Bates Expanded Steel Truss Co. v. Sisters of Mercy of Janesville

243 N.W. 456, 208 Wis. 457, 1932 Wisc. LEXIS 388
CourtWisconsin Supreme Court
DecidedJune 20, 1932
StatusPublished
Cited by2 cases

This text of 243 N.W. 456 (Bates Expanded Steel Truss Co. v. Sisters of Mercy of Janesville) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bates Expanded Steel Truss Co. v. Sisters of Mercy of Janesville, 243 N.W. 456, 208 Wis. 457, 1932 Wisc. LEXIS 388 (Wis. 1932).

Opinion

Fritz, J.

The underlying question which affects the claims of all of the subcontractors and materialmen on this appeal is whether the Commercial Casualty Insurance Company, as surety for Krasin Brothers, the principal contractors, is liable for the indebtedness which is owing by Krasin Brothers for labor and materials furnished in erecting a building on premises owned by the Sisters of Mercy, but for which indebtedness there exists no lien or claim for which the owner of the premises is liable. The contract between Krasin Brothers and the owner provided that—

“The contractor shall and will provide all materials and will perform all the work ... as shown on the drawings and described by the specifications prepared . . . and become hereby a part of this contract.”

The specifications, which by those words in the contract were made a part of the contract, provided:

“The contractor shall furnish and pay for a good and sufficient bond . . . conditioned upon the faithful performance of his contract and the payment of all claims for labor [460]*460performed or materials furnished in and about the completion of his contract.”

That requirement in the specifications was not complied with. The surety bond, which was furnished and accepted by the owner, was not, as prescribed by the specifications, conditioned upon the payment of all claims for labor or materials. Instead, the provision of the bond was merely as follows:

“The conditions of this bond are such that if said parties of the first part (Krasin Brothers) shall faithfully keep and perform the within contract and duly execute and perform all and several the undertakings and agreements therein contained, by them to be executed and performed, then this obligation shall be void, otherwise of full force.”

Consequently, neither the contract nor the bond, upon which the subcontractors and materialmen now rely to hold the surety, expressly provided that the contractor or the surety agreed to pay all claims for labor or materials furnished. The only provision in either the contract or the bond as to the payment of claims chargeable to the contractor is as follows:

“Article IX. If at any time there shall be evidence of any lien or claim for which, if established, the owner of the said premises might become liable, and which is chargeable to the contractor, the owner shall have the right to retain out of any payment then due or thereafter to become due an amount sufficient to completely indemnify it against such lien or claim. Should there prove to be any such claim after all payments are made, the contractor shall refund- to the. owner all moneys that the latter may be compelled to pay in discharging' any lien on said premises made obligatory in consequence of the contractor in default.”

It must be noted that that provision relates only to “any lien or claim for which . . . the owner . . . might become liable and which is chargeable to the contractor.” It is only [461]*461as to such liens or claims that the contract provides that “the contractor shall refund to the owner all moneys that the latter may be compelled to pay in discharging any lien.” If no such liens or claims exist in favor of the subcontractors or materialmen, who are still parties to this action, — if the only claims now involved herein are claims for which the owner does not become liable, and which the owner cannot be compelled to pay, — then they are not within the class of indebtedness to which that art. IX of the contract relates.

Under those facts and circumstances this case is ruled by the decisions in Electric Appliance Co. v. United States F. & G. Co. 110 Wis. 434, 85 N. W. 648; Yawkey-Crowley L. Co. v. De Longe, 157 Wis. 390, 147 N. W. 334. In the case at bar as in those cases, the fact that the owner accepted a bond, which was not in compliance with the specifications in that it did not require the payment of all claims for labor and material, was clearly a waiver of that requirement in the specifications as to the obligations of the proposed bond, and resulted in the abandonment or relinquishment of that requirement in the specifications. The following excerpts from the opinion in Yawkey-Crowley L. Co. v. De Longe, supra, are directly applicable in the case at bar: '

“Does the contract of the principal contractor and the owner and the bond given for its faithful performance show that it was intended that subcontractors furnishing labor or material for the erection of this building to the principal contractor should have the benefit of the bond given to secure faithful performance of the construction contract and promise payment to them? A consideration of the provisions of the contract and bond leads us to the conclusion that it was intended that the bond should be a protection only to the obligee party, O. F. De Longe. The contract and bond are a part of the complaint. It appears that the contractor was to provide all the materials and perform all the work required to erect and remodel the portions of the [462]*462buildings embraced in the plans and specifications, made a part of the contract. ... It is also stipulated that the owner shall have the right to deduct from any amount due the contractor his damages, and it is expressly agreed that if there shall be any lien or claim for which the owner, is legally liable and which arises from obligation of the contractor, the owner is to retain out of any amount due the contractor a sum sufficient to indemnify himself against such lien or claim. . . . The tenor of all the agreements in the contract and bond shows that the parties intended the security should be for the benefit of the owner only, and that laborers and materialmen were not to be benefited thereby, nor was there a promise of payment of their demands. Under these conditions of the contract and bond the security is only protection to the obligee named therein; and subcontractors and laborers of the contractor obtained no right which they can enforce against the surety, and hence they have no cause of action against the surety upon their complaints, and the demurrers' of the surety company to the complaints of these subcontractors and laborers must be sustained.”

This court has adopted a liberal policy in respect to the right of subcontractors, who furnished labor or materials to a principal contractor, to recover from a paid surety the indebtedness owing to them by the principal contractor. United States G. Co. v. Gleason, 135 Wis. 539, 116 N. W. 238; R. Connor Co. v. Ætna Indemnity Co. 136 Wis. 13, 115 N. W. 811; Warren Webster & Co. v. Beaumont Hotel Co. 151 Wis. 1, 138 N. W. 102; Concrete Steel Co. v. Illinois Surety Co. 163 Wis. 41, 157 N. W. 543; Milwaukee B. S. Co. v. Illinois Surety Co. 163 Wis. 48, 157 N. W. 545; Builders L. & S. Co. v. Chicago B. & S. Co. 167 Wis. 167, 166 N. W. 320; New York C. I. F. Co. v. Kenosha, 167 Wis. 371, 167 N. W. 451; Northwestern B. & I. Co. v. Maryland Cas. Co. 171 Wis. 526, 177 N. W. 31; Baumann v. West Allis, 187 Wis. 506, 204 N. W. 907; Sinaiko v. Hustad, 189 Wis. 298, 206 N. W. 976. However, in each of those cases with the exception of Baumann v. West Allis, [463]*463supra, there was either in the contract or in the bond a provision expressly promising to pay for all labor and material furnished to the principal contractor for the construction of the building.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Holland Plastics Co.
331 N.W.2d 320 (Wisconsin Supreme Court, 1983)
McCormick v. Kuhnly
131 N.W.2d 840 (Wisconsin Supreme Court, 1965)

Cite This Page — Counsel Stack

Bluebook (online)
243 N.W. 456, 208 Wis. 457, 1932 Wisc. LEXIS 388, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bates-expanded-steel-truss-co-v-sisters-of-mercy-of-janesville-wis-1932.