alleged result of defendant’s failure to perform it was necessary for plaintiff to employ others to tear out the work done and materials furnished by defendant and replace them with proper work and materials and to correct errors. The defendant denies that in consequence of any alleged failure on his part to comply with his agreement plaintiff was delayed in completing the job and obtaining payment therefor as alleged and denies that by reason thereof plaintiff has been damaged in the amount of $500, the $1,500 advance to defendant or in any other sum. He denies each and every allegation in plaintiff’s pleading “not hereinbefore specifically admitted or denied.”

Defendant’s cross-petition in its paragraph No. 1 stated that at all times material herein plaintiff was a corporation organized under Wyoming law. In its paragraph 2 it is averred that:

“That there is due and owing defendant from and by the plaintiff on account the sum of $950.00, together with interest thereon at the rate of seven per cent per annum from and after July 28, 1949; that a copy of the account with all credits and endorsements thereon is hereto attached, marked defendant’s exhibit ‘A’, and by reference is made a part hereof.”

Exhibit “A” mentioned in the foregoing paragraph is as follows:

*184 “C. A. RENTZ
PLASTER AND STUCCO CONTRACTOR
819 West 10th Street
Phone 7622

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Seaton v. State Highway Commission, District No. 1
784 P.2d 197 (Wyoming Supreme Court, 1989)
Nimmo v. State
603 P.2d 386 (Wyoming Supreme Court, 1979)
First National Bank of Thermopolis v. Bonham
559 P.2d 42 (Wyoming Supreme Court, 1977)
DeBaca v. State
404 P.2d 738 (Wyoming Supreme Court, 1965)
Hawkey v. Williams
281 P.2d 447 (Wyoming Supreme Court, 1955)

Cite This Page — Counsel Stack

Bluebook (online)
238 P.2d 927, 69 Wyo. 176, 1951 Wyo. LEXIS 10, Counsel Stack Legal Research, https://law.counselstack.com/opinion/benham-construction-co-v-rentz-wyo-1951.