Bayou Liberty Ass'n v. United States Army Corps of Engineers

217 F.3d 393, 30 Envtl. L. Rep. (Envtl. Law Inst.) 20757, 2000 U.S. App. LEXIS 17308, 2000 WL 874664
CourtCourt of Appeals for the Fifth Circuit
DecidedJuly 19, 2000
Docket98-31260
StatusPublished
Cited by72 cases

This text of 217 F.3d 393 (Bayou Liberty Ass'n v. United States Army Corps of Engineers) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bayou Liberty Ass'n v. United States Army Corps of Engineers, 217 F.3d 393, 30 Envtl. L. Rep. (Envtl. Law Inst.) 20757, 2000 U.S. App. LEXIS 17308, 2000 WL 874664 (5th Cir. 2000).

Opinion

CARL E. STEWART, Circuit Judge:

The appellant, Bayou Liberty Association, Inc. (“BLA”) challenges the district court’s denial of its motion for preliminary injunction and dismissal of its complaint. For the following reasons we remand to the district court with instructions to dismiss the case as moot.

FACTUAL AND PROCEDURAL BACKGROUND

In February 1998, Wal-Mart, Sam’s Club, and Home Depot (collectively “inter-venors” or “appellees”) applied to the United States Army Corps of Engineers (“Corps”) to obtain a permit pursuant to the Clean Water Act, 33 U.S.C. § 1344 to construct a retail complex in the Bayou Liberty area of St. Tammany parish. BLA is an association of approximately 140 members who own homes near the bayou.

After an administrative process which included participation from federal, state and local agencies, along with comments from the public, the Corps issued the defendants a permit in September 1998. Along with the permit, the Corps issued a “Permit Evaluation and Decision Document,” that included an environmental assessment (“EA”) with a finding of no significant impact (“FONSI”). Due to the finding of no significant impact the Corps was not required under the statute to complete a more extensive environmental impact statement.

In October 1998, BLA filed suit against the Corps under the National Environmental Policy Act (“NEPA”), 42 U.S.C. § 4331 et seq., and the Administrative Procedure Act (“APA”), 5 U.S.C. § 706, et seq. BLA alleged that the Corps had issued the permit in violation of NEPA by failing to consider the impact of the development, alone and along with the cumulative impact of other development, on flooding in Bayou Liberty. BLA sought declaratory and injunctive relief which in sum sought to suspend the permit issued by the Corps.

The district court denied BLA’s motion for a temporary restraining order. After further pleadings and argument the district court denied BLA’s motion for a preliminary injunction and dismissed BLA’s complaint with prejudice. BLA filed a notice of appeal and made a motion before this court for an injunction pending resolution of the appeal. That motion was denied in November 1998. Wal-Mart and Home Depot subsequently filed separate *396 motions to dismiss the appeal which have been carried with the case.

DISCUSSION

I. Mootness

Intervenors, Wal-Mart and Home Depot have filed motions to dismiss the appeal on the basis that BLA’s claims are moot because construction of the retail complex has been completed. We must address the issue of mootness first, because to qualify as a case for federal court adjudication, a case or controversy must exist at all stages of the litigation, not just at the time the suit was filed. Harris v. City of Houston, 151 F.3d 186, 189 (5th Cir.1989) (citations omitted). Whether a case is moot is a question of law that we resolve de novo. Id.

We have consistently found that a request for injunctive relief is moot when the event sought to be enjoined has occurred. Id. (citations omitted). When a party seeks an injunction to halt a construction project the case may become moot when a substantial portion of that project is completed. See Florida Wildlife Federation v. Goldschmidt, 611 F.2d 547 (5th Cir.1980). In the present case, BLA sought both injunctive and declaratory relief. In its complaint BLA requested the following relief: (1) a preliminary injunction staying or suspending the permit issued by the Corps for the retail complex development; (2) a declaratory judgment declaring that the Corps’ approval of the development permit without preparation of an EIS was arbitrary, capricious, and an abuse of discretion; (3) a permanent injunction vacating the Corps’ permit for the retail complex development and prohibiting reissuance of the permit until the Corps prepared an EIS; (4) a declaratory judgment stating that the Corps’ approval of the permit without consideration of all direct and indirect effects, and cumulative impact is arbitrary, capricious and an abuse of discretion; (5) a permanent injunction vacating the Corps’ permit until the Corps considers the direct, indirect, and cumulative environmental impacts of such development.

Based on this requested relief BLA’s claims are moot. BLA’s requested injunctive relief requests staying or suspending the permit and requiring the Corps to consider the direct, indirect, and cumulative impacts. BLA also sought declaratory relief stating that the Corps was required to consider these impacts before granting the permit. However, even if this court were to find in BLA’s favor and suspend or stay the permit, this action would not have any effect because the construction authorized by the permit has been substantially completed. As we have previously noted:

[T]he basic thrust of NEPA legislation is to provide assistance for evaluating proposals for prospective federal action in the light of their future effect upon environment factors, not to serve as a basis for after-the-fact critical evaluation subsequent to substantial completion of construction ... the courts have been reluctant, at least in the absence of blatant bad-faith violations, to grant relief after the challenged project has been substantially or wholly completed, even in instances where the agency ... has acted in violation of NEPA-mandated precon-struction procedures.

Richland Park Homeowners Association v. Pierce, 671 F.2d 935, 940 (5th Cir.1982).

BLA argues that the relief it requested is not moot because meaningful relief is still available. On appeal, BLA seeks a declaratory judgment defining the obligations of the Corps in evaluating applications for permits for construction on wetlands, and a remand to the Corps for further consideration of the risk of flooding from the retail complex and measures that can be taken to abate the risk.

BLA contends that its present situation is similar to one we resolved in Vieux Carre Property Owners v. Brown, 948 F.2d 1436 (5th Cir.1991). In Vieux Carre, *397 an historic building preservation group claimed that the Corps approved construction of a park and aquarium without following the procedures set forth in the National Historic Preservation Act (“NHPA”), 16 U.S.C. § 470 et seq. Id. at 1438.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
217 F.3d 393, 30 Envtl. L. Rep. (Envtl. Law Inst.) 20757, 2000 U.S. App. LEXIS 17308, 2000 WL 874664, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bayou-liberty-assn-v-united-states-army-corps-of-engineers-ca5-2000.