Barron Reed Construction v. 430, LLC

622 S.E.2d 83, 275 Ga. App. 884, 2005 Fulton County D. Rep. 3225, 2005 Ga. App. LEXIS 1131
CourtCourt of Appeals of Georgia
DecidedOctober 17, 2005
DocketA05A1966
StatusPublished
Cited by8 cases

This text of 622 S.E.2d 83 (Barron Reed Construction v. 430, LLC) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Barron Reed Construction v. 430, LLC, 622 S.E.2d 83, 275 Ga. App. 884, 2005 Fulton County D. Rep. 3225, 2005 Ga. App. LEXIS 1131 (Ga. Ct. App. 2005).

Opinion

BLACKBURN, Presiding Judge.

In this arbitrated construction dispute, Barron Reed Construction appeals the trial court’s confirmation of the arbitration award in favor of the owner, arguing that the agreement to arbitrate was unenforceable and that the arbitrator manifestly disregarded the *885 law. We hold that the construction agreement containing the arbitration clause was properly executed and that Barron Reed’s claims of “manifest disregard of the law” are nothing more than unreviewable factual issues. Accordingly, we affirm.

Barron Reed executed a paving contract to construct a new grocery store parking lot. The contract incorporated certain general conditions, which included an agreement to arbitrate. Dissatisfied with Barron Reed’s performance under the contract, the grocery store owner (a limited liability company named “430, LLC”) refused final payment and, asserting a claim against Barron Reed, instigated arbitration with the American Arbitration Association per the terms of the contract. In response, Barron Reed filed an action against the owner in superior court to recover monies unpaid under the contract and simultaneously moved to stay the arbitration. Admitting Barron Reed’s allegation that the parties had entered a binding contract, the owner in the superior court action alleged inadequate performance and again demanded arbitration.

In its argument to stay arbitration, Barron Reed now contended that the signature of the owner’s representative on the contract was unauthorized and that therefore the agreement to arbitrate was unenforceable. The court found otherwise, noting that Article 7.3 of the contract expressly provided that Jamie McCutchen (the person who signed the contract) was the owner’s designated representative. Thus, the court refused to stay the arbitration.

The arbitration proceeded and resulted in an award of $82,145.67 in favor of the owner. Based on the evidence, the arbitrator also found that McCutchen was duly authorized to execute the contract on behalf of the owner and that therefore the agreement to arbitrate was binding. When the owner sought to confirm the award, Barron Reed moved to vacate the award on the grounds that the agreement to arbitrate was not binding and that the arbitrator manifestly disregarded the law in his award. The court rejected Barron Reed’s arguments and confirmed the award. Barron Reed appeals this confirmation on the same grounds.

1. Barron Reed’s first two enumerations challenge the trial court’s ruling on the enforceability of the agreement to arbitrate, which in this case involves questions of law that we review de novo. See Deep Six, Inc. v. Abernathy 1 (questions of law are reviewed de novo). Barron Reed argues that McCutchen did not sign the agreement on behalf of 430, LLC, and that even if he did, no writing authorized McCutchen to sign the agreement. Under the latter argument, Barron Reed contends that absent written authority, *886 McCutchen lacked the power under the Equal Dignity Rule 2 to sign the agreement to arbitrate — which must be in writing 3 — on behalf of the owner. We reject these arguments.

Regarding the first argument, the first page of the contract provided that the contract was between 430, LLC as owner and Barron Reed as contractor. Article 7.3 expressly designated Mc-Cutchen as 430, LLC’s representative. Thus, McCutchen’s signature on the “Owner” line was clearly on behalf of 430, LLC.

Regarding the second argument, it is true that under OCGA § 10-6-2, the authority of an agent to execute an instrument required to be in writing must also be in writing. Turnipseed v. Jaje. 4 Barron Reed, however, is not the correct party to challenge McCutchen’s authority under this statute. This statute is designed to protect a principal from liability for the unauthorized actions of its agent; it is not designed for an opposing party in a contract to escape its obligations by challenging the authority of the other party’s representative. It would indeed be anomalous for a party — who admittedly has duly executed a contract — to be able to avoid its duties thereunder by claiming that the other party — who has admitted to the signing and to the validity of the contract and has fulfilled its obligations thereunder — was not bound to do so because its signing representative lacked a writing authorizing his signature. Whether the second party was bound by the contract would be an issue for that party to raise if it sought to avoid the contract; such would not be an issue for the first party to raise as a supposed defense to its own failure to fulfill its obligations. Thus, in cases where the statute is invoked, the invoking party is the principal who is challenging the authority of its own alleged representative. See, e.g., Turnipseed, supra at 322 (1); Lee v. Green Land Co. 5 Cf. Grange Mut. Cas. Co. v. Kay 6 (party to contract may not invoke incapacity of minor party so as to avoid first party’s contractual obligations). The burden is then on the other party to show that written authority. See Garden of Eden v. Eastern Sav. Bank 7 (“[o]ne seeking to hold the principal liable for the undertaking of his agent on a lease for over a year must show that the agent had written authority to act for the principal”).

Moreover, even if Barron Reed could raise this issue, and assuming a writing were required, then Barron Reed was charged with *887 notice that McCutchen’s authority to execute the contract was required by law to be in writing and was therefore under a duty to inquire and ascertain whether such written authority existed and what the limits of the authority were. 20/20 Vision Center v. Hudgens. 8 “[S]uch person is guilty of negligence in failing to make such an inquiry.” (Punctuation omitted.) Id. See Turnipseed, supra at 323 (2) (a). Barron Reed cannot take advantage of its own negligence and now claim that it is not bound by the contract.

Because the agreement to arbitrate was binding on Barron Reed, the trial court did not err in refusing to stay the arbitration.

2. Barron Reed’s remaining four enumerations of error would each require a review of the evidence presented to the arbitrator to determine whether the arbitrator manifestly disregarded the law.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Audrey Payton v. Theodore Jackson, Sheriff
Court of Appeals of Georgia, 2014
Payton v. Jackson
756 S.E.2d 555 (Court of Appeals of Georgia, 2014)
Garrett v. Southern Health Corp. of Ellijay, Inc.
739 S.E.2d 661 (Court of Appeals of Georgia, 2013)
Precision Planning, Inc. v. Richmark Communities, Inc.
679 S.E.2d 43 (Court of Appeals of Georgia, 2009)
ASSET ACCEPTANCE, LLC v. Wheeler
672 S.E.2d 493 (Court of Appeals of Georgia, 2009)
McGill Homes, Inc. v. Weaver
629 S.E.2d 535 (Court of Appeals of Georgia, 2006)
Malice v. Coloplast Corp.
629 S.E.2d 95 (Court of Appeals of Georgia, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
622 S.E.2d 83, 275 Ga. App. 884, 2005 Fulton County D. Rep. 3225, 2005 Ga. App. LEXIS 1131, Counsel Stack Legal Research, https://law.counselstack.com/opinion/barron-reed-construction-v-430-llc-gactapp-2005.