Bartlett v. Browning-Ferris Industries

683 So. 2d 1319, 1996 WL 638195
CourtLouisiana Court of Appeal
DecidedNovember 6, 1996
Docket96-218
StatusPublished
Cited by15 cases

This text of 683 So. 2d 1319 (Bartlett v. Browning-Ferris Industries) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bartlett v. Browning-Ferris Industries, 683 So. 2d 1319, 1996 WL 638195 (La. Ct. App. 1996).

Opinion

683 So.2d 1319 (1996)

J.W. BARTLETT, et al. Plaintiffs-Appellants,
v.
BROWNING-FERRIS INDUSTRIES, CHEMICAL SERVICES, INC., et al., Defendants-Appellees.

No. 96-218.

Court of Appeal of Louisiana, Third Circuit.

November 6, 1996.
Rehearing Denied January 2, 1997.

*1320 Leonard Knapp, Jr., Raleigh Newman, Donald Wayne McKnight, Lake Charles, for J.W. Bartlett, et al.

Michael A. Chernekoff, Robert M. Contois, Jr., Thomas Michael Nosewicz, New Orleans, John B. Scofield, John Richard Pohorelsky, Lake Charles, for Browning-Ferris Industries and Chemical Services, Inc.

Before DOUCET, C.J., and SAUNDERS and AMY, JJ.

DOUCET, Chief Judge.

The plaintiffs appeal a jury verdict denying their claim for damages allegedly resulting from the negligent operation of a hazardous waste disposal facility in the Willow Springs community near Lake Charles, Louisiana in Calcasieu Parish.

In the mid 1950s, Walter Elkins, Sr. began hauling oil field and industrial waste under the name of Mud Movers, Inc. In 1968, he decided that he needed a disposal site for the waste. He entered a 99-year lease for a site at the Willow Springs community in Calcasieu Parish. The lessors were aware of the type of waste to be dumped at the site. At that time, the property had on it ponds, including a reserve pit, and mud pit and a freshwater pit, remaining from an oil well drilled there at some time previously. After leasing the property, Mud Movers dug more ponds. The ponds were unlined and no testing was done to determine soil permeability. These open ponds were used for the disposal and/or storage of hazardous waste. In 1972, all the stock in Mud Movers was bought by a subsidiary of Browning-Ferris Industries, Inc. (BFI). That subsidiary later merged with Browning-Ferris Industries Chemical Services, Inc. (BFI-CSI). In the late 70s, a deep injection well was put into operation at the site. Waste was disposed of by injecting it into the well. Shortly after that, the operators began to develop a secure landfill for disposal of solids and sludges. By 1980, several older ponds had been closed and a receiving pond, an equalization pond and several mixing pits were in use. The receiving pond and equalization pond were clay lined. The mixing pits were unlined. Use of the mixing pits was discontinued in 1983. In 1984, CECOS International, Inc. (CECOS) began operating the site. By 1988, all waste coming onto the site was put into a tank system. In 1990, the operators of the site to began to phase out the waste disposal facilities at the site. After completion of the plan, all that will remain will be a tank farm system and the deep injection well.

In 1979, the state began regulating the transportation and disposal of hazardous waste. At that time, anyone engaging in those activities had to notify the state of their activities, so that the operation could be granted interim status. Interim status allowed them to continue to operate while undergoing permitting. The notification included the identity of the operator of the facility, the location of the site, what types of waste were being disposed of and the methods of disposal. The state received a notification concerning the Willow Springs site in October 1979. It stated that the site was doing chemical treatment of waste, land filling and injection into a well. It was the state's policy to inspect the site to verify the information in the notification. In February 1980, the Willow Springs facility submitted a Part I application for a hazardous waste disposal permit. Part II was submitted later in 1980. In May 1980, the federal government, through the Environmental Protection Agency (EPA), promulgated regulations concerning hazardous waste. The EPA regulations required that they be notified of the existence of disposal sites by November 1980. The EPA regulations also required submission on a permit application much like that submitted to the state. The permitting process continued over a number of years, during which time the Willow Springs site continued operating under interim status. In approximately 1980, a group of local residents formed a *1321 citizens' committee after becoming concerned about the possibility that emissions or releases from the Willow Springs site into the air and ground water could be causing damage to the local environment and the health of the residents of the area. Because of citizen complaints regarding odors, the state conducted air monitoring at the site and in the area. The citizens' committee asked the state to stay the permitting process while a study of the situation was done. The state provided some funding for the study. The permitting process for the Willow Springs facility was delayed for two years. Changes in regulations during that time required a complete rewriting and resubmission of the permit application in 1984. A permit was issued in 1988. The site operators appealed certain requirements of the permit felt to be redundant. A final permit was issued in December 1991.

In 1980, a number area residents, among them the appellants herein, sued for injunctive relief and for damages against a number of defendants believed to have been involved in the operation of the Willow Springs waste site, asking that hazardous waste disposal activities at the site be enjoined and for damages sustained because of the negligent operation of the site. After many amendments and extensive pretrial proceedings, the case came to trial with J.W. Bartlett and his wife, Roselma Bartlett and Gentry Vincent as plaintiffs and, as defendants, BFI, BFI-CSI, CECOS, and Walter Elkins, Jr., a former manager of the site.

After more than six weeks of trial and three days of deliberation, the jury returned a verdict in response to jury interrogatories finding that:

1. None of the defendants were negligent in their operation of the facility;

2. The operation of the site was a nuisance or an abuse of right within the legal meaning of those terms; and,

3. The plaintiffs sustained no damages arising out of the operation of the facility. The plaintiffs appeal.

ULTRAHAZARDOUS ACTIVITY

We will first consider plaintiffs' allegations regarding ultrahazardous activity. Plaintiffs allege that the trial court erred in failing to grant their motion for directed verdict seeking to have the defendants, BFI-CSI and CECOS found absolutely liable due to their engagement in an ultrahazardous activity. Plaintiffs further allege that the trial court erred in failing to instruct the jury regarding the law regarding liability for ultrahazardous activities and in failing to submit to the jury an interrogatory regarding ultrahazardous activity.

Louisiana courts have imposed absolute liability, i.e. liability without proof of negligence or fault, when harm results from the risks inherent in the nature of certain activities that can cause injury even when conducted with the greatest prudence and care. Such activities have included pile driving, storage of toxic gas, blasting with explosives, and crop dusting with airplanes. Ultrahazardous activities are determined as a matter of policy, after a balancing of claims and interests, a weighing of the risk and the gravity of harm, and the consideration of the individual and societal rights and obligations. Langlois v. Allied Chemical Corporation, 258 La. 1067, 249 So.2d 133 (1971).
The Louisiana Supreme Court has noted, however, that ultrahazardous activities involve an actor who is the sole cause of the damage and a victim who seldom has the ability to protect himself. Kent v. Gulf States Utilities Co., [418 So.2d 493 (La. 1982)]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Aertker v. Dresser L L C
W.D. Louisiana, 2022
Alexander v. Dresser L L C
W.D. Louisiana, 2022
Epperson v. Dresser L L C
W.D. Louisiana, 2022
Barrett v. Dresser L L C
W.D. Louisiana, 2021
Board of Commissioners v. Tennessee Gas Pipeline Co.
88 F. Supp. 3d 615 (E.D. Louisiana, 2015)
Alford v. Chevron U.S.A. Inc.
13 F. Supp. 3d 581 (E.D. Louisiana, 2014)
Johnson v. Orleans Parish School Board
938 So. 2d 219 (Louisiana Court of Appeal, 2006)
Conoco Inc. v. Halter-Calcasieu LLC
865 So. 2d 813 (Louisiana Court of Appeal, 2003)
Brown v. Olin Chemical Corp.
231 F.3d 197 (Fifth Circuit, 2000)
Bartlett v. BROWNING-FERRIS INDUS. CHEM. SERVICES, INC.
759 So. 2d 755 (Supreme Court of Louisiana, 1999)
Bartlett v. BROWNING-FERRIS INDUSTRIES
726 So. 2d 414 (Louisiana Court of Appeal, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
683 So. 2d 1319, 1996 WL 638195, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bartlett-v-browning-ferris-industries-lactapp-1996.