Becker v. Woarms

72 A.D. 196, 76 N.Y.S. 438
CourtAppellate Division of the Supreme Court of the State of New York
DecidedJuly 1, 1902
StatusPublished
Cited by4 cases

This text of 72 A.D. 196 (Becker v. Woarms) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Becker v. Woarms, 72 A.D. 196, 76 N.Y.S. 438 (N.Y. Ct. App. 1902).

Opinions

Ingraham, J.:

In this action the plaintiff seeks to recover from the defendants for the. damages sustained by breach of a contract. The complaint alleged that defendants entered into a written contract on -the 18th day of August, 1898, whereby they employed the plaintiff to manu[197]*197facture, construct and set up certain metal fittings and partitions, chiefly of bronze, according to certain specifications attached to said contract, and according to certain plans referred to therein, in the Albany Savings Bank, to be erected on the southwest corner of Pearl street and Maiden lane, Albany, N. Y., and the defendants agreed to pay the plaintiff for said work when completed according to said contract the sum of $6,850, and the making of two stipple-mental contracts to manufacture, construct and put up certain additional bronze and metal work in the said building; that the plaintiff entered into the performance of the work stipulated by him to be done under the said three several contracts, and had a large part of such manufactured material delivered at said bank building in Albany and the remainder thereof ready for delivery as fast as; required, whereupon the defendants, without just cause or excuse,, made claim that the work which the plaintiff was supplying and setting up on the job was not in accordance with the contracts and specifications, and acting on that claim the said defendants abruptly broke off said contracts by refusing to allow the plaintiff to perform and carry on his work to completion, notwithstanding that said work conformed entirely to the requirements of said contracts ; that the refusal of the defendants to accept the same, and the architect’s refusal to certify that said work was correct, and his refusal to approve the same, were both unreasonable and in nowise justified the defendants or said architect, or any one else with authority on the job, in stopping said work and preventing the plaintiff from carrying the same out to completion ; that the plaintiff upon being notified by the defendants by, or on, the 22d day of November, 1898, that they would not accept the work, notified the defendants in turn that the work was in conformity with the contracts, and then and there offered to proceed with the work to completion if the objections were withdrawn, and that by reason of the defendants’ default and violation of said contracts the plaintiff has sustained damage in the sum of $7,373, for which he demands judgment. The breach of the contract is denied by the answer, and it is also denied that the work of the plaintiff conformed to the requirements of the contract, and the answer alleges that the refusal of said defendants to accept the same, and that the architect’s refusal to certify that said work was correct and to approve [198]*198the same, were not unreasonable, but justify the defendants and the said architect in stopping said work and preventing the plaintiff from carrying the. same out to completion.

The question as to whether there was a breach of the contract by the defendants was the material question to be determined upon the trial, and that depended upon the obligation of the defendants to accept and use in the construction of the building of the Albany Savings Bank the materials furnished by the plaintiff. The plairn tiff testified that he met a Mr. Wesehler,, the superintendent of the, defendants ; that Wesehler called a Mr. Barmyer, who,, he said, was a general draftsman employed by the defendants and was the man to look over the job and superintend it; that the defendants had a contract .with the Albany Savings Bank to furnish some bronze material, and that there resulted from this interview the original contract in writing between, the plaintiff and the defendants, which was introduced in evidence. By this contract the plaintiff agreed-to provide “ all the materials ■ for and perform in a good and workmanlike manner, under the direction of Henry Ives Cobb, architect, and according to the plans and. specifications of the said architect, all the work set forth and explained in said plans and specifications, which plans and specifications, being identified by the signatures of the parties hereto, are to be considered as forming a part of this agreement; and in case any particulars shall be deficient or not clearly expressed in said plans and specifications, the said party of the second part (plaintiff) will apply to the said architect for additional -drawings and explanations, and will carry out the general design as directed by the said architect in a thorough manner as part of the contract. And in case of any said work done dr materials provided by the said party of the. second part shall be unsatisfactory to the said architect, then the said party of the second part will, on being notified thereof by the said architect, immediately remove such unsatisfactory work or materials and supply, the place thereof with other work and materials satisfactory to the said architect.” It was also provided that “If any question should arise during the progress of the work, or in the settlement of accounts touching the same, it is to be referred to the said architect, whose decision shall be binding upon both parties; ” that “ The work under this contract is to be begun forthwith and carried on promptly^ [199]*199and to be completed to the satisfaction of the architect as expressed by his written certificate on or before November 1st, 1898.” It was also provided that In case of any failure or unreasonable delay of the said party of the second part (plaintiff), whether by act or default in the performance of any of the above stipulations or compliance with the true intent of these presents, not authorized in writing by the said party of the first part (defendants) or said architect, it shall be lawful for the said party of the first part or said architect,, after giving five days’ notice in writing of their intention to the said party of the second part to provide other workmen and materials to complete the said work in the place of the said party of the second part, and to deduct the costs and charges thereby occasioned, from the sums otherwise becoming due to the said party of the second part, under this agreement, without prejudice to any other remedy which the said party of the first'part may have for breach thereof; ” and “ It is agreed that the decision of the architect as to whether there has been any failure or unreasonable delay in performance of any of the stipulations or compliance with the true intent of these presents, as mentioned in paragraph IY in this contract shall, in the absence of fraud or bad faith upon the part of Henry Ives Cobb, the architect, be final and conclusive upon the parties hereto, of which fact his certificate in writing shall be conclusive evidence.” The contract by its terms referred to the fitting and office partition for the “ bank building of Albany Savings Bank, now being erected on southwest cornér'of Horth Pearl Street and Maiden Lane, Albany, H. Y.” The architect who, by the agreement of the parties to this contract, was to determine whether or not the work and materials furnished by the defendant was a compliance with the contract, was not an architect employed by either of the parties to the agreement or representing either of them. He had prepared the plans for the building for the Albany Savings Bank, having charge of the construction of the building as between these defendants and the Albany Savings Bank, and whose approval of the work furnished by the defendants was necessary to enable the defendants to carry out their contract with the bank.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Untitled Texas Attorney General Opinion
Texas Attorney General Reports, 1961
Duffy Bros. v. Bing & Bing, Inc.
217 A.D. 10 (Appellate Division of the Supreme Court of New York, 1926)
Willson & Adams Co. v. Mack Paving & Construction Co.
147 A.D. 141 (Appellate Division of the Supreme Court of New York, 1911)
Woarms v. Becker
84 A.D. 491 (Appellate Division of the Supreme Court of New York, 1903)

Cite This Page — Counsel Stack

Bluebook (online)
72 A.D. 196, 76 N.Y.S. 438, Counsel Stack Legal Research, https://law.counselstack.com/opinion/becker-v-woarms-nyappdiv-1902.