BellSouth Mobility, Inc. v. Parish of Plaquemines

40 F. Supp. 2d 372, 1999 U.S. Dist. LEXIS 9593, 1999 WL 144277
CourtDistrict Court, E.D. Louisiana
DecidedMarch 11, 1999
DocketCiv.A. 98-1754
StatusPublished
Cited by4 cases

This text of 40 F. Supp. 2d 372 (BellSouth Mobility, Inc. v. Parish of Plaquemines) is published on Counsel Stack Legal Research, covering District Court, E.D. Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
BellSouth Mobility, Inc. v. Parish of Plaquemines, 40 F. Supp. 2d 372, 1999 U.S. Dist. LEXIS 9593, 1999 WL 144277 (E.D. La. 1999).

Opinion

ORDER AND REASONS

FELDMAN, District Judge.

Before the Court are cross-motions for Summary Judgment. 1 Plaintiff BellSouth *375 Mobility brings a challenge under the Telecommunications Act of 1996 to the decision by defendant Council of the Parish of Plaquemines denying BellSouth’s zoning requests for building two cellular phone towers. For the reasons that follow, Bell-South’s Motion is DENIED and the defendants’ and intervenors’ Motions are GRANTED.

Background

BellSouth Mobility is licensed by the Federal Communications Commission to administer cellular telecommunications in Plaquemines Parish. Reliable service there requires five cellular transmission towers. This suit arises out of BellSouth’s efforts to obtain permission to construct two towers on separate parcels of property in the Parish at Jesuit Bend and Nairn; there is no dispute concerning the other three towers. The tower proposed for Jesuit Bend was to be 220 feet tall and self-supporting; the one at Nairn would be 340 feet tall, supported with guy wires. Intervenors Bonnie Kinnard and Bruce Gasquet live on property adjacent to the proposed sites.

BellSouth initially applied for construction permits in December 1997. In the past, the Parish Department of Permits approved other types of transmission towers after notice to adjoining property owners, but without public hearing. Yet, faced with increases in permit applications resulting from the burgeoning cellular communications industry, the Parish Attorney and Parish Zoning Consultant reevaluated this process. They concluded that cellular towers, like radio and television broadcasting towers, were “conditional uses,” not “permitted uses.” Thus, construction requires a grant of conditional use after a public hearing process under the Comprehensive Zoning Ordinance for Plaquemines Parish.

Despite recognizing that a public hearing was required, the Parish Attorney advised the Council that the old procedure should be used in conformity with historical practice. Hence, following notice to adjoining property owners, the Council approved BellSouth’s permit applications in early 1998.

In March 1998, the Gasquets sought in-junctive relief in state court. The trial court denied relief. While finding that the Council did not follow its own regulations requiring a public hearing, the trial judge concluded that he did not have the authority to issue a preliminary injunction. The judge noted, however, that the same record would support the grant of a permanent injunction if properly presented in such a proceeding.

Later that month, the Council revoked BellSouth’s permits in response to the ruling. BellSouth also filed applications for conditional use permits. After public hearing, the Plaquemines Parish Development Board voted not to recommend approval to the Council. The Board did not provide written reasons for its decision.

In May 1998, at the conclusion of another public hearing, the Council denied Bell-South’s permit requests as evidenced by two Council Resolutions (Numbers 98-357, 358). BellSouth received written letters of notification in July 1998. The Council did not provide written reasons for the denial beyond the letters and transcripts of proceedings, as well as the documentary record including citizen complaints, petitions, a real estate appraisal, and photographs and other drawings.

*376 Following the Council’s denial, Bell-South sued the Parish, the Council, and Edward Theriot, both individually and in his capacity as Council President, under the Telecommunications Act of 1996, 47 U.S.C. § 332. BellSouth also sought relief under 42 U.S.C. §§ 1983, 1988. It moves for partial summary judgment on the Telecommunications Act claim. Defendants and intervenors seek summary judgment on all claims. 2

Law and Application

I.Summary Judgment Standard

Federal Rule of Civil Procedure 56 instructs that summary judgment is proper if the record discloses no genuine issue as to any material fact and that the moving party is entitled to judgment as a matter of law. No genuine issue of fact exists if the record, taken as a whole, could not lead a rational trier of fact to find for the nonmoving party. See Matsushita Elec. Indus. Co. v. Zenith Radio Corp., 475 U.S. 574, 586, 106 S.Ct. 1348, 89 L.Ed.2d 538 (1986). A genuine issue of fact exists only “if the evidence is such that a reasonable jury could return a verdict for the nonmov-ing party.” Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248, 106 S.Ct. 2505, 91 L.Ed.2d 202 (1986). The mere argued existence of a factual dispute does not defeat an otherwise properly supported motion. See id. Therefore, “[i]f the evidence is merely colorable, or is not significantly probative,” summary judgment is appropriate. Id. at 249-50, 106 S.Ct. 2505 (citations omitted).

In addition, if the party opposing the motion fails to establish an essential element of his case, summary judgment is proper. See Celotex Corp. v. Catrett, 477 U.S. 317, 322-23, 106 S.Ct. 2548, 91 L.Ed.2d 265 (1986). In evaluating the summary judgement motion, a court must read the facts in the light most favorable to the non-moving party. Anderson, 477 U.S. at 255, 106 S.Ct. 2505.

II.Personal Capacity Suit

The denial of a request for rezoning of a specific parcel of property is a legislative act. Calhoun v. St. Bernard Parish, 937 F.2d 172, 174 (5th Cir.1991); see also Arlington Heights v. Metropolitan Housing Corp., 429 U.S. 252, 97 S.Ct. 555, 50 L.Ed.2d 450 (1977). As such, members of the Parish Council involved in the zoning decision are entitled to absolute legislative immunity from personal capacity suits. Calhoun, 937 F.2d at 174. This holds true regardless of BellSouth’s allegations of discriminatory intent. Id. Thus, the personal capacity claims against Edward Theriot, the Council’s president, are dismissed.

III.Telecommunications Act of 1996 A. Standards

Congress passed the Telecommunications Act of 1996 to overhaul federal regulation of communication companies.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

BellSouth Mobility v. Miami-Dade County, Florida
153 F. Supp. 2d 1345 (S.D. Florida, 2001)
Vertical Broadcasting, Inc. v. Town of Southampton
84 F. Supp. 2d 379 (E.D. New York, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
40 F. Supp. 2d 372, 1999 U.S. Dist. LEXIS 9593, 1999 WL 144277, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bellsouth-mobility-inc-v-parish-of-plaquemines-laed-1999.