Benderson Development Co. v. Schwab Bros. Trucking, Inc.

64 A.D.2d 447, 409 N.Y.S.2d 890, 1978 N.Y. App. Div. LEXIS 12747
CourtAppellate Division of the Supreme Court of the State of New York
DecidedNovember 10, 1978
StatusPublished
Cited by31 cases

This text of 64 A.D.2d 447 (Benderson Development Co. v. Schwab Bros. Trucking, Inc.) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Benderson Development Co. v. Schwab Bros. Trucking, Inc., 64 A.D.2d 447, 409 N.Y.S.2d 890, 1978 N.Y. App. Div. LEXIS 12747 (N.Y. Ct. App. 1978).

Opinion

OPINION OF COURT

Dillon, J.

Defendant Glens Falls Insurance Company (Glens Falls) appeals from a monetary judgment in favor of plaintiff Benderson Development Company, Inc. (Benderson) following a nonjury trial. The action arises out of two agreements, one dated October 16, 1964, and another nearly identical agreement dated December 4, 1964, between Benderson and Glens Falls. Both agreements were made in connection with a series of short-term loans made to Schwab Bros. Trucking, Inc. (Schwab Bros.) by Benderson.

Schwab Bros, was the successful bidder on a public improvement project to build a section of the Kensington Expressway in the City of Buffalo. Glens Falls issued performance and [450]*450materialmen’s bonds guaranteeing to the State of New York faithful performance of the contract by Schwab Bros., as well as the payment of subcontractors’, laborers’ and material-men’s claims under the contract. As security for the bonds, Glens Falls took from Schwab Bros, an assignment for all moneys due or to become due under the Kensington Expressway contract.

Prior to obtaining the award of the Kensington Expressway project, Schwab Bros, began work on other public improvement contracts both in the State of New York and in the State of Michigan. Glens Falls had also provided performance and materialmen’s bonds to the public entities on those projects. As it became apparent that Schwab Bros, was unable to finance this expanding series of public improvements, Philip Schwab, the principal in Schwab Bros., with the assistance of David D. Baker (Baker), the agent and manager of the Glens Falls Buffalo branch, obtained a series of short-term loans to cover the costs of continuing work on the projects. To secure these loans, Schwab Bros, assigned to the lenders the progress payments, earned or to be earned, under the respective public improvement contracts. However, since Schwab Bros, had previously assigned the same progress payments to Glens Falls in connection with the surety bonds for the same projects, agreements were entered into between Glens Falls and the lenders, giving the lenders first rights to any progress payments made under the contracts. One such agreement was executed by Schwab Bros., Benderson and Glens Falls on October 16, 1964 in relation to the Kensington Expressway contract. In pertinent part, the agreement reads as follows:

"whereas, Surety has obligated and bound itself upon the following bonds, to wit:
"(a) Performance bond No. 97-16-87 in the amount of Two Million Seven Hundred Thirty-One Thousand Eight Hundred Thirty Dollars ($2,731,830.00) guaranteeing unto the State of New York (hereinafter called 'Owner’), the faithful performance by Schwab bros. trucking, inc. (hereinafter called 'Contractor’) [on the Kensington Expressway contract] and * * *
"(b) Bond No. 97-16-87 in the amount of Two Million Seven Hundred Thirty-One Thousand Eight Hundred Thirty Dollars ($2,731,830.00) guaranteeing unto Owner the payment of Subcontractor’s, laborer’s and materialmen’s claims upon and under the aforesaid contracts; and
"whereas, under and by virtue of said bond, Surety has [451]*451been granted an assignment of certain proceeds, monies, accounts and contract rights due or to become due from Owner to Contractor; and
"whereas, Lender has and will advance funds to Contractor to defray the costs of performing said contracts with Owner; and
"whereas, Lender has received from Contractor, as security, an assignment of all proceeds, monies, accounts and contract rights, due or to become due, from Owner to Contractor; and
"whereas, Lender and Surety wish to clarify their respective rights to the proceeds, monies, accounts, and contract rights, due or to become due, to Contractor from Owner and assigned to each of them as security, and also wish to secure the Lender from and out of all funds howsoever arising under the said contract;
"now, therefore, for good and valuable consideration, the receipt and adequacy of which are acknowledged by each of the parties hereto, the parties agree as follows:
"1. Lender shall have the first and prior right to all proceeds, monies, accounts and contract rights earned or to be earned by Contractor or by the Surety by reason of work done by either of them under the aforesaid contracts, including the right to progress payments, retained percentages, funds earned but retained by the Owner, and funds unearned and retained by the Owner until performance by the Contractor and/or Surety.
"2. Surety hereby waives, subordinates, subrogates and assigns to the Lender any and all liens, security interests and rights in and to any proceeds, monies, accounts and contract rights, due or to become due, to Contractor and/or Surety from Owner, to the extent necessary for Lender to obtain a first and prior lien and security interest therein and thereto, superior to Surety, whether Surety’s rights and interests arise by virtue of the assignment to Surety under the aforesaid bonds, or by virtue of work done under the contracts or bond by the Surety, or by virtue of its right to subrogation, if any.
"3. It is specifically understood between the parties hereto that any funds and amounts earned by Contractor and/or Surety shall be paid to or used for the benefit of Lender as security for amounts loaned to Contractor (including all interest and charges thereon) and Surety shall execute any and all instruments necessary to effectuate the foregoing.”

[452]*452Attached to the agreement was a power of attorney issued to Baker by Glens Falls.

Benderson ultimately advanced one million dollars to Schwab Bros, under this agreement. Schwab Bros., by Philip Schwab, gave Benderson a demand note for the full sum. In addition, Philip Schwab and his wife Mary Louise Schwab executed a separate instrument in which they personally guaranteed payment of the loan.

A similar loan transaction was arranged with respect to public improvement contracts in Pahokee and Belle Glade, Florida, on which Schwab Bros, was the successful bidder and Glens Falls was the surety. Schwab Bros, made assignments of progress payments under these , public improvement contracts to . both Glens Falls and Benderson, and on December 4, 1964 Glens Falls and Benderson executed an agreement concerning the Florida projects which is indistinguishable in terminology from the agreement of October 16, 1964. Shortly thereafter Benderson advanced Schwab Bros. $50,000 on the Florida contracts.

In February, 1965 Schwab Bros, defaulted on the Kensington Expressway and Florida projects. Glens Falls elected not to perform for Schwab Bros, on the Kensington Expressway job although demands to do so were made by Benderson and the State of New York. Additionally, on February 20, 1965 C. Irving Bush, Glens Falls’ vice-president, wrote a letter to Benderson in which he asserted that Baker lacked authority to execute the agreements with Benderson on behalf of Glens Falls.

Benderson alleges that during the course of discussions preceding the execution of the assignments by Schwab Bros, and the agreements with Glens Falls, numerous representations were made by Baker to the effect that the surety, Glens Falls, was guaranteeing repayment of the loans.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Iskalo Elec. Tower LLC v. Stantec Consulting Servs., Inc.
219 A.D.3d 1157 (Appellate Division of the Supreme Court of New York, 2023)
PASQUARELLA, ROGER v. 1525 WILLIAM STREET, LLC
120 A.D.3d 982 (Appellate Division of the Supreme Court of New York, 2014)
Borrelli v. Chamberlain
21 A.D.3d 1382 (Appellate Division of the Supreme Court of New York, 2005)
ESL Federal Credit Union v. Bovee
9 Misc. 3d 256 (New York Supreme Court, 2005)
Cusano v. Klein
280 F. Supp. 2d 1035 (C.D. California, 2003)
Pepsico, Inc. v. Central Inv. Corp., Inc.
271 F. Supp. 2d 1040 (S.D. Ohio, 2001)
Benderson v. Wiper Check Inc.
266 A.D.2d 903 (Appellate Division of the Supreme Court of New York, 1999)
L & B 57th Street, Inc. v. E.M. Blanchard, Inc.
143 F.3d 88 (Second Circuit, 1998)
Street, Inc. v. Blanchard, Inc.
143 F.3d 88 (Second Circuit, 1998)
Alizio v. Perpignano
245 A.D.2d 477 (Appellate Division of the Supreme Court of New York, 1997)
Tigue v. Commercial Life Insurance
219 A.D.2d 820 (Appellate Division of the Supreme Court of New York, 1995)
Kula v. State Farm Fire & Casualty Co.
212 A.D.2d 16 (Appellate Division of the Supreme Court of New York, 1995)
Port Distributing Corp. v. Pflaumer
880 F. Supp. 204 (S.D. New York, 1995)
Intercontinental Credit Corp. v. Roth
184 A.D.2d 251 (Appellate Division of the Supreme Court of New York, 1992)
Menorah Nursing Home, Inc. v. Zukov
153 A.D.2d 13 (Appellate Division of the Supreme Court of New York, 1989)
Pantone, Inc. v. Esselte Letraset Ltd.
691 F. Supp. 768 (S.D. New York, 1988)
Lowy v. Bay Terrace Cooperative, Section VIII, Inc.
698 F. Supp. 1058 (E.D. New York, 1988)
Niagara Mohawk Power Corp. v. Groves
134 A.D.2d 822 (Appellate Division of the Supreme Court of New York, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
64 A.D.2d 447, 409 N.Y.S.2d 890, 1978 N.Y. App. Div. LEXIS 12747, Counsel Stack Legal Research, https://law.counselstack.com/opinion/benderson-development-co-v-schwab-bros-trucking-inc-nyappdiv-1978.