BECO Construction Co. v. J-U-B Engineers, Inc.

184 P.3d 844, 145 Idaho 719, 2008 Ida. LEXIS 84
CourtIdaho Supreme Court
DecidedMay 2, 2008
Docket33378
StatusPublished
Cited by30 cases

This text of 184 P.3d 844 (BECO Construction Co. v. J-U-B Engineers, Inc.) is published on Counsel Stack Legal Research, covering Idaho Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
BECO Construction Co. v. J-U-B Engineers, Inc., 184 P.3d 844, 145 Idaho 719, 2008 Ida. LEXIS 84 (Idaho 2008).

Opinion

J. JONES, Justice.

BECO Construction filed suit against JU-B Engineers, claiming that J-U-B had delayed BECO’s work on a construction project, thereby subjecting it to liability for liquidated damages. The district court dismissed BECO’s complaint on summary judgment and awarded attorney fees to JU-B. BECO appeals the dismissal of its claim that J-U-B intentionally interfered with its construction contract, as weE as the fee award. We affirm the grant of summary judgment but vacate a portion of the fee award.

*722 I.

In November 2003, the Pocatello Development Authority hired J-U-B Engineers, Inc., to serve as the qualified design professional on a development project in downtown Pocatello. In June 2004, the City of Pocatello awarded a Construction Contract to BECO Construction Company, Inc., to serve as the general contractor for the first phase of the project, which consisted of “reconstructing the pavement, sidewalk, installing street lights, installing storm sewer, installing waterlines, grading and landscaping.” In this contract, BECO and the City agreed that the project would be substantially completed within 90 days of commencement and totally completed within 20 days thereafter. The Construction Contract provided for liquidated damages in the event of BECO’s failure to complete the project within this time-frame.

The Construction Contract provided that J-U-B, as the engineer, would act as the City’s representative, and specifically delineated J-U-B’s role throughout the project. In general, J-U-B’s role included visiting the construction site, observing the work performed, and reporting back to the City on the progress and quality of BECO’s work on the project. In addition, the contract authorized J-U-B to make recommendations to the City as to whether to allow certain changes in the progress and methods of the work performed. It expressly allowed J-U-B to perform testing and inspections at its discretion to determine the quality of the work performed. Finally, the contract specified that J-U-B would review and approve final payment upon completion of the project. In essence, J-U-B acted as the City’s representative throughout the project.

BECO commenced its initial work on June 9, 2004, with full production proceeding on June 14, 2004. When BECO requested final payment, J-U-B informed the City that BECO had not completed its work, and recommended the City not make final payment. BECO filed a complaint against the City and J-U-B as codefendants, claiming breach of contract with regard to both defendants, negligence with regard to both defendants, and intentional interference with contract with regard to J-U-B. The latter claim alleged that J-U-B’s interference with its work significantly delayed BECO’s ability to make timely progress, which ultimately resulted in BECO incurring substantial liquidated damages. In June 2005, BECO and the City reached an agreement resolving the issues between them, which left only BECO’s claims against J-U-B.

J-U-B filed its first motion for summary judgment on July 27, 2005. BECO withdrew its breach of contract claim, and the district court granted summary judgment to J-U-B regarding its negligence claim. 1 However, the district court denied summary judgment on the issue of intentional interference with contract. J-U-B thereafter filed a second motion for summary judgment, contending further discovery proved BECO could not establish a genuine issue of material fact that would enable BECO to prevail on its intentional interference claim. This time, the district court granted summary judgment to JU-B. The court concluded that BECO failed to offer any admissible evidence to establish an issue of material fact as to whether J-UB interfered with BECO’s contract with the City.

BECO moved for reconsideration but the district court affirmed its prior grant of summary judgment to J-U-B. The district court also awarded attorney fees to J-U-B pursuant to I.C. § 12-120(3). BECO appealed the court’s grant of summary judgment on its intentional interference claim, as well as the fee award.

II.

In this case, we consider whether the district court erred when it granted summary judgment to J-U-B with regard to BECO’s intentional interference with a contract claim; whether the district court erred when it applied I.C § 12-120(3) to award attorney fees to J-U-B; and whether the district court abused its discretion by awarding J-U-B excessive attorney fees.

*723 A.

When a party appeals a district court’s grant of summary judgment, this Court applies the same standard the district court used when it ruled on the motion. Carnell v. Barker Mgmt., Inc., 137 Idaho 322, 326, 48 P.3d 651, 655 (2002). Summary judgment is proper “if the pleadings, depositions, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to judgment as a matter of law.” Idaho R. Civ. P. 56(c). We must construe all disputed facts in favor of the nonmoving party, and draw all reasonable inferences we can draw from the record in favor of the nonmoving party. Carnell, 137 Idaho at 327, 48 P.3d at 656. Summary judgment is appropriate where the nonmoving party bearing the burden of proof fails to make a showing sufficient to establish the existence of an element essential to the party’s case. Id.

B.

BECO alleges J-U-B’s actions throughout the construction project exceeded the scope of J-U-B’s responsibilities as the project engineer, interfered with BECO’s contract with the City, and caused costly delay in BECO’s ability to meet its contractual deadlines. BECO asserts its evidence regarding three disputed issues was sufficient to preclude summary judgment. First, BECO alleges JU-B interfered with the contract by improperly testing asphalt/aggregate compaction with the intent to promote failing tests. Second, it alleges J-U-B interfered by acting outside its contractual duties and unreasonably shutting down the project. Third, it alleges J-U-B interfered by unreasonably delaying commencement of the project. BECO claims questions of material fact exist on each of these issues. It also argues the district court improperly weighed conflicting evidence in reaching its decision in that it compared the affidavit of plaintiffs expert with that of defendant’s expert.

A prima facie case of tortious interference with contract exists where a plaintiff establishes the existence of a contract, knowledge of the contract on the part of the defendant, intentional interference causing breach of the contract, and injury to the plaintiff resulting from the breach. Barlow v. Int’l Harvester Co., 95 Idaho 881, 893, 522 P.2d 1102, 1114 (1974). J-U-B concedes the first two elements. The parties’ arguments on appeal focus primarily on the third element — whether J-U-B intentionally and improperly interfered with the contract between BECO and the City.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Streamline Builders, LLC v. Chase
Idaho Supreme Court, 2024
Papin v. Papin
454 P.3d 1092 (Idaho Supreme Court, 2019)
Francis Hospitality, Inc. v. Read Properties, LLC
820 S.E.2d 607 (Supreme Court of Virginia, 2018)
Skaskiw and Vermont Volunteer Services for Animals Humane Society
2014 VT 133 (Supreme Court of Vermont, 2014)
Madison Real Property v. Thomason
Idaho Court of Appeals, 2013
Ferrell v. United Financial Casualty Co.
305 P.3d 529 (Idaho Supreme Court, 2013)
Zoellner v. St. Luke's Regional Medical Center, Ltd.
937 F. Supp. 2d 1261 (D. Idaho, 2013)
Syringa Networks, LLC v. Idaho Department of Administration
305 P.3d 499 (Idaho Supreme Court, 2013)
Printcraft Press, Inc. v. Sunnyside Park Utilities, Inc.
283 P.3d 757 (Idaho Supreme Court, 2012)
Kayser v. McClary
875 F. Supp. 2d 1167 (D. Idaho, 2012)
Hopkins Northwest Fund, LLC v. Landscapes Unlimited, LLC
264 P.3d 379 (Idaho Supreme Court, 2011)
Taylor v. McNichols
243 P.3d 642 (Idaho Supreme Court, 2010)
Mortensen v. Stewart Title Guaranty Co.
235 P.3d 387 (Idaho Supreme Court, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
184 P.3d 844, 145 Idaho 719, 2008 Ida. LEXIS 84, Counsel Stack Legal Research, https://law.counselstack.com/opinion/beco-construction-co-v-j-u-b-engineers-inc-idaho-2008.