Becker v. Setien

904 S.W.2d 338, 1995 Mo. App. LEXIS 1085, 1995 WL 350928
CourtMissouri Court of Appeals
DecidedJune 13, 1995
DocketWD 49453
StatusPublished
Cited by11 cases

This text of 904 S.W.2d 338 (Becker v. Setien) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Becker v. Setien, 904 S.W.2d 338, 1995 Mo. App. LEXIS 1085, 1995 WL 350928 (Mo. Ct. App. 1995).

Opinion

LAURA DENVIR STITH, Judge.

This is a negligence action arising from an accident at the construction site of Southeast Elementary School II construction project (construction project). Plaintiffs John and Kaye Becker have sued Defendants Carlos Setien, d/b/a Structural Steel Contract Services Corporation (Setien) and Havens Steel Company (Havens). Defendants, in accordance with their contract, installed the metal flooring for the gymnasium mechanical room, a room which was suspended from the ceiling of the gymnasium, and made a 3'4" by 4'4" access opening in the floor of the room so as to provide access to the room once it was completed. Once they had completed the floor and built the access opening, Defendants’ employees removed the ladder which provided access to the room and vacated the area. They did not cover, guard or barricade the hole itself.

Mr. Becker and his co-employees, in the meantime, had been building the concrete walls for the mechanical room. As the room was located 20 feet above the gymnasium floor, they reached it and built the walls by standing on a scaffolding located just outside where the walls were being built. Shortly after Defendants’ men left, and despite a warning about the presence of the hole, Mr. Becker decided to stand inside the room rather than on the scaffolding in order to build the walls. In the course of his work, he fell through the hole and sustained serious injury.

Plaintiffs alleged that Defendants were negligent in vacating the area after completing the flooring without covering, barricading, or otherwise guarding the hole. Plaintiffs also alleged that the failure to barricade violated OSHA regulations and that this provided a separate basis for liability. 1

Both Defendants Setien and Havens denied Plaintiffs’ allegations and asserted the applicability of the doctrine of comparative fault. They claimed that their contracts did not require them to build any, barricade or guard around the access opening, and that in any event they had turned control of the mechanical room and access hole back over to the prime contractor before Mr. Becker fell and thus could no longer be held respon *341 sible for injuries resulting to an employee of another subcontractor, such as Mr. Becker. Defendants also argued that the OSHA regulations on which Plaintiffs relied were irrelevant, because they only applied to temporary openings and the opening through which Mr. Becker fell was a permanent, not a temporary, opening.

Setien and Havens each filed independent motions for summary judgment. The trial court at first denied the motions, but on reconsideration and clarification of certain underlying facts, the court granted summary judgment in favor of both Defendants. This appeal followed. We affirm.

1. FACTUAL AND PROCEDURAL BACKGROUND

On October 5, 1990, the date of the accident, Mr. Becker was a bricklayer for Lindsey Masonry (Lindsey) working at the construction project site. He had worked as a bricklayer for eight years and had held the status of journeyman bricklayer for four or five years. Lindsey had sub-contracted with D.M. Ward Construction Company (Ward), the prime contractor for the construction project, to construct the walls of the school.

Defendant Setien had signed a subcontract with Ward to fabricate and install the steel elements of the construction project with the exception of the metal roof, deck and bar joints. Because Setien was not physically allowed at the project site, 2 Setien’s performance was limited to the fabrication and delivery of the steel. The steel was fabricated at Setien’s business location- and then delivered to the job site. The installation and erection of the steel delivered to the construction site was completed by Havens, pursuant to a subcontract with Setien.

The architectural and structural drawings for the Gymnasium Mechanical Room & Cooling Tower (“mechanical room”) clearly depict an uncovered “access opening” measuring 3'4" x 4' approximately 20 feet above the gymnasium floor. They did not depict either a barricade or cover for the access opening. It is undisputed that Defendants’ contract did not specifically require them to build a cover or barricade for the opening, and that when the building was finally completed, including at the time of summary judgment, the opening had no cover or barricade. 3

The details of the construction of the hole and of the accident were revealed through the deposition of the plaintiff, Mr. Becker, and through the affidavits of Havens’ foreman, John Dietrich, and Havens’ Field Superintendent, Robert Wirthman. This evidence revealed that, on the afternoon of October 4, 1990, Plaintiff Becker and the other masons were laying and “striking up” the concrete blocks which were to form the walls to the gymnasium mechanical room. As the room was attached to the ceiling and was 20 feet above the gymnasium floor, in order to reach the location for the walls, Mr. Becker and the other masons stood on a scaffold which had been constructed just outside the location for the walls.

The afternoon of October 4,1990, was also the day that Havens’ employees were to build the metal floor for the gymnasium mechanical room, and to cut the access opening in the rooflfloor of the gymnasium mechanical room, as called for by their contract. They put up a ladder through the opening so that they could reach the room to do their work. This was the only access opening to the room. Mr. Dietrich stated, without contradiction, that:

At no time while Havens was working in this area of the construction project did I observe employees of Lindsay [sic] Masonry or any other trade to be working on the inside of the wall or in the area where work was being performed by Havens. At all times while Havens was at work in this area of the project, the masonry contrae- *342 tors performed their work from the scaffolding on the outside of the wall.

Plaintiffs offered no opposing evidence. Further, Mr. Becker stated that, while standing on the scaffolding and building the wall from the outside of the room, he saw “the steel guys” use a chain saw to cut the hole for the access opening in the floor of the room on the afternoon of October 4, 1990. He further agreed that he saw the hole without difficulty after it was cut.

Mr. Dietrich stated that, the following morning, October 5, 1990, his men:

completed the installation of the metal deck work in the area of the mechanical room over the P.E. storage room. On that morning, I advised the prime contractor on the project, D.M. Ward Construction Company, that Havens was about to complete its work in that area.

After Havens’ men finished installing the metal deck work in the area of the mechanical room that morning, they vacated the area. Havens did not cover, guard, or barricade the floor opening before it left. 4 However, Mr. Dietrich stated that:

When we completed our work, and as I was leaving, I warned Mr. Becker and his foreman about the existence of the access opening on the other side of the wall....

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Housel v. HD Development of Maryland, Inc.
196 F. Supp. 3d 1039 (W.D. Missouri, 2016)
John C. Rapp v. Eagle Plumbing, Inc.
Missouri Court of Appeals, 2014
Rapp v. Eagle Plumbing, Inc.
440 S.W.3d 519 (Missouri Court of Appeals, 2014)
Weber v. McBride & Son Contracting, Co.
182 S.W.3d 643 (Missouri Court of Appeals, 2005)
Cook v. Smith
33 S.W.3d 548 (Missouri Court of Appeals, 2000)
Gould v. United States
994 F. Supp. 1177 (W.D. Missouri, 1998)
Rincon v. ABC Cutting Contractors, Inc.
706 So. 2d 322 (District Court of Appeal of Florida, 1997)
O'Neal v. Steinhage
949 S.W.2d 274 (Missouri Court of Appeals, 1997)
O'Brien v. Mansfield
941 S.W.2d 582 (Missouri Court of Appeals, 1997)
Shady Valley Park & Pool, Inc. v. Fred Weber, Inc.
913 S.W.2d 28 (Missouri Court of Appeals, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
904 S.W.2d 338, 1995 Mo. App. LEXIS 1085, 1995 WL 350928, Counsel Stack Legal Research, https://law.counselstack.com/opinion/becker-v-setien-moctapp-1995.