Benes v. Hickox Building Co.

112 N.E.2d 553, 64 Ohio Law. Abs. 449, 1952 Ohio App. LEXIS 814
CourtOhio Court of Appeals
DecidedOctober 20, 1952
DocketNo. 22088
StatusPublished
Cited by2 cases

This text of 112 N.E.2d 553 (Benes v. Hickox Building Co.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Benes v. Hickox Building Co., 112 N.E.2d 553, 64 Ohio Law. Abs. 449, 1952 Ohio App. LEXIS 814 (Ohio Ct. App. 1952).

Opinion

[450]*450OPINION

By METCALF, J:

Plaintiff, a building contractor, brought suit against the defendant for loss of profits claimed to have been occasioned by the defendant’s alleged wrongful repudiation of a building contract.

The defendant is the owner of premises located at the corner of Euclid Avenue and East 9th Street in the City of Cleveland upon which formerly was located the Hiekox Building. On March 22, 1946, and while the Hiekox Building was being razed to permit the construction of a commercial building especially adapted for the use and occupancy of Bond Stores, Inc., hereinafter referred to as “Bond” as lessee of the defendant under a long term lease, the parties to this action entered into a written contract for the construction of the building in question. The contract between the parties hereto provides in Article I:

“Section 1, Scope of the Work. The Contractor shall furnish all necessary labor and materials required to perform and shall perform all the work shown on the drawings entitled ‘Building for Bond Stores, Inc., Euclid Avenue and East 9th Street, Cleveland Ohio,’ (except such portions of the work of this Contract by the provisions of Section 1 of Article I hereof) as prepared by Walker & Weeks, Architects, hereinafter called the ‘Architects,’ whose address is 1240 Huron Road, Cleveland, Ohio.

“In general the work covered by this Contract contemplates a complete building, ready for use by Bond Stores Inc., hereinafter called ‘Bond’ as lessee of the Owner under a certain Indenture of Lease dated as of June 1, 1944 and hereinafter called the ‘Lease,’ but in no event shall the work covered by this Contract include the following terms:

“(a) The demolition of the existing structure known as the Hiekox Building.

“(b) The furnishing of the structural steel; and

“(c) The furnishing and installation of the store fixtures and equipment;

“and the Owner reserves the right to obtain proposals on the following items (which are not at the date of this Contract included in the work covered hereby);

[451]*451“(1) Plumbing work;

“(2) Heating and air-conditioning work;

“(3) Electrical work;

“(4) Elevators (2) and sidewalk lift;

“(5) Pneumatic tube system; and

“(6) Sprinkler system;”

The defendant reserved the right to include any or all of these excepted items within the scope of the work to be performed by the contractor.

Article n of the Contract provides for the commencement of the work and the time of its completion as follows:

“The Contractor shall commence work on the foundations at once and shall proceed with the same as rapidly as permitted by the Progress of the work of demolition of the Hickox Building.

“The Contractor shall commence the balance of the work covered by this Contract forthwith upon the approval of this Contract by Bond and the deposit with the Disbursing Agent, in accordance with the provisions of Section 3 of Article I of the aforesaid Lease, of the cost of the New Building.

“All work covered by this Contract shall be completed by the Contractor within One Hundred (100) working days after the first delivery by the Owner to the Contractor of structural steel; * * *”

Article III of the contract provides for the contract sum to be paid to the contractor as follows:

“Section 1. The Owner shall pay the Contractor for the performance of this Contract, in current funds, as follows:

“(a) The cost of the work performed by the Contractor hereunder as such cost is defined and restricted by the provisions hereinafter contained in Section 2 of this Article III; and

“(b) The Contractor’s fee which shall be Twenty Five Thousand Dollars ($25,000.00) plus an amount equivalent to Five Percent (5%) of the cost as defined and restricted in Section 2 of this Article III, of such Item (1) to (6) inclusive, as set forth in Section 1 of Article I hereof, as the Owner, m accordance with the provisions of said Section, causes to be included in the work covered by this Contract; provided, however, in no event shall such additional fee of the Contractor exceed Ten Thousand Dollars ($10,000.00), and provided further, anything in this Contract to the contrary notwithstanding, if this Contract is not approved by Bond, then the Contractor’s fee shall not exceed Five Percent (5%) of the cost as defined and restricted in Section 2 of this Article of the work performed by the Contractor hereunder.”

[452]*452Section 2 of this Article sets forth the items that shall be included “For the purposes of determining the cost of the work performed by the Contractor. hereunder.”

The above are the pertinent parts of the contract involved in this litigation. At the end of the written instrument and following the signatures of the parties thereto there is a form to be signed by Bond approving the contract, which approval was not given.

Pursuant to the first paragraph of Article II the contractor did some work on the foundation and was paid therefor under the terms of the contract. Bond not having approved the contract the defendant refused to permit the plaintiff to commence the balance of the work of constructing the building. Subsequently a contract was let .to a third party who constructed the building. This action is brought by the plaintiff under his claim that the defendant refused to permit him to carry out his obligations under the .contract, claiming damages in the sum of $45,000.00, which he alleges to be the fair value of his profit, benefits and rights under the contract. It is defendant’s contention that unless and until the contract had the approval of Bond the plaintiff had no right under the contract to commence the construction of the building.

The case was tried to the Common Pleas Court of Cuyahoga Cbunty, without the intervention of a jury, and the court found in favor of the defendant, from which judgment this appeal stands on questions of law.

There are ten separate assignments of error; and while we have examined the record with all of them in view, perhaps the sixth covers the position of plaintiff more clearly. It reads:

“The trial court erred in admitting under the guise of surrounding circumstances, parol evidence and in using said evidence to off-set an intention expressed in the written contract.”

The question, the answer to which is dispositive of this appeal, is whether the approval of Bond of the building contract is essential to its enforcement as between the parties to this action?

In order to determine the importance or unimportance of the approval of the construction contract by Bond, it seems to this court that the Lease given by the defendant to Bond becomes most important. This Lease is referred to in the contract under consideration. The commencement of the construction work was to begin forthwith “upon the approval of this contract by Bond and the deposit with the Disbursing [453]*453Agent in accordance with the provisions of Section 3 of Article I of the aforesaid Lease, of the cost of the New Building.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Malcuit v. Equity Oil & Gas Funds, Inc.
610 N.E.2d 1044 (Ohio Court of Appeals, 1992)
Juengel Const. Co., Inc. v. Mt. Etna, Inc.
622 S.W.2d 510 (Missouri Court of Appeals, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
112 N.E.2d 553, 64 Ohio Law. Abs. 449, 1952 Ohio App. LEXIS 814, Counsel Stack Legal Research, https://law.counselstack.com/opinion/benes-v-hickox-building-co-ohioctapp-1952.