Bausch & Lomb Optical Co. v. United States

78 Ct. Cl. 584, 1934 U.S. Ct. Cl. LEXIS 379, 1934 WL 2018
CourtUnited States Court of Claims
DecidedJanuary 8, 1934
DocketNo. E-17
StatusPublished
Cited by3 cases

This text of 78 Ct. Cl. 584 (Bausch & Lomb Optical Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bausch & Lomb Optical Co. v. United States, 78 Ct. Cl. 584, 1934 U.S. Ct. Cl. LEXIS 379, 1934 WL 2018 (cc 1934).

Opinions

Williams, Judge,

delivered the opinion of the court:

This case is before the court under an order granting; plaintiff’s motion for a new trial on the ground of newly discovered- evidence.

The petition asserts that there is a balance due the plain- • ('tiff for work performed under Navy contract no. 33631, of -'$34,195.23, as follows:

" 1. The -sum of $16,743.67, the Navy Department’s one- ■ fourth part of the cost to plaintiff of maintaining extra guards at its plant from December 4, 1917, to December 6,, 1918.

• 2. The sum of $17,451.56, which was deducted by the Comptroller General from the amount due plaintiff under the contract upon a final settlement of the same.

The amount deducted by the Comptroller General from, the amount due plaintiff under contract no. 33631 consisted of the items $16,743.67, which had been paid to the plaintiff' ■ by the War Department as that Department’s one-fourth ' part of the cost of maintaining the additional guards, and $707.89, which as liquidated damages had been assessed against the plaintiff and deducted from the amount due-plaintiff under another' contract and which had later been refunded to plaintiff by the War Department.

Upon the former hearing of the case we held that the plaintiff was not entitled to recover the amount claimed as compensation for maintaining extra guards at its plant during the period involved, for the reason that plaintiff had no ' contract, ¿xpress or implied, either with the Navy Department or the War Department, obligating the Government to pay such expenses. We held that plaintiff was entitled to recover $707.89, the sum deducted from the amount due . plaintiff under contract no. 33631, as liquidated damages due the United States from plaintiff under war contract no. 'Po 55 C.F., and judgment was awarded plaintiff, in that amount. The defendant in this proceeding does not contest, plaintiff’s right to recover as to' this item of the claim;.

[603]*603The special findings of fact as previously made have been amended to accord with the additional evidence adduced by plaintiff in the proceedings under the new trial.

The circular letter set forth in finding V did not direct plaintiff to install additional guards at its plant. The plaintiff was informed in the letter that it would be required to provide such additional watchmen and devices for protection of its plant and property, and the work in process for the Navy Department “ as may be required by the Secretary of the Navy,” and “that in case the Navy Department directs, the contractor to provide additional watchmen * * *, special arrangements will be made in each case to make a suitable modification in existing contracts so as to provide for such expense.” The provisions of the letter, which became a part of all existing contracts and those subsequently entered into between plaintiff and the Bureau of Supplies and Accounts of the Navy Department, only obligated the Government to contribute to the expense of maintaining such additional watchmen as the Navy Department should direct plaintiff to provide. The determination as to whether extra watchmen should be installed at plaintiff’s plant rested solely with the Secretary of the Navy. Unless, therefore, the Secretary of the Navy, or someone having authority to represent him, directed plaintiff to install the additional guards at its plant there existed no contractual liability on the part of the United States to compensate plaintiff, in whole or in part, for the cost incurred in their maintenance.

Lieutenant Commander Charles H. Davis, Jr., naval inspector of ordnance, and Lieutenant Colonel Thomas J. Smith, Jr., Army inspector of ordnance, who participated in the conference at plaintiff’s plant at the time it was determined that the security of the plant required the employment of extra guards and that they should be immediately installed, were not contracting officers. They were stationed at plaintiff’s plant charged with the duty of inspecting and examining for their respective departments articles and equipment, then being manufactured by plaintiff, to determine before acceptance by the Government whether such articles and equipment met contract requirements. It [604]*604is not shown that either of these officials had authority to act on any matter relating to plaintiff’s contracts outside of the performance of these duties. Inspector Davis therefore did not have authority, on behalf of the Navy Department, to require or direct plaintiff to install extra guards at its plant under the circular letter of October 16, 1917, or to contract with plaintiff in reference to the expense of maintaining such guards. The Navy Department did not thereafter confirm or ratify the unauthorized action of Inspector Davis in participating in the installation of the additional guards at plaintiff’s plant and did not at any time direct the plaintiff to provide them. Consequently no legal liability attached to the Government under the provisions of the circular letter to make “ special arrangements ” or suitable modifications for the additional expense incident to the maintenance of the guards.

The letter of November 22, 1918 (finding XIII) from the naval inspector of ordnance at plaintiff’s plant set forth a letter received by that official from the acting chief of the Bureau of Ordnance, which was obviously a circular letter addressed to all firms having ordnance contracts with the Navy Department. The instructions to naval inspectors to “ take steps to reduce as rapidly as possible the forces of guards and watchmen to the number normally necessary on a peace basis ” had reference only to such additional watchmen and guards as the Navy Department had “ directed ” contractors to provide at their plants and for whose expense arrangements had been made between the “ Navy Department and the contractor concerned.” The letter created no liability on the part of the Government to pay any part of the expense incurred in maintaining extra guards which the Navy Department had not directed contractors to provide, nor can it be construed as a recognition by the Navy Department of the authority of Inspector Davis to direct the installation of the extra guards at plaintiff’s plant or as a ratification of his unauthorized action in so doing.

The plaintiff contends that in the event it be held there was no express contract providing that the Government would pay, on behalf of the Navy Department, one-fourth part of the expense of maintaining the additional guards [605]*605it is entitled to recover the amount claimed on an implied contract. In support of this contention numerous cases are cited in which the rule is announced that where a party enters into an agreement with a representative of the Government, even though such agreement be not reduced to writing, and the representative of the Government had no authority to make the agreement, the party may recover the value of the services rendered under the contract, if he has performed in accordance with its terms, and such services have been accepted by the Government.

There is no question as to the correctness of this rule and it has been applied by this court in many cases. The right to recover in such cases is limited to the reasonable value of the services performed and accepted. It must appear that the Government received and accepted the services performed and that it derived the benefit of them. In this case the plaintiff received the direct benefit of the services of the additional guards at its plant. They were guarding and protecting its plant and property.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Montefiore Hospital Ass'n v. United States
5 Cl. Ct. 471 (Court of Claims, 1984)
Salem Products Corporation v. United States
298 F.2d 808 (Second Circuit, 1962)
Central Engineering & Construction Co. v. United States
59 F. Supp. 553 (Court of Claims, 1945)

Cite This Page — Counsel Stack

Bluebook (online)
78 Ct. Cl. 584, 1934 U.S. Ct. Cl. LEXIS 379, 1934 WL 2018, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bausch-lomb-optical-co-v-united-states-cc-1934.