Barton Solar, LLC v. RBI Solar, Inc.

CourtDistrict Court, D. Vermont
DecidedFebruary 21, 2025
Docket5:21-cv-00025
StatusUnknown

This text of Barton Solar, LLC v. RBI Solar, Inc. (Barton Solar, LLC v. RBI Solar, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Vermont primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Barton Solar, LLC v. RBI Solar, Inc., (D. Vt. 2025).

Opinion

UNITED STATES DISTRICT COURT DISTRICT OF VERMONT US FEB 21 PH bs 04 CLERK VO □□ BARTON SOLAR, LLC ) he Plaintiff, ) Vv. No. 5:21-cv-00025 RBI SOLAR, INC., Defendant. )

ORDER DENYING PLAINTIFF’S MOTION FOR A MANDATORY INJUNCTION (Doc. 119; Doc. 139) Plaintiff Barton Solar, LLC (“Barton” or “Plaintiff’) seeks a mandatory injunction, compelling RBI Solar, Inc. “RBI” or “Defendant” either to make emergency repairs to the solar array that is the subject of this litigation or certify that the array, in its current condition, is structurally sound. Plaintiff is represented by Andrew J. Snow, Esq. and Ronald W. Dunbar Jr., Esq. Jesse Lipcius, Esq. and Daniel Seff, Esq. represent Defendant. I. Background The Barton Solar Project is a solar electric generation facility located in Barton, Vermont. (Doc. 112-10, 1.) It is owned and operated by Plaintiff. (Doc. 42, 9 1.) RBI is an Ohio company specializing in the design, manufacture, and installation of custom racking systems. (/d. {J 2, 7.) On July 21, 2014, Barton contracted with RBI to design and install a racking system and solar panels for the Barton Solar Project. (Doc. 105-4.) The racking system is the foundation of the solar array, and includes the posts driven into the ground as well as the above-ground structural components connected to the embedded posts. (See Doc. 112-10, 4 4; Doc. 112-13, 92.) The solar panels attach to the above-ground components of the racking system. (See Doc. 105-6 at 8; Doc. 112-1 at 42; Doc. 112-13, 2.)

RBI completed the installation of the racking system and solar panels in 2015. (See Doc. 112-10, 4 1, 19; Doc. 105-9 at 26:9-13.) Shortly after construction was completed, Barton told RBI it noticed damage to the solar array. (See Doc. 112-10, | 8.) Barton alleged that the damage was the result of frost heaving. (/d. J 9.) Frost heave is defined as “the upward ground movement that occurs as soil freezes.” (Doc. 119-1 at 4.) Specifically, Plaintiff believed the upward movement of the embedded racking posts caused damage to other components of the racking system. (See Doc. 112-10, {J 8-9.) Initially, RBI took some measures to try and remediate the problem. (Doc. 112-5 at 59:13- 60:4, 63:25-64:7; see Doc. 112-14, {Ff 5-6.) For example, RBI installed tie-downs to some of the embedded posts. (Doc. 112-5 at 67:15-68:6.) RBI placed an anchor in the ground adjacent to the existing post and the post was tied to the anchor in an effort to keep the post from moving. Id. On October 27, 2016, Krebs & Lansing Consulting Engineers (“K&L”), the civil site engineer for the Barton Solar Project, inspected the array. (Doc. 112-13, 99 4-5.) They marked the portion of the electrical conduit attached to the racking posts, in addition to the posts themselves, so, at a future date, K&L could determine whether any additional upward movement of the conduit or the racking posts had occurred. (Ud. J] 4-7.) Upon returning on April 20, 2017, to remeasure the markings, K&L determined upward movement had occurred. Ud. 7 7.) K&L visited the site again on May 16, 2018, and discovered the embedded posts continued to move. (Id. 8-9.) Barton alleges the frost heaving action has caused the racking posts to move upward, in varying amounts, causing the other components of the racking system to bend, twist, or break. (Doc. 112 at 13; see Doc. 112-1 at 4.) Barton further alleges that the majority of the posts have moved upward significantly enough that they no longer provide a stable foundation for the solar

/

panels, rending the entire solar array unstable. (See Doc. 119 at 10.) At this time, Barton asserts that the solar array is near “catastrophic failure” due to the extent of the movement in the racking posts. Ud. at 8.) Plaintiff alleges, in part, that RBI’s design and installation of the racking system failed to consider the likelihood that the ground on which this array was built would experience frost heaving. (See Doc. 112-1 at 3.) RBI disagrees as to the cause and extent of the damage and movement of the racking posts. (Doc. 105 at 8-9; Doc. 145 at 9-10.) RBI contends the need for emergency repairs is speculative, asserting that the movement in the racking posts may be due to factors outside of its work. (See Doc. 105 at 8.) RBI also disputes the reliability of Plaintiff’s data as to the movement of the racking posts. (Ud. at 11.) It asserts that K&L’s post movement measurements are unreliable as no baseline measurements were taken at the time of installation, and therefore cannot support a claim for emergency relief. (/d.) I. Procedural History In this action, there are five remaining claims brought by Barton against RBI, including Breach of Express Warranty, Breach of Express Contract for Indemnification, Breach of Contract, Fraudulent Inducement, and Fraudulent Concealment. (Doc. 112-10, § 2.) Barton seeks “full, just and adequate compensation, compensatory damages, treble damages, punitive damages, attorneys’ fees, costs, and such other relief as is just and appropriate.” (Doc. 42 at 19.) Defendant filed a Motion for Partial Summary Judgment on July 17, 2023 as to the counts alleging Breach of Express Contract for Indemnification, Fraudulent Inducement, and Fraudulent Concealment. (Doc. 105.) Plaintiff has not filed for summary judgment.

On February 23, 2024, Barton filed a Motion for a Mandatory Injunction to Compel RBI to make emergency repairs to the array. (Doc. 119.) Specifically, Barton asserted the following in support of its request for injunctive relief: [b]ecause of this frost action impact on the driven post foundations at the Barton Solar Project, the foundation system has failed, and has resulted in post heaving, which has and is causing ongoing damage to the electrical equipment, conduit, modules, and wiring at the project site, that has required annual repairs and remediation, and has cost Barton thousands of dollars in lost revenues due to an inability of the pv system to generate maximum power due to system outages and downtime caused by the heaving and concomitant damage. at 5-6.) Barton further asserted that the costs being incurred by Barton are “accelerating.” (Ud. at 7.) Barton argued: [i]f this work is not completed, the next broken module in the array will render the array at less than 100% operating efficiency (since no replacement modules exist for that damage/destroyed module), which loss in production and revenue can never be replaced. As stated, this damage may also shut down the array inverters due to a “ground fault” condition resulting from this damage and destruction. (Id. at 11.) Additionally, Barton alleged that a significant number of posts in the racking system have heaved sufficiently to cause substantial destabilization of the solar array which necessitates immediate remediation. Barton stated that “[a]t any moment, an event such as a strong wind could completely topple portions of the system causing catastrophic damage to the array and anyone in the immediate vicinity.” Cd. at 9.) RBI, in a response filed March 8, 2024, opposed the granting of this motion. (See Doc. 121.) In this response, RBI challenged Barton’s characterizations that “a strong wind event could completely topple portions of the [Project] causing catastrophic damage.” (/d. at 4) (alteration in original) (quoting Doc. 119 at 9.) RBI further argued that the possibility of an award of monetary damages at the end of the litigation renders a mandatory injunction inappropriate. (/d. at 7-8.)

On July 19, 2024, this motion, as well as Defendant’s Motion for Partial Summary Judgment, were stayed pending settlement negotiations. (Doc. 125.) The matter was referred to Magistrate Judge Kevin J. Doyle for that purpose. On September 27, 2024, the parties notified the court that settlement negotiations were not successful. (Doc. 133, J 1-2.) The case was assigned to this court on October 1, 2024. (Doc. 135.) A status conference was held on November 12, 2024. (See Doc.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Barton Solar, LLC v. RBI Solar, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/barton-solar-llc-v-rbi-solar-inc-vtd-2025.