Bellsouth Telecommunications, Inc. v. Johnson Brothers Corporation of Louisiana

106 F.3d 119, 1997 U.S. App. LEXIS 6497, 1997 WL 52182
CourtCourt of Appeals for the Fifth Circuit
DecidedApril 1, 1997
Docket96-30062
StatusPublished
Cited by17 cases

This text of 106 F.3d 119 (Bellsouth Telecommunications, Inc. v. Johnson Brothers Corporation of Louisiana) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bellsouth Telecommunications, Inc. v. Johnson Brothers Corporation of Louisiana, 106 F.3d 119, 1997 U.S. App. LEXIS 6497, 1997 WL 52182 (5th Cir. 1997).

Opinions

PER CURIAM:

Plaintiff-Appellee filed suit against Defendants-Appellants to recover for damage to two buried telephone cables which occurred during excavations conducted pursuant to a contract with the State of Louisiana Department of Transportation and Development. The district court granted summary judgment on the question of liability and subsequently did not permit submission of the question of comparative fault to the jury. Following a jury trial on the question of damages, a monetary judgment was entered in favor of plaintiff. Defendants appealed,

¿ BACKGROUND

On August 11,1994, BellSouth Telecommunications, Inc. (“BellSouth”) filed suit against Johnson Brothers Corporation of Louisiana, Ohbayashi Corporation, Johnson Brothers Corporation and Ohbayashi Corporation (A Joint Venture) (hereafter collectively, “Johnson Brothers”) for damage to BellSouth’s underground conduit and cables. The damage occurred on August 13, 1993, during an excavation which Johnson Brothers was performing pursuant to a contract with the State of Louisiana Department of Transportation and Development (“DOTD”) for work on the Greater New Orleans Bridge Project No. 2.

In its Answer filed on October 4, 1994, Johnson Brothers admitted that it had not complied with Louisiana’s Underground Utilities and Facilities Damage Prevention Law (“Damage Prevention Law” or “the Act”), La.Rev.Stat.Ann. §§ 40:1749.11, et seq., but disputed that this violation provided the basis for recovery by BellSouth. Johnson Brothers also averred comparative fault on the part of BellSouth for its failure to provide accurate and reliable information with respect to the location of its cables.

Following initial discovery, BellSouth filed a motion for summary judgment contending that Johnson Brothers’ failure to comply with the Damage Prevention Law made it liable to BellSouth for the damages incurred. In opposition, Johnson Brothers argued that Bell-South was precluded from recovery by its own negligence in submitting to the DOTD erroneous plats upon which Johnson Brothers relied in performing the excavation.2

On May 25,1995, the district court granted summary judgment in favor of BellSouth on the question of liability. BellSouth then filed a motion for reconsideration or, in the alternative, motion in limine seeking clarification [122]*122of the court’s ruling. Specifically, BellSouth sought clarification as to whether Johnson Brothers’ defense of comparative negligence remained viable. On June 27, 1995, treating BellSouth’s motion as one in limine, the district court granted the motion and clarified that BellSouth’s previous provision of erroneous plats to the DOTD under La.Rev. Stat.Ann. § 38:2223 could not form the basis for comparative fault.

Johnson Brothers then filed a motion for reconsideration and/or for leave to present evidence of BellSouth’s comparative fault.3 BellSouth filed a motion for summary judgment on the quantum of damages to which it was entitled. On October 11, 1995, the district court denied BellSouth’s motion, concluding that there were genuine issues of material fact which precluded summary judgment on damages. It also denied Johnson Brothers’ motion, making clear that it had already found that § 38:2223 could not serve as a basis for comparative fault under the Damage Prevention Law.

Following trial to a jury on the question of damages, a judgment in the amount of $54,-092.18 was entered in favor of BellSouth.

Johnson Brothers appealed from the various rulings of the district court and from the final judgment, raising essentially two issues on appeal: (1) whether the district court erred by refusing to allow Johnson Brothers to submit evidence to the jury on the issue of BellSouth’s comparative fault; and (2) whether the district court improperly instructed the jury on the issue of damages.

II. DISCUSSION

A. The District Court’s Ruling on Summary Judgment, as Clarified by Subsequent Rulings

We review grants of summary judgment de novo, guided by the standards of Federal Rule of Civil Procedure 56, which provides that summary judgment is appropriate “if the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to judgment as a matter of law.” Fed.R.Civ.P. 56(c).

In this case, the material facts are undisputed: (1) Johnson Brothers damaged Bell-South’s cables; (2) BellSouth’s Utility Plat No. F2 purporting to show the location of the cables was erroneous; (3) Johnson Brothers relied on Utility Plat No. F2 as it proceeded with the excavation on August 13, 1993; and (4) Johnson Brothers did not comply with Louisiana’s Damage Prevention Law.

The question which the district court had to resolve was a question of law, specifically: whether Johnson Brothers’ violation of the Damage Prevention Law precluded introduction of evidence of comparative fault on the part of BellSouth.

“It is well-established that this court reviews de novo questions of law raised in summary judgment appeals. See Eugene v. Alief Indep. Sch. Dist., 65 F.3d 1299, 1303 (5th Cir.1995). More specifically, we review a district court’s interpretation of a state statute de novo. See Transcontinental Gas Pipe Line Corp. v. Transportation Ins. Co., 953 F.2d 985, 987 (5th Cir.1992).” Occidental Chemical v. Elliott Turbomachinery Co., 84 F.3d 172, 175 (5th Cir.1996).

Thus, on review, this court must determine whether the district court correctly construed the Damage Prevention Law to preclude Johnson Brothers’ comparative negligence claim. Louisiana’s Damage Prevention Law provides, in pertinent part:

A. ... [N]o person shall excavate or demolish ... near the location of an un[123]*123derground facility or utility, ... without having first ascertained in the manner prescribed in Subsection B of this Section, the approximate location of all underground facilities or utilities in the area which would be affected by the proposed excavation or demolition.
B. (1) Except as provided in R.S. 40:1749.15 [emergency excavation], prior to any excavation or demolition, each excavator ... shall serve telephonic notice of the intent to excavate or demolish to the regional notification center serving the area in which the proposed excavation or demolition is to take place. Such notice shall be given to the notification center at least forty-eight hours, but not more than one hundred twenty hours, excluding weekends and holidays, in advance of the excavation or demolition activity....

La.Rev.Stat.Ann.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
106 F.3d 119, 1997 U.S. App. LEXIS 6497, 1997 WL 52182, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bellsouth-telecommunications-inc-v-johnson-brothers-corporation-of-ca5-1997.