Bartlett v. Miller & Schroeder Municipal, Inc.

355 N.W.2d 435, 1984 Minn. App. LEXIS 3557
CourtCourt of Appeals of Minnesota
DecidedSeptember 18, 1984
DocketCX-84-466
StatusPublished
Cited by14 cases

This text of 355 N.W.2d 435 (Bartlett v. Miller & Schroeder Municipal, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bartlett v. Miller & Schroeder Municipal, Inc., 355 N.W.2d 435, 1984 Minn. App. LEXIS 3557 (Mich. Ct. App. 1984).

Opinion

OPINION

POPOVICH, Chief Judge.

This appeal is from a judgment of dismissal of appellants’ action based upon the running of the statute of limitations. Appellants are holders of industrial development revenue bonds issued by the Seaway Port Authority of Duluth (SPAD), underwritten by respondent Miller & Schroeder, and used to finance the construction of a malic acid plant. Following the default of the tenant of that facility, the plant was sold below cost in September 1976.

A class action suit was brought on behalf of the bondholders in federal district court in May 1976, but class certification was denied in May 1977. A similar class action was then brought in state court in November 1977. The trial court, distinguishing American Pipe and Construction Co. v. Utah, 414 U.S. 538, 94 S.Ct. 756, 38 L.Ed.2d 713 (1974), ruled that the statute of limitations was not tolled during this second class action, and that the six-year statutory period had expired when this action was brought on July 27, 1983. We affirm.

FACTS

Some of the facts of this case are set out in our opinion in the related case of Whitehill v. Seaway Port Authority of Duluth, 349 N.W.2d 313 (Minn.Ct.App.1984).

The malic acid plant was to be leased by International Organics, Inc. (IOI), a newly-formed company owned by four individuals, respondents Edward Lemke and Robert Mack, and Paul Price and Warren Peterson. In addition to the revenue bonds, financing for construction of the facility was to come from equity in IOI, a loan from a local development agency, and a loan from the United States Economic Development Agency (EDA).

Sale of the $1,585,000 in revenue bonds was completed in July 1973. Following the Arab oil embargo in the fall of 1973, however, prospects for the production of malic acid from benzene, a petroleum by-product, changed drastically.

In July 1974, IOI informed SPAD that it would be financially unable to complete the project, due to cost overruns in construction and the rising price of benzene. A letter to this effect was sent to SPAD by respondent Lemke, the president of IOI. Respondents Price and Peterson, however, wanted IOI to continue with the project. Lemke and Mack resigned their positions with IOI in August 1974, and the project continued. IOI, however, was unable to obtain the additional capital required to complete the plant and put it in operation. The EDA loan was available only upon completion of construction, contrary to representations allegedly made by respondents that it would be unconditionally available.

The revenue bonds were to be paid from rental payments made by IOI, but IOI never made any rental payments. SPAD took possession of the unfinished' plant in December 1974 and began a search for other buyers or tenants.

A Reserve Fund established by the terms of the Bond Resolution was sufficient to make the interest payments due the bondholders until June 1, 1976, when the first default occurred. The plant was sold, at a price substantially below cost, in September 1976.

On May 19, 1976, Miller & Schroeder filed a class action suit in federal district court against SPAD, IOI, its four shareholders, and the First National Bank of Duluth, alleging the following: federal securities law fraud, state securities law fraud, common law fraud, negligence and *438 breach of fiduciary duty, and breach of contract. Shortly thereafter, one of the bondholders (not a party here), Daisy Whitehill, moved to intervene as a plaintiff, to have Miller & Schroeder realigned as a defendant, and to have the bondholders certified as a class with her as its representative. The motions for intervention and realignment were granted, and White-hill filed her complaint.

The federal district court, however, denied the motion for class certification on May 10, 1977. The court held, in the federal securities law claim, individual questions of law and fact predominated over common questions. The pendent state claims were also denied certification. After a motion for reconsideration of its decision, the district court on June 29, 1977 again rejected certification, and directed all bondholders be notified of the denial of the class action status, and be given 60 days to intervene. The bondholders were also advised they should seek legal counsel if they felt they had a claim. It appears no bondholders moved to intervene, the federal action lapsed, and was later dismissed for lack of prosecution in November 1980.

Whitehill then brought a class action in state court on November 8, 1977. Initially venued in Hennepin County, this action named SPAD and Miller & Schroeder as defendants. The original complaint alleged breach of contract and fiduciary duty by both SPAD and Miller & Schroeder, common law fraud, and failure to register securities in violation of state law.

Plaintiff Whitehill, in response to motions for dismissal made by both SPAD and Miller & Schroeder, wrote to all bondholders notifying them of the status of the class action litigation. This letter, which is undated, requested additional written concurrences to the litigation from the bondholders. Whitehill, who had already obtained concurrences from holders of 25% of the total principal of the bonds as required by Section 4-11 of the Bond Resolution, was seeking additional concurrences in response to SPAD’s claim that a 51% concurrence was required. SPAD subsequently settled out of the suit.

Miller & Schroeder moved to strike the class action allegations based on collateral estoppel due to denial of certification in federal district court. On July 3, 1978, the state trial court granted this motion with respect to the common law fraud and non-registration claims, holding that class certification on these pendent state claims had been decided on the merits in the federal action. The federal court’s orders were found to be ambiguous as to whether denial on the other claims was on the merits or under principles of pendent jurisdiction, so these were allowed to stand as class action claims. The bondholders were not formally notified of this order, but were informally notified according to appellants’ counsel.

Following this order, Whitehill amended her complaint adding the previously-omitted federal defendants, deleting the non-registration claim, and removing the common law fraud claim as a class action allegation. This amendment appears to have been intended to preserve Whitehill’s action as a class action, following the state trial court’s order. There were subsequent amendments of the complaint, but no other significant action until a motion to consolidate with the files of other bondholders, including all but one of appellants here, in October 1981. This motion was denied in March 1982.

Miller & Schroeder thereafter moved to strike the class action allegations of the Whitehill complaint. The trial court granted this motion in January 1983.-

Appellants then brought the present action on July 27, 1983 in St. Louis County. Appellants’ attorney has been involved in the case since the Whitehill action in federal court.

ISSUE

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pronk v. City of Rochester
D. Minnesota, 2023
Chappell v. BUTTERFIELD-ODIN SCHOOL DISTRICT NO. 836
673 F. Supp. 2d 818 (D. Minnesota, 2009)
Abbotts v. Campbell
551 F.3d 802 (Eighth Circuit, 2008)
Mercer v. Andersen
715 N.W.2d 114 (Court of Appeals of Minnesota, 2006)
Raygor v. University of Minnesota
604 N.W.2d 128 (Court of Appeals of Minnesota, 2000)
Johnson v. County of Anoka
536 N.W.2d 336 (Court of Appeals of Minnesota, 1995)
Singer v. Eli Lilly & Co.
153 A.D.2d 210 (Appellate Division of the Supreme Court of New York, 1990)
Stevens v. McLouth Steel Products Corp.
446 N.W.2d 95 (Michigan Supreme Court, 1989)
Jolly v. Eli Lilly & Co.
751 P.2d 923 (California Supreme Court, 1988)
Lee v. Criterion Insurance
659 F. Supp. 813 (S.D. Georgia, 1987)
Korwek v. Hunt
646 F. Supp. 953 (S.D. New York, 1986)
Hanna Mining Co. v. InterNorth, Inc.
379 N.W.2d 663 (Court of Appeals of Minnesota, 1986)
Carlson v. Independent School District No. 283
370 N.W.2d 51 (Court of Appeals of Minnesota, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
355 N.W.2d 435, 1984 Minn. App. LEXIS 3557, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bartlett-v-miller-schroeder-municipal-inc-minnctapp-1984.