Beaver Creek Coal Company v. Nevada Power Company

968 F.2d 19, 1992 U.S. App. LEXIS 25255, 1992 WL 113747
CourtCourt of Appeals for the Tenth Circuit
DecidedMay 27, 1992
Docket89-4114
StatusPublished
Cited by1 cases

This text of 968 F.2d 19 (Beaver Creek Coal Company v. Nevada Power Company) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Beaver Creek Coal Company v. Nevada Power Company, 968 F.2d 19, 1992 U.S. App. LEXIS 25255, 1992 WL 113747 (10th Cir. 1992).

Opinion

968 F.2d 19

NOTICE: Although citation of unpublished opinions remains unfavored, unpublished opinions may now be cited if the opinion has persuasive value on a material issue, and a copy is attached to the citing document or, if cited in oral argument, copies are furnished to the Court and all parties. See General Order of November 29, 1993, suspending 10th Cir. Rule 36.3 until December 31, 1995, or further order.

BEAVER CREEK COAL COMPANY, Plaintiff-Appellee,
v.
NEVADA POWER COMPANY, Defendant-Appellant.

No. 89-4114.

United States Court of Appeals, Tenth Circuit.

May 27, 1992.

Before HOLLOWAY and McWILLIAMS, Circuit Judges, and BRATTON,*

ORDER AND JUDGMENT**

HOLLOWAY, Circuit Judge.

The primary issue in this appeal is whether the district court in the District of Utah erred in interpreting a coal supply contract on summary judgment. The court ruled as a matter of law that the Equity Clause in the parties' agreement did not contemplate the buyer's claim of inequity based upon an increase in the contract price of coal to a level significantly higher than the prevailing market price. For essentially the same reasons as were given by the district court, we affirm.

* In 1980 an electric utility, Nevada Power Company (Nevada Power), as purchaser and Beaver Creek Coal Co. (Beaver Creek) as seller concluded a long-term coal supply agreement. By its terms the agreement was effective for approximately 15 years, from March 1980 through December 1994. The contract terms established a base price for all coal delivered under the agreement of $20 per ton f.o.b. Acco, Utah. Under Section 8 of the contract, the parties agreed to make the base price adjustable on the basis of variables, including specified United States Department of Labor statistical indices, royalty rates, labor costs, and taxes.1

In addition to the price Adjustment Clause, the agreement contained language the parties described in general terms as an "equity clause." Section 9, entitled "Inequity and Hardship," provided:

It is the intent of the parties hereto that this Agreement, as a whole and in all of its parts, shall be equitable to both parties throughout its term. The parties recognize that omissions or defects in this Agreement beyond the control of the parties or not apparent at the time of its execution may create inequities or hardship during the term of the Agreement, and further, that supervening conditions, circumstances or events beyond the reasonable and practicable control of the parties may from time to time give rise to inequities which impose economic or other hardships upon one or both of the parties.

In the event an inequitable condition occurs which adversely affects one party, it shall be the joint and equal responsibility of both parties to act promptly to determine the action required to cure the inequity and effectively to implement such action. Upon written claim of inequity served by one party upon the other, the parties shall act jointly to reach an agreement concerning the claimed inequity within sixty (60) days of the date of such written claim. The party claiming inequity shall include in its claim such information and data as may be reasonably necessary to substantiate the claim and shall freely and without delay furnish such other information and data as the other party reasonably may deem relevant and necessary.

Coal Supply Agreement Sec. 9, at 12-13. The dispute between the parties focuses on the intended operation of the Equity Clause in relation to the base price Adjustment Clause.

The parties generally agree that by mid-1987 the base price adjustment formulas had increased the contract price to approximately $34 per ton, while the market price remained in the $20 range. In June 1987, Nevada Power sent a letter to Beaver Creek claiming an inequity under Section 8 of the contract, in part on the ground that the contract price had "increased to a level significantly higher than prevailing market price." II R.Doc. 103(a) Ex. F(1).

Following unsuccessful negotiations between the parties over Nevada Power's Section 9 claim, Beaver Creek filed this diversity action in the District of Utah in October 1987. In an amended complaint Beaver Creek sought, in part, a ruling by a declaratory judgment that Nevada Power was not entitled to relief under the Equity Clause. I R.Doc. 86.

In an unpublished Memorandum Decision and Order the district court decided that summary judgment interpreting the agreement was appropriate because the contract language was unambiguous as a matter of law. Without considering extrinsic evidence, the district court interpreted the Equity Clause as encompassing two categories of inequity claims: "one based on defects or omissions in the Agreement and one based upon supervening conditions, circumstances or events." III R.Doc. 141, at 8. The court concluded that Nevada Power had not presented valid claims within either category. The district court then entered final judgment in favor of Beaver Creek. Id. Doc. 163.2

We review a district court's ruling on a motion for summary judgment de novo, applying the same standard that the district judge used. Osgood v. State Farm Mut. Auto Ins. Co., 848 F.2d 141, 143 (10th Cir.1988). On summary judgment, we view all proffered summary judgment materials in the light most favorable to the non-moving party. Id. Summary judgment is proper only if the moving party has shown that there are no genuine issues of material fact and that it is entitled to judgment as a matter of law. Fed.R.Civ.P. 56(c).

II

Nevada Power contends that summary judgment was improper because it proffered extrinsic evidence of the parties' intent that created genuine issues of material fact over the meaning of the contract language. However, under the general rules of contract interpretation that Utah follows, a court must attempt to determine the intended meaning of a contract from the plain language of the instrument before considering extrinsic evidence about the parties' intended meaning. See, e.g., Plateau Mining Co. v. Utah Div. of State Lands & Forestry, 802 P.2d 720, 725 (Utah 1990); Utah Valley Bank v. Tanner, 636 P.2d 1060, 1061-62 (Utah 1981). If the meaning of a contract is clear and unambiguous, extrinsic evidence generally is not admissible to explain the parties' intent. E.g., Faulkner v. Farnsworth, 665 P.2d 1292, 1293 (Utah 1983). Thus, we must address first the district court's ruling that the contract language was unambiguous as a matter of law. See, e.g., Gomez v. American Elec. Power Serv.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
968 F.2d 19, 1992 U.S. App. LEXIS 25255, 1992 WL 113747, Counsel Stack Legal Research, https://law.counselstack.com/opinion/beaver-creek-coal-company-v-nevada-power-company-ca10-1992.