Barrus Construction Co. v. North Carolina Department of Transportation

324 S.E.2d 1, 71 N.C. App. 700, 1984 N.C. App. LEXIS 3971
CourtCourt of Appeals of North Carolina
DecidedDecember 18, 1984
DocketNo. 8411SC195
StatusPublished
Cited by2 cases

This text of 324 S.E.2d 1 (Barrus Construction Co. v. North Carolina Department of Transportation) is published on Counsel Stack Legal Research, covering Court of Appeals of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Barrus Construction Co. v. North Carolina Department of Transportation, 324 S.E.2d 1, 71 N.C. App. 700, 1984 N.C. App. LEXIS 3971 (N.C. Ct. App. 1984).

Opinion

WELLS, Judge.

We address first the DOT’s cross assignment of error that service of process was not timely and that the court erred in denying its motion to dismiss. The state has consented to suit on highway contract claims. N.C. Gen. Stat. § 136-29 (1981 and Cum. Supp. 1983). Such a suit is timely filed if instituted by filing of complaint and issuance of summons within six months after the final decision of the State Highway Administrator denying the claim. Id. Plaintiff filed its complaint, and summons issued, within the time set by statute. However, the summons was not properly served on the DOT’s registered process agent or the Attorney General as required by N.C. Gen. Stat. § 1A-1, Rule 4(j)(4) of the Rules of Civil Procedure (1983). After the six-month period had expired, but only 30 days after issuance of the original summons, the DOT moved to dismiss. Five days later, and 35 days after issuance of the original summons, plaintiff obtained an alias or pluries summons which was properly served in due time on the DOT. The trial court ruled that the alias summons continued the action and denied the DOT’s motion. We affirm that ruling.

G.S. § 136-29 only requires institution of the civil action, not service of process, within six months. N.C. Gen. Stat. § 1A-1, Rule 4(d) of the Rules of Civil Procedure (1983) provides that a civil action may be continued in existence against “any defendant” (emphasis added) by suing out alias summons within 90 days of the last preceding summons. No special attention to this rule appears for suits against the state, nor does this civil action appear to be any different from other civil actions. The state, once it has con[704]*704sented to suit, occupies the same position as any other litigant. Smith v. State, 289 N.C. 303, 222 S.E. 2d 412 (1976). There is no indication that the original summons designated the wrong defendant, only that it was incorrectly served. Compare Roshelli v. Sperry, 57 N.C. App. 305, 291 S.E. 2d 355 (1982) (correcting summons to name correct defendant institution of new action). We therefore hold that although the first service was of no effect, Stone v. Hicks, 45 N.C. App. 66, 262 S.E. 2d 318 (1980), plaintiff timely continued its action in existence and dismissal was improper. Rule 4(d); Williams v. Bray, 273 N.C. 198, 159 S.E. 2d 556 (1968); see also Consolidation Coal Co. v. Disabled Miners of So. W. Van, 442 F. 2d 1261 (4th Cir.), cert. denied, 404 U.S. 911 (1971) (error to dismiss where second, correct service timely). The court had jurisdiction and correctly denied the DOT’s motion.

Turning now to the merits, we note that summary judgment may be granted to the non-moving party in appropriate cases. A-S-P Associates v. City of Raleigh, 38 N.C. App. 271, 247 S.E. 2d 800 (1978), rev’d on other grounds, 298 N.C. 207, 258 S.E. 2d 444 (1979). Where dispute arises only as to questions of law, summary judgment is appropriate. Kessing v. Mortgage Corp., 278 N.C. 523, 180 S.E. 2d 823 (1971). Both parties concede in their briefs that there is no dispute concerning any material fact. “When a contract is in writing and free from any ambiguity which would require resort to extrinsic evidence, or the consideration of disputed fact, the intention of the parties is a question of law. The court determines the effect* of their agreement by declaring its legal meaning.” Lane v. Scarborough, 284 N.C. 407, 200 S.E. 2d 622 (1973); see also Salvation Army v. Welfare, 63 N.C. App. 156, 303 S.E. 2d 658 (1983), disc. rev. denied, 311 N.C. 306, 317 S.E. 2d 682 (1984); 4 S. Williston, Law of Contracts § 616 (3d ed. 1961); Restatement (Second) of Contracts § 200, Comment c. (1981). Since this contract is in writing, and the facts are undisputed, its legal effect was for the court and summary judgment was appropriate.

Plaintiffs position is simple: since the contract expressly provides that there will be a 180-day inspection period after the intermediate completion date, the DOT, in adjusting the intermediate date, was required to correspondingly adjust the final contract completion date to reflect the 180-day interval. Therefore, plaintiff and not the DOT was entitled to judgment. We disagree.

[705]*705First, the contract sets intermediate and final contract time separately, and sets liquidated damages separately for overruns of each date. Second, it separately provides that intermediate completion dates “may be extended on the same basis as [final] completion dates . . . .” Nowhere does the contract require that extensions to the intermediate date be matched exactly by extensions to the final date. Rather, it simply provides that such extensions may be made. Third, it provides that extensions of time or remittances of damages for delay shall be “only to the extent and in the proportion that such delays were caused by the conditions set forth in [the section describing good cause for which the DOT would grant extensions].” The contract thus clearly reflects an intent to allow the DOT discretion in adjusting extensions to avoid unfairness.

The undisputed facts show that even before its request for an extension, plaintiff had accepted unequal extensions of the intermediate and final dates. In fact, the original dates agreed upon were 166 days apart, although the DOT later adjusted the final contract date to reflect the proper interval as part of its response to plaintiffs original verified claim. Plaintiff then stipulated to separate groups of “authorized time extensions” for the two contract dates. Only one of the items appears as an extension to both dates. The major item of difference, a 90-day winter weather extension, was added only to the intermediate date in adherence to the terms of the contract, which provides that upon authorized extension beyond 15 December the 90 days is added automatically to the contract time. The final contract date, however, was not extended beyond 15 December and thus did not receive the 90-day extension. Plaintiff does not object to this discrepancy, insisting instead on the inflexibility of the 180-day interval.

It is apparent however from both the plaintiffs claim and the DOT’s answers to interrogatories that adjustments to contract time reflect in large part contract, and not actual, time. By the time plaintiff submitted its claim, it had already completed the work, subject only to possible correction of pavement markings. Plaintiff was already in breach under the terms of the contract; allowing extensions served only to reduce the amount of damages assessed, not to extend time to complete the work. Even accepting plaintiffs requested extensions in toto, substantial damages would still be due. The distinction between contract time and ac[706]*706tual time is crucial. We note that the DOT, in adjusting contract time, did correct the original mistake in setting the interval 166 days. Contract time thus properly allowed 180 days. The adjustments made, while generally reflecting actual delays, did not correspond exactly to work in the field as plaintiff contends.

The 90-day adjustment mentioned above is one example; plaintiff received it even though it is clear from the record that work continued during the period 15 December-16 March.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

C. W. Matthews Contracting Co. v. State
330 S.E.2d 630 (Court of Appeals of North Carolina, 1985)
CW MATTHEWS CONTRACTING CO., INC. v. State
330 S.E.2d 630 (Court of Appeals of North Carolina, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
324 S.E.2d 1, 71 N.C. App. 700, 1984 N.C. App. LEXIS 3971, Counsel Stack Legal Research, https://law.counselstack.com/opinion/barrus-construction-co-v-north-carolina-department-of-transportation-ncctapp-1984.